GS Breaks Ground on Donghae AIDC... Chairman Huh Taesoo: "Leap Forward as a Global Hub in the AI Era"
President Lee Attends as First GW-Scale AIDC Among Mega-Projects Breaks Ground
Construction Begins on 1.2 GW of 2.4 GW Total, with Facilities to Be Completed and Begin Operations in Phases by 2029
GS and Donghae City Form Co-Prosperity Council to Explore Ways to Grow Together with the Region
GS Group said on the 28th that it had held a groundbreaking ceremony for the Donghae GS Artificial Intelligence Data Center (AIDC) at the Bukpyeong 2nd General Industrial Complex in Donghae, Gangwon State, with President Lee Jae-myung in attendance, and had begun construction of a 1.2-GW AIDC.
The project is the first GW-scale AIDC included in the government’s “Three Mega-Projects for a Great Leap Forward for Korea” to break ground, about five months after the announcement.
In his welcoming remarks, GS Group Chairman Huh Taesoo said, “GS aims to build a world-class AI data center here and make it a starting point for Korea to emerge as a global hub in the AI era. Above all, through this investment, we will create jobs in the region, open up opportunities for local businesses, and help young people in the region dream of the future.”
GS Group is pursuing its 2.4-GW AIDC project in two phases of 1.2 GW each. The Donghae AIDC, which broke ground this time, is part of the first phase. The company plans to divide a site of about 80,000 pyeong at the Bukpyeong 2nd General Industrial Complex into three zones and build a 700-MW center, as well as develop a 500-MW center on an additional site.
The AIDC project that broke ground this time is targeted for completion and operation in 2029. The first 100-MW center is scheduled for completion in 2028, followed by the remaining centers in succession. GS plans to expand the business beyond Donghae by using group-owned land and other sites suitable for data center construction, with Donghae as its base.
The ceremony was attended by key group executives, including Chairman Huh, GS Vice Chairman Hong Sunji, GS Engineering & Construction CEO Yoon Hong Huh, GS AI Infra CEO Do Hyunsu, and GS E&R CEO Hwang Byungso.
After the official ceremony, President Lee and Chairman Huh visited exhibition booths set up at the site. LS ELECTRIC showcased power supply equipment for data centers, while LG Electronics presented cooling solutions.
Groundbreaking five months after mega-project announcement
Seeking ways to grow together with the region
In June, GS established GS AI Infra, a dedicated data center subsidiary, and has since been preparing the project by bringing together the group’s expertise in power generation and energy, as well as GS Engineering & Construction’s design and construction capabilities. The site was selected based on its large area, power supply infrastructure, and transport accessibility.
After signing a business agreement with Gangwon State and Donghae City in July to develop the data center, the company underwent various reviews and obtained permits, including a power system impact assessment and a building permit. It also explained the project plan to the Donghae City Council and gathered residents’ opinions on construction through public information sessions.
The first-phase investment plan, at 1.2 GW, is valued at about 15 trillion won, while the investment required to build the 2.4-GW facility is estimated at about 30 trillion won. Including the cost of graphics processing units (GPUs) and memory, the total project size is expected to reach as much as 120 trillion won.
GS Group has formed a co-prosperity development council with Donghae City to explore ways for AIDC construction and operations to expand local employment and boost the economy. GS estimates that the 1.2-GW project will require a cumulative total of about 70,000 workers during construction and about 1,000 direct and indirect workers during operations. Once the data center is operational, partner companies and IT service providers are also expected to establish a presence in Donghae.
Meanwhile, GS plans to use the council to assess the impact of data center construction and operations on the environment and residents’ daily lives, and to incorporate local feedback. Previously, the underground transmission line connecting Bukpyeong Substation to the data center site was designed to bypass the area around the Bukpyeong Five-Day Market in response to residents’ feedback.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
A GS official said, “We want this project to be more than simply building an AI data center and creating temporary jobs. We hope to make it a genuine opportunity to build Donghae’s future together.”