AI Data Center Matching One Nuclear Plant's Capacity... 15 Trillion Won Project Breaks Ground in Donghae
First Groundbreaking for 1.2-GW Mega-Project... Operations Targeted for 2029
Final Scale to Reach 2.4 GW... South Korea Joins Race to Build the World's Largest AI Infrastructure
Government to Raise Domestic Solution Localization Rate, Now at 10%, and Foster Export Industry
A massive artificial intelligence (AI) data center capable of receiving 1.2 gigawatts (GW) of power will be built in Donghae, Gangwon Province. That is more than 20% above the generating capacity of a 1,000-megawatt (MW) Korean Standard Nuclear Power Plant. The estimated investment for the first phase alone amounts to 15 trillion won, while the final target of 2.4 GW would rank among the largest facilities in the world. South Korea has now joined in earnest the race to build gigawatt-scale AI infrastructure, a competition led by major countries including the United States.
On November 28, the Ministry of Science and ICT held a groundbreaking ceremony for the Donghae GS AI Data Center at the Bukpyeong 2nd General Industrial Complex in Donghae, Gangwon Province. This is the first gigawatt-scale AI data center among the government's mega-projects to begin construction.
An artist's rendering of the GS artificial intelligence (AI) data center to be built in the Bukpyeong No. 2 General Industrial Complex in Donghae, Gangwon Province. GS plans to build a first-phase facility with a capacity of 1.2 gigawatts (GW) by 2029. Provided by Donghae City.
View original imageThe project is the first phase of GS's plan to build a 2.4-GW AI data center in Donghae, announced at the "National Briefing on Three Major Mega-Projects" on June 29. The goal is to complete the 1.2-GW data center in stages starting in 2028, with construction finished and operations beginning in 2029.
According to the International Energy Agency (IEA), a typical data center has a power capacity of 10 to 25 MW. The first phase of the Donghae AI data center will be 48 to 120 times that size, and 12 times the size of a 100-MW ultra-large AI data center. Its capacity will exceed the generating capacity of a 1,000-MW Korean Standard Nuclear Power Plant.
In a blueprint for South Korea's economy released in October 2025, OpenAI cited its "Stargate" project, a massive AI infrastructure initiative, as an example of a project requiring a power supply of more than 1.2 GW. Securing gigawatt-scale data centers is emerging as a key infrastructure priority in the global AI race.
In a disclosure in September, GS said it planned to invest about 15 trillion won in the first phase of the project. The company selected the Bukpyeong 2nd General Industrial Complex as a suitable site for a large-scale AI data center, citing the abundant power-generation capacity along Gangwon Province's east coast and the potential to introduce a seawater-based cooling system in the future.
GS also unveiled its data center development plan and measures to benefit the local community. During construction, the company plans to fill a certain proportion or more of security, general service, and skilled technical jobs with local workers. After the facility is completed, it expects demand for direct and indirect employment to range from several hundred to more than 1,000 people.
GS will actively hire local specialists for operations, including server, network, security, and facility management, and will also work to establish specialized data center training programs in partnership with local universities. The company plans to support local young people in building careers in the area by linking on-site training and mentoring with job opportunities.
Domestic Solutions Account for 10% of AI Data Center Market; Industry to Be Fostered as a National Strategic Sector
The government is also accelerating efforts to develop industries across the AI data center supply chain, building on the large-scale project. Its strategy is to go beyond data center construction, strengthen the competitiveness of materials, components, equipment, and operational solutions, and foster them as a new export industry.
On November 20, the Ministry of Science and ICT issued a legislative notice on subordinate regulations for the Special Act on the Promotion of the Artificial Intelligence Data Center Industry, which takes effect in March 2027. Key provisions include establishing a one-stop permitting system, setting 50 MW as the threshold for exemptions from power system impact assessments for AI data centers outside the Seoul metropolitan area, easing facility installation requirements, and providing a legal basis for designating special zones for AI data centers. The ministry will hold a public hearing on December 9 and collect feedback through December 30.
In 2027, the government will also pursue the creation of clusters that include research and development (R&D) and large-scale demonstration test beds to foster industries across the AI data center supply chain. It plans to increase the domestic content rate of AI data center solutions, currently at around 10%, and build an industrial ecosystem linking "localization, demonstration, and exports." In the first half of 2027, it will invite applications from organizations and companies to conduct R&D projects and from regions seeking to host clusters.
Through the "AIDC Alliance," which brings together the central and local governments, data center operators, and materials, components, and equipment companies, the government will incorporate industry feedback into policy and work to develop AI data centers into a national strategic industry.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
Bae Kyunghoon, Deputy Prime Minister and Minister of Science and ICT, said, "AI data centers are essential infrastructure for the AI era and for South Korea to become a leading AI nation. We will continue working closely with GS, relevant ministries, Gangwon Province, and Donghae City to ensure that the Donghae GS AI Data Center is built as planned and becomes a leading example of a mega-project that benefits the local community."
© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.