Mirae Asset Securities AI Infrastructure Investment Report
Investment bottleneck shifts from GPU supply to "financing"
"AIDC financing crunch unlikely to spread to financial markets"

Financing is emerging as a new bottleneck in the investment cycle for artificial intelligence (AI) infrastructure. Concerns about whether companies can stay afloat until they begin generating revenue are spreading to financial markets. However, Mirae Asset Securities said that 2027 will be a year in which the market separates the winners from the losers among AI infrastructure companies, and that these concerns are unlikely to materialize.


AI Investment: Can Companies Hold Out? ... "Next Year Will Separate the Winners from the Losers" [Weekend Money] View original image

On Nov. 29, Mirae Asset Securities researchers Kwon Youngbae and Kim Sumin said in a report that the bottleneck in AI infrastructure investment is shifting from the supply of graphics processing units (GPUs) to financing. According to the Financial Stability Report released by the Federal Reserve, debt issuance related to advanced computing rose from $130 billion in 2023 to more than $680 billion from January through October 2026. The share of advanced-computing-related industries in nonfinancial investment-grade corporate bond issuance also rose from less than 6% to 31%.


During the construction of AI data centers, cash is spent on GPU orders, power connections, installation and inspection, while revenue begins to come in only after services launch. Hyperscalers that also operate established businesses in areas such as cloud computing, advertising and software have stable cash flows. For neocloud companies, whose main business is renting computing capacity, however, the time lag between investment and revenue remains a funding gap (capital expenditures minus operating cash flow). Amazon, Meta, Google and Microsoft are among the leading hyperscalers, while CoreWeave is one of the major neocloud companies.


According to the report, based on market expectations for 2027, the funding gap is $122 billion for the four hyperscalers—Amazon, Meta, Google and Microsoft—$26.6 billion for Oracle, $140.4 billion for xAI and $60.9 billion for the three neocloud companies. Measured not in absolute dollar amounts but as a share of capital expenditures (CAPEX) covered by external financing, the three neocloud companies are at 60%, far higher than xAI at 53%, Oracle at 28% and the four hyperscalers at 11%.


CoreWeave, a leading neocloud company, generated $5.6 billion in operating cash flow from January through September 2026, equivalent to just 23% of its investing cash flow of -$24.7 billion. It covered the shortfall with $21.3 billion in cash from financing activities, while its interest expense in the third quarter was more than twice its adjusted operating profit.


Mirae Asset Securities nevertheless judged that the immediate risk of insolvency is not high. "As of September, liquidity stood at $9.8 billion and the order backlog reached $132.5 billion," the firm said. "Management expects to receive about $9 billion in customer prepayments over the next three months, so CoreWeave's risk ultimately comes down to how it allocates funds between repayment and new investment."


Delays in data center construction put pressure on the funding gap. Of the 16 GW of capacity scheduled to come online in the United States in 2026, only about 5 GW is actually under construction. Last year, 26% of planned construction projects were also delayed. Assuming that 30% to 40% of data center investment is delayed by about three to six months, approximately $305 billion of global AI capital expenditure in 2027 could be tied up without generating revenue. However, the longer supply is delayed, the more profitable operational capacity becomes.


AI Investment: Can Companies Hold Out? ... "Next Year Will Separate the Winners from the Losers" [Weekend Money] View original image

The report said AI data centers are highly profitable, so the funding gap is not a problem as long as they are operational. Based on an investment cost of $37.9 billion per 1 GW, the simple payback period is 2.5 years for Anthropic and Nscale under six-year long-term contracts, 1.8 years for IREN under a three-year contract, and 1 to 1.3 years for CoreWeave under short-term contracts of three to six months. Mirae Asset Securities said, "Even if project delays push back the start of operations by six to seven months, the payback period can be brought forward by 12 to 30 months, depending on the monetization model or computing prices." It added, "According to our analysis, even a short-term contract of three to six months (18 months) delayed by six months can recoup the investment about 12 months earlier than a long-term contract without delays (30 months)."


The report also said that difficulties some neocloud companies face in raising funds would not derail the AI infrastructure investment cycle. Hyperscalers and chipmakers are expected to absorb projects that struggle to secure financing through methods such as customer prepayments, credit enhancements, project acquisitions, joint ventures (JVs) and special purpose vehicles (SPVs). For example, Google acquired Crusoe's Wyoming site after the company failed to secure a customer and invested $17 billion directly in it. At the end of September 2026, the four hyperscalers had $381 billion in available liquidity—cash and securities minus their financing needs for 2027—equivalent to 3.8 times the three neocloud companies' capital expenditure for 2027. Mirae Asset Securities said, "Even if neocloud companies face a financing crunch, the risk is likely to remain with the neocloud companies."


Mirae Asset Securities forecast that 2027 would be a year in which the market separates the winners from the losers among AI infrastructure companies. "Even if some neocloud companies struggle to raise funds, their projects will not disappear; they will simply be pushed back," the firm said. "2027 will be the year that distinguishes companies able to withstand that time lag from those that cannot, and identifies high-quality projects."



The firm also considered the likelihood that a financing crunch among AI infrastructure companies would spread to the broader financial market to be low, taking into account hyperscalers' financial resources and their exposure to the financial sector. Banks' direct exposure to data centers is less than 2% of total U.S. loans and less than 1.2% of eurozone corporate loan commitments, while AI-related investments by U.S. life insurers account for 2.1% of their bond holdings. Mirae Asset Securities said, "Profitability per gigawatt at AI data centers significantly exceeds required returns, and the combination of various financing techniques could sustain the flow of capital from long-term investors."