DS Investment & Securities: "Overweight Construction; GS E&C Is Top Pick"

If nuclear power plant order expectations drove construction stocks higher this year, data center construction starts are likely to be the catalyst next year. DS Investment & Securities named GS E&C as the contractor with the highest visibility for data center orders.


Image generated by Google Gemini

Image generated by Google Gemini

View original image

In a recent report, DS Investment & Securities researcher Kang Taeho said, "In the first half of last year, year-to-date returns in the construction sector rose 648% for Daewoo Engineering & Construction and 201% for Hyundai Engineering & Construction, as expectations for large-scale nuclear power plant orders had a significant impact on stock prices." He added, "Next year, rather than focusing on vague expectations of accelerated business activity in the construction sector, investors should focus on companies actually building up order backlogs that can lift earnings estimates for 2027 and 2028."


Data center orders are expected to be key to the construction sector's performance next year. Construction periods are short, at two to three years, so orders quickly translate into revenue.


Another point to watch is that the shift to AI data centers is increasing the share of mechanical, electrical and plumbing (MEP) work, driving up construction costs per megawatt (MW). Kang said, "For data centers ordered since 2022, the order value per MW based on IT load—the amount of electricity used by IT equipment—has mostly exceeded KRW 10 billion. The average value, including new orders from 2025 and 2026, has risen to around KRW 13 billion." He added, "Given the expansion of AI data centers, the average value is expected to rise to around KRW 16 billion."


Fewer than 10 domestic contractors have the technical capabilities required to build data centers, so their bargaining power is expected to remain intact even as unit prices rise.


The government is also pursuing the expansion of the data center market. In June, it announced a goal of building 18.4 GW of AI data centers by 2035 through three mega projects. All of the 8.4 GW planned in Phase 1, including projects in Ulsan, Donghae and Sejong, will be outside the Seoul metropolitan area, with construction targeted to begin in the first half of 2028.


Kang said, "GS Donghae AI Data Center received a construction permit for Phase 1 (100 MW) last month and has moved on to the construction stage. Applying construction costs of KRW 10 billion to KRW 16 billion per MW of IT load to companies' announced plans and the government's policy targets, the domestic data center construction market is estimated to be worth up to KRW 196 trillion, or KRW 15 trillion to KRW 19 trillion annually."


Based on these findings, DS Investment & Securities recommended increasing exposure to the construction sector and named GS E&C as its top pick.


Kang said, "Including its subsidiary GS Xi C&A, GS E&C has the largest portfolio of data center projects in Korea, with 22 references. The GS Group's GS Donghae AI Data Center has also received a construction permit for Phase 1, with construction set to begin on November 28." He added, "GS E&C is expected to secure around KRW 2.5 trillion in data center orders annually from 2027 to 2029. Applying a 9% operating profit margin (OPM), that would amount to about 59% of next year's operating profit, giving the company the greatest earnings leverage among the companies covered by the brokerage."



He added, "The lack of firm order commitments and the timeline for securing tenants are risk factors. However, we believe order visibility is the highest in the sector, given that permitting is progressing fastest among the three mega projects."