The Daegu-Gyeongbuk New Airport construction project has been delayed by difficulties securing funding. Against this backdrop, Uiseong and Gunwi counties in Gyeongsangbuk-do, the areas set to host the relocated airport, jointly asked the National Assembly to develop measures to get the project back on track.
Call for revision of special law and funding; residents' losses total 3.1 billion won, with pre-compensation measures also proposed [Photo=Uiseong County]
View original imageUiseong County said Choi Yucheol, head of Uiseong County, and the head of Gunwi County visited the National Assembly on November 25, met with Jin Seongjun, chair of the National Assembly's National Defense Committee, and Assemblyman Joo Hoyoung, and explained key issues related to the new airport project. They also requested support to expedite its implementation.
The two county heads expressed concern that prolonged discussions on amending the special act to secure funding for the military airport relocation project could also delay construction of the civilian airport. They stressed that the foundation for moving ahead with the new airport project must be secured by passing the amendment to the special act promptly and establishing stable funding measures.
They also called for measures to address restrictions on property rights and other harm to residents in the areas set to be relocated.
Since the site for relocation was selected, restrictions on land transactions and development have remained in place, making it difficult for residents to repair their homes and improve or replace the varieties of fruit trees in their orchards.
As of now, 281 cases of harm to residents have been identified, totaling 3.11 billion won: 222 housing-related cases amounting to 1.21 billion won and 59 orchard-related cases amounting to 1.9 billion won.
Urges Revision of Special Act and Funding Measures
Calls for Advance Compensation for Residents in Incorporated Areas
281 Cases of Damage to Residents, Worth 3.11 Billion Won
Demands Measures as Property Rights Restrictions Drag On
[Photo by Uiseong County]
The two counties accordingly called for the prompt passage of the amendment to the special act related to the new airport, the development of diverse funding measures, including the designation of a joint project operator, and advance compensation for residents in areas to be incorporated into the project in preparation for prolonged delays.
The Daegu-Gyeongbuk New Airport is being promoted as a key project to expand the region's transportation and industrial infrastructure and support balanced national development. However, with funding for the project delayed, restrictions on property rights and disruptions to daily life for residents in the relocation areas could continue for an extended period. Calls are growing for the project to move forward while measures to address harm to residents are developed at the same time.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
Uiseong County plans to visit the Ministry of National Defense and the National Assembly with Gunwi County again on November 27 to make additional requests to ensure the new airport project proceeds as planned.
© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.