"One Floor a Day, Like Clockwork"... 'High-Rise Modular Housing' Cuts Construction Time by 20% [Modular Housing at the Forefront of Fast-Track Construction] (1)
A look at the modular housing site in Uiwang Chopyeong
Construction time per floor cut from 13 days to 1
Also reduces the risk of on-site workers falling
The construction site of Korea Land and Housing Corporation (LH)'s Uiwang Chopyeong A-4 Block in Uiwang, Gyeonggi Province, visited on Nov. 25. Work was underway to hoist large modules prefabricated at a factory by crane and stack them in place to build a 22-story high-rise modular housing complex using a concrete construction method for the first time in South Korea. It took just over 20 minutes to set one module in place.
Modules being installed at the Korea Land and Housing Corporation (LH) Uiwang Chopyeong A-4 Block construction site in Uiwang, Gyeonggi Province. NRB.
View original imageAmid growing concerns over a housing supply shortage in the Seoul metropolitan area, high-rise modular construction, which can shorten construction schedules, is emerging as a key alternative. After starting construction on modular housing projects in Chopyeong, Uiwang, Gyeonggi Province (381 units), and Sejong (450 units) last year, LH began work this year on 150 senior welfare housing units in Doyang, Goheung, South Jeolla Province. Construction will also begin in Wando, South Jeolla Province, next month. Next year, Gyeonggi Housing & Urban Development Corporation (GH) plans to start construction on 400 units in Gyosan, Hanam, while LH is aiming to begin work on a total of more than 2,300 units in Geomo, Siheung; Songu, Pocheon; Wangsuk, Namyangju; and Changneung, Goyang.
According to the Korea Research Institute for Construction Policy, the domestic modular construction market is projected to grow from KRW 120 billion in 2020 to KRW 1.75 trillion in 2022, and to as much as KRW 4.4 trillion by 2030.
On Nov. 16, Minister of Land, Infrastructure and Transport Hong Ji-seon visited a construction site for modular integrated public rental housing in Sejong's 5-1 Living Area to review the project's progress. Hong said, "Modular construction is drawing attention as a key alternative that can shift the construction industry from labor-intensive work to technology-driven production and significantly shorten construction periods. If you submit suggestions on what is needed to develop the modular housing market, we will review them promptly and reflect them in policy."
Modular housing construction sites are said to be able to shorten construction schedules by 20-30% compared with conventional methods. At the Uiwang Chopyeong site, workers had reached the 12th floor, where modules were being stacked, and had brought in fully packaged bathroom fixtures through a structure whose exterior work, including installation of windows, was already complete. The structure was ready for interior work, such as airtight and waterproof treatment and wallpapering, without any further exterior work. Because the upper-floor residential modules can be manufactured at a factory while foundation and basement civil engineering work is underway, the overall construction period can be reduced significantly.
Jeong Yunyoung, site manager for modular construction company NRB, explained, "Conventional reinforced concrete (RC) construction takes about 13 days to complete one floor, but modular construction can stack one floor a day, shortening the overall construction schedule by 20-30%."
Another advantage of modular design is that it can be applied as is to other project sites. Applying the standard modular design used at the Uiwang site to other projects can greatly shorten the design and permitting period, which typically takes one to two years. Jeong said, "Because the modules are manufactured in a roofed factory, they are less affected by the weather. Bringing them to the site with the exterior work already completed also reduces the risk of workers falling. As technology and experience accumulate, we should be able to gradually reduce the number of workers required."
At the construction site of Korea Land and Housing Corporation (LH)’s Uiwang Chopyeong A-4 Block in Uiwang, Gyeonggi Province, NRB site manager Jeong Yunyoung points to a modular joint as he explains it. Photo by Sim Seonga.
View original imageThe past prejudice that "modular homes are flimsy, like container houses" is also fading. Gyeonggi Happy House in Yeongdeok, Yongin, developed by GH and South Korea's first 13-story high-rise modular housing complex, received a high score of 4.33 out of 5 from newlywed households in a housing performance satisfaction survey conducted after residents moved in by the Housing Research Institute of the Korean Housing Association. Choi Seong-muk, manager of the Happy House complex, said, "Some residents have even said they didn't know it was a modular home. There's no difference from a conventional building."
Hanam Gyosan A1 Block, part of the third-generation new town development and scheduled to break ground in the first half of 2027, is expected to usher in a new era of next-generation high-rise modular housing. It will be South Korea's tallest modular housing project, with 25 floors above ground and 400 units, combining high-rise construction with large-scale development.
Hanam Gyosan A1 Block will upgrade even the core sections of its stairwells and elevator shafts, where reliance on cast-in-place reinforced concrete (RC) has caused construction bottlenecks, by using a modular precast concrete (PC) core system. It will also eliminate the double-floor structure to secure a ceiling height of 2.4 meters, on par with conventional apartments, and expand its unit mix to include family-sized homes, such as those with 59 square meters of private living space.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
However, challenges remain before modular construction can be widely commercialized. Concrete modules are heavier than conventional steel-frame structures, resulting in higher transportation costs. As the industry is still in its early stages and has yet to achieve economies of scale, the key will be to lower overall construction costs, which are currently higher than those of conventional methods, and improve cost-effectiveness. A GH official said, "In coordination with a research and development demonstration project by the Ministry of Land, Infrastructure and Transport, we plan to establish standard floor plans and a standard model for modular PC components. We also aim to mass-produce modules of the same specifications at factories and maximize the benefits of faster supply by reducing construction costs and shortening construction schedules."
© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.