Corporation refuses to assume private contract and insists on open competition
Sets appropriate service fee at 56 billion won after rigorous review
Sends third letter urging private participants to secure financing
May take action under agreement if land sale contract is not signed

Seongnam Urban Development Corporation in Gyeonggi Province has reaffirmed its firm stance on two key issues in the Baekhyeon MICE urban development project: the design services contract and project financing. The corporation said it would uphold the principle of open competition and require private participants to fulfill their financing obligations.


On Nov. 26, the corporation issued an official statement saying, "There is no legal basis whatsoever for the project financing vehicle (PFV) to assume a design services contract that a private participant signed with a specific company before the establishment of Seongnam MICE PFV." It said it would be inappropriate for a project company with public investment to take on an unverified private contract as is.

Aerial rendering of Baekhyeon MICE. Provided by Seongnam Urban Development Corporation.

Aerial rendering of Baekhyeon MICE. Provided by Seongnam Urban Development Corporation.

View original image

"No direct award for core services worth tens of billions of won"

The two sides have sharply differing views on the scale of the design services contract at issue. According to the corporation, the private participant initially proposed a design services fee of 76 billion won, while the corporation's review found that an appropriate fee would be about 56 billion won. The private-sector side later lowered the amount and resubmitted a contract proposal worth 45 billion won, but it too failed to pass the PFV board and was rejected.


The corporation said that, regardless of the amount, awarding a core services contract worth tens of billions of won to a specific company without a competitive process would directly violate the principles of fairness and transparency.


The corporation emphasized, "Open competitive bidding is not intended to exclude the incumbent company; it is the minimum safeguard needed to ensure that all companies have a fair opportunity to participate."


Apparently mindful of the past controversy surrounding the Pangyo Daejang urban development project, it added, "We are moving forward with the project while rigorously implementing safeguards to ensure public benefits, including capping private participants' profits at 6%."

Urges private participants to fulfill financing obligations

The corporation's position is that, under the project agreement, securing financing for the project is the responsibility of the private participants.


The corporation said it understands that the PFV has not yet secured funds to pay the remaining balance on existing service contracts or the deposit for the architectural design services contract. It stressed that project funds, including the land purchase price, must be secured on time for the next steps to proceed.


The corporation had already sent the private participant two official letters urging it to fulfill its financing obligations. On Nov. 25, it sent a third letter, issuing what amounted to a final warning. It emphasized that if it reasonably determines that the private participant cannot carry out the financing plan in the project proposal, or if the participant fails to sign the land sale contract without a valid reason, this could constitute grounds for termination under the agreement. The corporation said it would consider taking action under the agreement.



Seongnam Urban Development Corporation said, "We will move forward steadily with the Baekhyeon MICE urban development project through responsible project management based on the law and principles."