Project Feasibility and Economic Viability Constraints Hamper Progress
Lack of Specific Policy Standards

The government has selected modular housing as a key solution to labor shortages at construction sites and shorter construction periods, and pledged a major expansion in the number of units ordered along with financial support. However, regional development corporations in the Seoul metropolitan area, which play a key role in supplying public housing, remain cautious about placing orders on a full scale, citing limits to project feasibility and economic viability, as well as the lack of specific policy standards.

Metropolitan Development Corporations Hesitate Despite 35 Million Won per Household in Support [Modular Housing, the Spearhead of Dakgong] 2 View original image

According to the Ministry of Land, Infrastructure and Transport on Nov. 27, the government will increase its target for orders of modular public housing from 2027 to 2030 by 8,000 units, from 12,000 to 20,000. The annual average number of units ordered will rise from 3,000 to 5,000. This is a follow-up to the plan for accelerating housing supply announced in August. The government aims to build up the industry's production capacity by securing stable demand from the public sector.


In particular, to ease the construction cost burden, which is considered the biggest obstacle to modular housing, the government plans to provide 35 million won per household toward the additional costs compared with conventional construction methods. Modular housing can cut construction time by 20-30% compared with conventional methods, but has been criticized as less economically viable because construction costs are about 30% higher than those of conventional reinforced concrete construction, partly due to the upfront investment in production facilities and logistics costs.


An official from the Ministry of Land, Infrastructure and Transport said, "We are actively seeking cooperation not only from Korea Land and Housing Corporation (LH), but also from regional development corporations that have previously built modular housing."

Metropolitan Development Corporations Hesitate Despite 35 Million Won per Household in Support [Modular Housing, the Spearhead of Dakgong] 2 View original image

However, regional development corporations in the Seoul metropolitan area have responded lukewarmly. They believe that securing economic viability must come first before projects can move forward in earnest, and that detailed criteria have yet to be met, including construction costs exceeding project costs.


Seoul Housing & Communities Corporation (SH) is continuing technical demonstrations, including those involving precast concrete (PC) modular housing, but remains cautious about assessing the feasibility of expanding the business. Precast concrete involves making concrete frames in a factory and assembling them at the construction site. An SH official said, "We have not yet conducted a feasibility review or a profitability investigation (PI) to determine whether the business can be viable. Internal data from previous small-scale modular housing projects showed that construction costs exceeded project costs, so we have not yet begun a full-scale review." The official added, "Even if the government covers roughly half of the additional construction costs, SH would still have to cover the other half."


Incheon Housing and City Development Corporation (IH) is in a similar position. An IH official said, "A subsidy of 35 million won per household has little immediate significance when we do not know where the housing will be built or what form it will take." The official added, "We will need to wait for the results of a consulting project on plans to develop and commercialize specialized housing models, which is due to be completed next year, before we can consider follow-up procedures such as identifying potential sites for pilot projects."



Gyeonggi Housing and Urban Development Corporation (GH) is waiting for the government to announce detailed policies and guidelines. A GH official said, "We will proceed with our existing in-house plan for ordering modular housing," adding, "We have yet to receive official calculations or detailed data on the subsidy per household, so plans for additional orders based on the support are still under review."


This content was produced with the assistance of AI translation services.