Minister of Climate, Energy and Environment Kim Seong-hwan (third from left in the back row) poses for a commemorative photo with representatives of residents of Hanam's Gamil District after attending the “Dong Seoul Converter Station Residents’ Council Appreciation Event” at the National Assembly on the afternoon of the 25th. Ministry of Climate, Energy and Environment.

Minister of Climate, Energy and Environment Kim Seong-hwan (third from left in the back row) poses for a commemorative photo with representatives of residents of Hanam's Gamil District after attending the “Dong Seoul Converter Station Residents’ Council Appreciation Event” at the National Assembly on the afternoon of the 25th. Ministry of Climate, Energy and Environment.

View original image

The construction of the Dong Seoul Converter Station, long delayed by resident opposition and permitting disputes, has reached a breakthrough. This follows three months of consultations, after the government, Korea Electric Power Corporation (KEPCO), and representatives of residents in Gamil District, Hanam, Gyeonggi Province, agreed on a draft agreement that includes an independent safety review and the pursuit of administrative procedures. However, whether to finalize the agreement will be decided in a resident vote among the heads of households in all 19 apartment complexes in Gamil District.


The Ministry of Climate, Energy and Environment said on November 25 that Minister Kim Seonghwan and representatives of Gamil District residents had agreed on the draft agreement at the “Appreciation Ceremony for the Dong Seoul Converter Station Residents’ Consultative Group,” held at the National Assembly.


The Dong Seoul Converter Station project is a key power grid construction project intended to supply electricity generated on the east coast to the Seoul metropolitan area. KEPCO has been pursuing a project to move the existing 345-kV outdoor AC facilities at the Dong Seoul Substation in Gamil-dong, Hanam, Gyeonggi Province, indoors and add 500-kV high-voltage direct current (HVDC) conversion facilities. Once completed, the capacity of the power facilities will increase 3.5-fold, from the current 2 GW to 7 GW.


However, the project faced difficulties from its early stages as residents of nearby Gamil District voiced opposition over concerns about electromagnetic fields, noise, and fire risks. Residents opposed expanding large-scale power facilities on a site close to residential areas and educational institutions, and called for the facilities to be relocated to an alternative site and for their safety to be verified.


In August 2024, Hanam City rejected four permits sought by KEPCO for the indoor conversion and expansion of the Dong Seoul Substation, citing insufficient consultation with residents and concerns about the impact on the residential environment. KEPCO then filed an administrative appeal, and in December of the same year, the Gyeonggi Provincial Administrative Appeals Commission ruled in KEPCO’s favor, bringing the dispute over the project into a new phase.


As residents continued to oppose the project despite the permitting dispute, the government and KEPCO began direct consultations with their representatives. Since the first meeting of the Dong Seoul Converter Station consultative group on August 26, representatives of Gamil District residents, the Ministry of Climate, Energy and Environment, KEPCO, and the office of Lee Kwang-jae of the Democratic Party of Korea held a total of 17 meetings. They focused on the possibility of relocating the facilities to an alternative site, living environment issues such as electromagnetic fields and noise, and measures to ensure resident safety.


The key elements of the draft agreement are to conduct an objective review by an independent expert organization while pursuing the administrative procedures needed to move the project forward. An external expert organization will review materials submitted by KEPCO on the possibility of relocating the facilities to an alternative site, as well as materials related to resident safety and environmental impacts, including electromagnetic fields, noise, and fire risks.


While the review is underway, KEPCO will begin the administrative procedures for construction of the Dong Seoul Converter Station. However, the procedures must be suspended if the final review identifies any serious defects or risks. The Ministry of Climate, Energy and Environment will request that KEPCO take any necessary follow-up measures and check whether they are actually implemented.


The draft agreement also includes measures to protect resident safety and the residential environment. The converter station building will use electromagnetic shielding materials, and after construction is completed, electromagnetic field and noise levels will be monitored together with residents. Trees will be planted as a screen on the side facing Gamil District to reduce the impact on the residential environment.


Measures to support the local community and promote coexistence will be developed through a separate consultative group. A group comprising resident representatives and KEPCO will be formed to discuss additional support projects and other ways to benefit the community.


However, this agreement does not in itself mean that residents have given their final consent to the project. A resident vote among the heads of households in all 19 apartment complexes in Gamil District must be held to decide whether to sign the agreement. If the vote passes, resident representatives, the Ministry of Climate, Energy and Environment, KEPCO, and the office of National Assembly member Lee Kwang-jae will sign the agreement, which will take effect on the date of signing. The date of the vote has not yet been announced.



“I sincerely thank the resident representatives who worked hard to prepare the draft agreement over the past three months despite the difficult circumstances,” Minister Kim Seonghwan said. “This consultative group is significant because we established procedures together to review residents’ concerns and discussed ways to support the local community and promote coexistence.” He added, “The government will provide support to ensure that measures to protect resident safety, improve the residential environment, and benefit the local community are fully implemented.”


This content was produced with the assistance of AI translation services.

© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.

Today’s Briefing