BAI Uncovers 'Defective Completion' of 47 Jeju Road Projects
Completed road and lane-marking projects despite substandard quality
Investment review evasion and alleged favoritism in port construction also uncovered
It was revealed that 47 road construction projects commissioned by Jeju Special Self-Governing Province, Jeju City, and Seogwipo City were completed without any significant corrective action, even though the pavement thickness, lane-marking retroreflectivity, and other features failed to meet quality standards. As many as 32 public officials neglected their duties to supervise the work and inspect the completed projects. The audit also uncovered cases in which a road project that had received an “inadequate” rating in two investment reviews was pushed ahead by reducing its budget, and a contractor for port construction work was selected without following the legally required review process.
On November 25, the Board of Audit and Inspection (BAI) released the findings of its “Regular Audit of Jeju Special Self-Governing Province,” announcing a total of 16 measures, including one disciplinary action request, seven requests for caution, and seven notifications. The audit was conducted in consideration of the fact that Jeju Province had been granted considerable autonomy over its finances and personnel under a special act, but had not been audited since 2019.
The audit found that from 2022 through 2025, Jeju Province, Jeju City, and Seogwipo City carried out a total of 835 projects, including 397 road resurfacing projects and 438 pavement-marking projects. The total contract value amounted to approximately KRW 110.4 billion.
Among these, quality test results submitted directly by contractors showed that the asphalt pavement thickness and compaction density failed to meet standards in 21 road resurfacing projects worth approximately KRW 6 billion. The retroreflectivity required to identify lane markings at night also fell short of standards in 26 pavement-marking projects worth approximately KRW 6.2 billion. However, the commissioning authorities approved the projects as complete without requiring necessary measures, such as remedial construction.
Insufficient compaction density in road pavement increases the likelihood that rainwater will seep in and cause potholes. Poor lane-marking retroreflectivity makes it harder for drivers to see at night, increasing the risk of traffic accidents. The BAI notified the Jeju Province Audit Committee to conduct its own investigation into the 32 public officials involved and take appropriate measures, including disciplinary action. It also called for the authorities to inspect the work of contractors responsible for defective construction and take necessary measures, such as remedial construction.
The audit also found a case in which Jeju City reduced the scope of a project to avoid the results of an investment review. The city received an “inadequate” rating in two Jeju Province investment reviews, in August 2019 and March 2021, for the expansion and paving of County Road No. 71. The reviews cited a lack of urgency and project feasibility, as well as concerns about environmental damage.
At the time, the project’s total cost of KRW 4.14 billion meant it was subject to an investment review. Jeju City reduced the construction section from the original 1.5 kilometers to 1.1 kilometers and lowered the project cost to KRW 3.98 billion. It then proceeded with the work without undergoing the investment review required for projects costing KRW 4 billion or more.
The project was completed in April 2025, but the remaining 3.9 kilometers of the 5-kilometer route were left unpaved. As a result, vehicles could not use that section, and the road was found to be failing to serve its intended function.
Quality control of the construction was also inadequate. Civil servant A, a grade 6 team leader in charge of the project, was informed that the contractor had not conducted asphalt quality tests but nevertheless ordered that the work be approved as complete without requiring tests or corrective measures. In a sample inspection of three paved road sections, the BAI found that two failed to meet quality standards for compaction thickness and degree of compaction.
The BAI requested disciplinary action against A. It also notified the Ministry of the Interior and Safety to devise appropriate measures, such as reducing local grant tax allocations, in response to Jeju Province proceeding with the project without following the investment review results.
The audit uncovered procedural violations in port construction projects that could undermine fairness in contractor selection. From March 2021 through February 2023, Jeju Province selected contractors for eight port construction design and construction management service projects using the Statement of Qualifications (SOQ) evaluation method without obtaining a review from the Provincial Construction Technology Deliberation Committee.
In particular, employees of Jeju Province’s Maritime and Port Affairs Division who served as evaluation committee members were found to have given perfect scores to a company established by a former Jeju Province civil servant. As a result, the rankings of contractors were reversed in four of the eight projects, with companies that had ranked second or third in the preliminary qualification evaluation (PQ) for project performance capabilities ultimately taking first place.
At two port construction sites, contractors brought in and used riprap—large stones used in port structures and other facilities—without Jeju Province’s approval. The construction managers failed to properly control this, and Jeju Province was also found to have neglected its oversight and supervision duties.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
The BAI therefore called on Jeju Province to follow the legally required review procedures when selecting contractors for port construction projects. It also notified the province to assess the extent of the deficiencies of construction managers and technical personnel who inadequately managed the projects and take appropriate measures.