Honam Semiconductor Water Supply Network to Be Built; Deoknam Plant to Double Treatment Capacity
KRW 72.3 billion to be invested in 4 km of new water transmission pipelines
Priority supply of 150,000 tons of water per day to begin in late 2028
To supply 150,000 tons of water per day to the Honam semiconductor cluster, Gwangju will double the treatment capacity of Deoknam Water Treatment Plant and install 4 kilometers of new water transmission pipelines.
According to Jeonnam-Gwangju Integrated Special City on November 25, the city is investing a total of KRW 72.3 billion in upgrades to Deoknam Water Treatment Plant and the construction of new water transmission pipelines. The goal is to complete the facilities by December 2028 and prioritize water supply for semiconductor production facilities (fabs).
The initial water supply will consist of 50,000 tons per day from Juam Dam and 100,000 tons per day from Boseonggang Dam. Gwangju Special City will invest KRW 45.1 billion to increase the plant's average daily treatment capacity from 220,000 tons to 440,000 tons. It will add 7,000 cubic meters of water storage capacity and switch the filter-cleaning method from water-only washing to a process that uses both water and air.
A further KRW 9.2 billion will be invested in pipelines to carry water to the semiconductor cluster. A 1-kilometer pipeline with a diameter of 1,350 millimeters will connect the existing water transmission pipeline to the cluster. To prepare for emergencies such as a shutdown of the water treatment plant, the city will also invest KRW 18 billion in a 3-kilometer looped transmission pipeline connecting Deoknam Water Treatment Plant and Yongyeon Water Treatment Plant.
Discussions are also continuing over how to share the project costs. The national and local governments will each cover half the cost of upgrading Deoknam Water Treatment Plant, while the semiconductor water transmission pipeline will be built entirely with national funds. The looped transmission pipeline will be funded by the city, which is discussing expanded national support. At a city council administrative audit on November 9, concerns were raised that investment in water facilities needed for a national strategic industry could burden local finances.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
Gwangju Special City will begin basic and detailed design work next month and complete the designs by October 2027, before starting construction. The facilities are scheduled for completion by December 2028.