Four districts under the project acceleration policy, covering 6,132 households
Associations established an average of 172 days after district designation
Songpa Hanyang 1-cha fastest, at 112 days ("Shortest")

The Seoul Metropolitan Government said on the 24th that four districts covered by its “Redevelopment Project Process Acceleration” policy, comprising a total of 6,132 households, received approval to establish residents’ associations an average of 172 days after district designation.

Seoul City Hall CI

Seoul City Hall CI

View original image

Songpa Hanyang 1-cha achieved the fastest result among the four districts, receiving approval to establish its association 112 days after district designation. The other three districts—Doksan 2, Sadang 17 and Sillim 8—also completed the association-establishment process early. All four districts received approval 142 to 253 days ahead of the standard processing period of 365 days.


The key to dramatically shortening the association-establishment period was a change that allows procedures previously begun only after a redevelopment district was designated to start beforehand. In the past, after a district was designated, residents had to form a project promotion committee, collect consent forms, draft bylaws and select officers in sequence. As a result, establishing an association took an average of three years and six months.


To shorten the association-establishment period, the Seoul Metropolitan Government set a one-year standard processing period in July 2025. Starting in August that year, it also held joint city-district project acceleration meetings and closely managed schedules for each project site. In addition, under “Regulation Reform No. 142,” announced in August 2025, residents were allowed to form project promotion committees voluntarily before district designation, subject to the district head’s approval.


In August 2026, the city introduced measures to improve the process for accelerating association establishment, further expanding the work that can be prepared before district designation. If a project promotion committee meets the consent requirements for association establishment, it can select a professional management company, draft bylaws and choose officers before the district is designated. The city also reduced the period for filing objections to estimated cost allocations from at least 60 days to 30 days, and now allows an inaugural general meeting to be held during that period. These changes make it possible to shorten the time from district designation to association establishment to as little as 120 days.


Currently, a total of around 21,000 households across 11 districts, including Myeonmok 10, Mia-dong 130 and Beon-dong 148, are preparing to establish associations after receiving approval for project promotion committees before redevelopment district designation, following regulatory reforms and amendments to relevant laws. The city plans to closely manage these districts through joint city-district project acceleration meetings until their associations are established. If the law is amended to lower the consent threshold for establishing a redevelopment association to 70%, the city will support districts that meet the requirement in carrying out association-establishment work in advance.



Myeong Nojun, Seoul Metropolitan Government’s housing chief, said, “The projects have shown firsthand that by easing regulations and changing procedures, association establishment—which used to take three years and six months—can be completed in just four months. We hope districts that have formed project promotion committees in advance will make active use of the improved procedures. The Seoul Metropolitan Government will continue to monitor project progress through to completion and ensure it meets its target of starting construction on 310,000 homes by 2031.”