Icheon Mayor Seong Suseok Visits Eugene Tech Expansion Site... First Fast-Track Permitting Success
Processed the construction start report within two weeks of launching the dedicated team
Met the company’s requested October 1 date
Mayor Seong: “Timing is a source of competitiveness for corporate investment”
Heard about additional investment plans and challenges
Icheon Mayor Seong Suseok visited the site of Eugene Tech’s factory expansion in Maegok-ri, Hobeop-myeon, Icheon, Gyeonggi Province, on November 20. It is the first project to use the “fast-track” system for expediting investment attraction since Mayor Seong took office.
Icheon Mayor Seong Suseok visits Eugene Tech's plant in Maegok-ri, Hobeop-myeon, Icheon, Gyeonggi Province, on the 20th to inspect progress on the factory expansion, then poses for a commemorative photo with company executives and employees. Provided by Icheon City.
View original imageIcheon City processed the construction start report within two weeks of launching a dedicated team, with relevant departments jointly reviewing permitting issues.
Eugene Tech signed an investment agreement with Icheon City in June 2024 and is expanding its semiconductor-related factory and research facilities at its Icheon site in stages. The city launched a dedicated investment attraction team after deciding on and publicly announcing the district unit plan for the Eugene Tech District last September.
The team monitored progress at each stage, including development permits, factory expansion approval, and building permits. Relevant departments regularly shared their review comments and requests for supplementary information and consulted with the company and relevant organizations. As a result, the city processed Eugene Tech’s construction start report on October 1, the date the company had requested.
During his visit to the site that day, Mayor Seong heard about Eugene Tech’s future investment plans, challenges during construction, and areas where additional support was needed. He also encouraged the public officials who had worked together to process the permits.
“The timing of a company’s investment is a source of competitiveness, and the city administration must be a reliable ally so companies do not miss investment opportunities,” Mayor Seong Suseok said. “We will continue to listen directly to companies’ challenges on site and actively seek solutions.”
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
Icheon City plans to continue providing support tailored to each company’s investment schedule, from investment consultations and permitting through to construction, led by its dedicated investment attraction team.