AIDCs Outside Seoul Metro Area Get Easier Power Reviews Up to 50 MW; Colocation Centers Also Eligible for Support
Ministry of Science and ICT Announces Proposed Enforcement Decrees and Rules for AIDC Special Act
Starting in March 2027, colocation AI data centers will also be eligible for support under the Special Act on AI Data Centers (AIDC Special Act). AI data centers outside the Seoul metropolitan area will be exempt from the Power System Impact Assessment if their contracted power capacity is 50 MW or less.
The Ministry of Science and ICT said on November 20 that it had drawn up proposed enforcement decrees and rules for the Special Act on the Promotion of the AI Data Center Industry and would hold a 40-day public notice period through December 30.
The AIDC Special Act was enacted to support the rapid construction and stable operation of AIDCs and is set to take effect in March 2027. The proposed subordinate legislation sets out in detail the eligibility criteria for support under the act, licensing and permitting procedures, and standards for applying various special provisions.
The proposed enforcement decree includes under the act's definition of an AIDC a "third-party service facility" that provides space and power, communications, and cooling infrastructure so another operator can install and operate AI equipment there. Until now, colocation data centers have been excluded from support for national strategic technology businesses under the Restriction of Special Taxation Act and have therefore been ineligible for AIDC tax benefits.
An eligible AIDC is defined as a facility equipped with AI accelerators, such as graphics processing units (GPUs) and neural processing units (NPUs), above a specified scale, as well as power and cooling infrastructure. Specifically, it must either have AI equipment with a power capacity of at least 250 kW that accounts for at least 50% of the total power capacity of its information and communications equipment, or have AI equipment with a power capacity of at least 5 MW. The ratio of total facility power capacity to information and communications equipment power capacity must also be no greater than 1.5.
The AIDC registration system is divided into construction registration before construction work begins, operational registration 30 days before operations begin, and registration of changes within 30 days of any change to key details. To prevent operators from registering without actually proceeding with their projects, applicants must specify a planned construction start date within one year of registration. The consolidated licensing and permitting procedure has also been further detailed. The proposed rules specify response deadlines for the Ministry of Science and ICT and relevant agencies, and allow the process to proceed based on the documents submitted if an agency does not respond by the deadline.
AI data centers newly built, expanded, or converted outside the Seoul metropolitan area will be exempt from the Power System Impact Assessment (PSIA) if their contracted power capacity is 50 MW or less. In addition, the government will introduce a fast-track process to prioritize the PSIA for megaprojects and projects eligible for consolidated licensing and permitting, alongside a simplified AIDC assessment system that exempts data centers in special zones from nontechnical assessments.
Facility regulations will also be eased: parking requirements for AIDCs will be reduced by 20% from the current standard, and local governments may grant an additional reduction of up to 50% through local ordinances. When calculating gross floor area for the purpose of determining requirements to install artwork in buildings, server rooms and cooling equipment rooms will be excluded. However, only 50% of the area of server rooms in the Seoul metropolitan area will be excluded.
Procedures for designating AIDC special zones outside the Seoul metropolitan area have also been established. If a local government submits a business plan and a plan to secure infrastructure, the Ministry of Science and ICT will review them within 90 days, and the zone will be designated following deliberation and a decision by the National AI Strategy Committee. Infrastructure that the central and local governments may support in special zones will include not only power and water supply facilities but also roads and bridges, energy storage facilities, waste heat reuse facilities, high-speed communications infrastructure, security and disaster response facilities, and facilities that promote coexistence with local residents.
The Ministry of Science and ICT will also draw up regional coexistence guidelines in the first half of 2027, including procedures for gathering opinions from residents living near data centers. A public hearing on the proposed subordinate legislation will be held on December 9 at Nuritkum Square in Mapo-gu, Seoul.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
Bae Kyunghoon, Deputy Prime Minister and Minister of Science and ICT, said, "The proposed subordinate legislation will give operators greater predictability, including clarity on which AIDCs are eligible for support under the special act and the scope of benefits they can receive." He added, "During the public notice period, we will carefully gather feedback from industry stakeholders and prepare to make AIDCs a foundation for the growth of the AI industry."