Ruling Cancels Master Plan, Derailing Project's First Step
"Insufficient Review of Bird-Strike Risks and Environmental Impact"
Year-End Construction Start and Advance Payment Schedule Also Uncertain
Gadeokdo New Airport Lawsuit Also on High Alert

The Saemangeum International Airport construction project, worth KRW 807.7 billion and pursued after being exempted from a preliminary feasibility study, is at risk of prolonged delays after a court twice ruled to cancel its master plan. Whatever path the Ministry of Land, Infrastructure and Transport (MOLIT), the defendant in the lawsuit, chooses—appealing to the Supreme Court or drawing up a new master plan—the project will be delayed by several years, making it difficult for the airport to open in 2029.


According to relevant government ministries on November 19, MOLIT said it “respects the court’s ruling, will carefully review the written judgment, and plans to decide on its next steps” after the Seoul High Court on November 18 ruled in favor of the plaintiffs, including the Joint Action to Cancel Saemangeum New Airport, as the lower court had. MOLIT has yet to decide whether to appeal to the Supreme Court or draw up a new master plan. After the government lost the first trial in September 2025, it bolstered its arguments on safety and appealed. Officials in the government and local governments say they “did not expect to lose the second trial as well.”


Second Trial Also Cites Bird-Strike Risk... Argument That Gunsan Airport Has Had No Accidents Fails

Artist's rendering of Saemangeum International Airport. HJ Heavy Industries

Artist's rendering of Saemangeum International Airport. HJ Heavy Industries

View original image

Bird-strike risk was the issue that derailed the project in both the second trial and the first trial. After losing the first trial in September 2025, the government and Jeonbuk Special Self-Governing Province focused their arguments in the appeal on the fact that nearby Gunsan Airport had experienced nine bird strikes over the previous 15 years without any resulting damage.


A Jeonbuk provincial government official said, “We explained that the figures were high because the comparison criteria differed from those for existing airports, and that bird strikes could be adequately managed, but the court reached a different conclusion.”


The appellate court recognized the need for an airport to promote balanced regional development, but said safety must come first. It pointed out that it was unreasonable to downplay the risk based solely on operational experience at Gunsan Airport, even though an assessment using MOLIT’s model for evaluating potential sites for new airports found the bird-strike risk at the project site to be significantly higher than at other airports in Korea.


Appeal or New Master Plan? Relocating the Site Also Under Discussion

Saemangeum Airport Stalled Again on Appeal... Contractors Selected, Budget Set, but Site May Have to Be Relocated View original image

MOLIT is in a difficult position. Appealing to the Supreme Court to keep the national project moving would carry significant risks. A ministry official said, “The first and second trials were trials of fact, in which the facts and evidence are contested, whereas the Supreme Court reviews questions of law, including whether the law was applied correctly. We need to first analyze whether the environmental and procedural issues identified by the court can be addressed and whether there is a chance of the ruling being overturned on appeal before deciding whether to proceed.” With two courts having found the bird-strike risk assessment inadequate, it will be difficult to overturn the ruling in the Supreme Court, which considers only whether the law was misinterpreted.


If the government does not appeal within two weeks of receiving the official copy of the judgment, or if it ultimately loses in the Supreme Court, the master plan announced in June 2022 will be automatically canceled without any separate procedure. To resume the Saemangeum airport project, the government would need to resolve the safety and environmental issues identified by the court, then draw up and announce a new master plan. Drawing up a new master plan typically takes two to three years. MOLIT began work on the current master plan in June 2020 and announced it two years later, in June 2022. Since the scope and method of redrafting the plan have not been determined, it is still difficult to estimate how long the project will actually be delayed.


Relocating the airport site instead of pursuing the lawsuit is also gaining traction. At a press conference on November 18, the Jeonbuk provincial government said, citing the court’s concerns about the location, that “it will be difficult to insist on the current site” and that “we will need to discuss internally how to proceed.” The provincial government says the exemption from the preliminary feasibility study, granted in 2019 as part of a national balanced-development project, would remain in effect even if the site were changed. It says the court canceled the master plan announced by MOLIT in 2022, which is separate from the exemption.


The original schedule called for construction to begin at the end of 2025 and the airport to open in 2029. With that timeline now derailed, the construction and engineering companies that won contracts for the project, as well as the government’s budget execution schedule, have also been thrown into disarray. In June 2024, MOLIT selected an HJ Heavy Industries consortium, including Daewoo Engineering & Construction, Kolon Global, KCC Engineering & Construction, and Shinseong Construction, as the eligible bidder for detailed design through a turnkey contract, under which design and construction are awarded together. It also assembled a design team that included Korea Engineering Consultants Corporation. However, follow-up procedures, including consultations on the environmental impact assessment, were suspended after the government lost the first trial in September 2025.


Despite the situation, the government included KRW 120 billion for site preparation work in its proposed 2027 budget. The original plan was to begin construction at the end of 2026 and pay an advance on the construction contract once the appeal had concluded, but after losing the appeal, the schedule became uncertain.


Gadeokdo New Airport Lawsuit Raises Similar Issues... Implications for National Airport Projects

Saemangeum Airport Stalled Again on Appeal... Contractors Selected, Budget Set, but Site May Have to Be Relocated View original image

Saemangeum International Airport is a project to build a runway, passenger terminal, and other facilities on a 3.4-million-square-meter site in the Saemangeum area, west of Gunsan Airport. With the start of construction now uncertain, the development of a Saemangeum “tri-port”—an integrated land, sea, and air logistics network linking the new port, railway, and airport—is also expected to face delays.


The repercussions could extend to other national airport projects being pursued by MOLIT. The first trial is underway in a lawsuit filed by 1,028 residents against the MOLIT minister seeking to cancel the master plan for Gadeokdo New Airport.


Bird-strike risk and environmental damage are also at issue at Gadeokdo New Airport, which is being pursued after receiving an exemption from a preliminary feasibility study. The site preparation work alone is estimated to take 106 months and cost KRW 10.7 trillion, more than 19 times the approximately KRW 560 billion construction cost of Saemangeum Airport.


The Daewoo Engineering & Construction consortium has completed the basic design and began detailed design on November 9. The government is targeting a 2035 opening and is preparing to begin main construction in the first half of 2027.



If the ruling canceling the master plan for Saemangeum Airport is finalized, it is expected to put further pressure on the Gadeokdo lawsuit, which involves similar issues. Conversely, if the Supreme Court overturns the ruling, MOLIT will be able to breathe a sigh of relief. As MOLIT weighs whether to appeal the Saemangeum ruling, it must also consider the potential repercussions for major national airport projects as a whole, including Gadeokdo New Airport.


This content was produced with the assistance of AI translation services.