Jinju-Sacheon National Route Bypass to Receive KRW 271.8 Billion; Follow-Up Steps Underway to Expedite Construction
Part of City Road No. 27 Temporarily Opens; Construction Begins on Urban Planning Road Near Former Jinju Station

Jinju City in South Gyeongsang Province is pursuing the expansion of major arterial roads and the construction of urban planning roads to address rising traffic volumes in the city center and recurring congestion around industrial complexes.


The city announced on November 17 that it is taking follow-up steps to expedite construction of the Jinju-Sacheon National Route Bypass, has temporarily opened part of City Road No. 27, and has begun construction of an urban planning road in the area around the former Jinju Station.


The road network expansion projects aim to divert traffic from National Route 3 and improve access to Jeongchon Industrial Complex, the Sinjinju Station area, and the area around the former Jinju Station.


[Photo provided by Jinju City] Location map of the “Shin Jinju Station Area–Maedong, Jeongchon-myeon Road Construction Project (City Road No. 27),” being carried out by Jinju City. The project will invest KRW 48.5 billion to build a two-lane road measuring 1.83 km long and 9 m wide, from the Shin Jinju Station Area to Maedong Village in Jeongchon-myeon. Construction is scheduled to resume in early 2027.

[Photo provided by Jinju City] Location map of the “Shin Jinju Station Area–Maedong, Jeongchon-myeon Road Construction Project (City Road No. 27),” being carried out by Jinju City. The project will invest KRW 48.5 billion to build a two-lane road measuring 1.83 km long and 9 m wide, from the Shin Jinju Station Area to Maedong Village in Jeongchon-myeon. Construction is scheduled to resume in early 2027.

View original image

In particular, traffic from companies and workers at industrial complexes in Jeongchon-myeon converges in the area, causing congestion on National Route 3 during commuting hours. The need for alternative roads has therefore been raised.


◆ Jinju-Sacheon National Route Bypass: KRW 271.8 Billion Project

Jinju City is pursuing the Jinju-Sacheon National Route Bypass project to divert traffic from National Route 3. The project has a total budget of KRW 271.8 billion and will cover 6.1 km.


Last August, the project passed a preliminary feasibility study conducted as part of the comprehensive review for the Sixth National Road and National Regional Road Construction Plan.


Since the study was approved, the city has been taking follow-up administrative steps, including visiting the National Assembly and relevant central government agencies to explain the need for the project and call for its expedited implementation.


However, it is expected to take some time before construction can begin, as procedures such as detailed design and land compensation must first be completed.


Accordingly, Jinju City plans to ease traffic congestion in Jeongchon-myeon by carrying out projects to expand and build City Road No. 27 alongside other work until the bypass opens.


The city expects the bypass to help divert traffic from the existing National Route 3 and improve travel conditions for vehicles traveling between Jinju and Sacheon.


◆ Part of City Road No. 27 Expanded to Five Lanes and Temporarily Opened

Jinju City is also pursuing road expansion and new construction projects on City Road No. 27 to reduce congestion around Jeongchon Industrial Complex.


Jeongchon-myeon sees heavy traffic from industrial complex workers commuting to and from work, as well as freight vehicles, causing congestion on National Route 3 and at nearby intersections.


In particular, as more vehicles use City Road No. 27 to travel toward Jeongchon Industrial Complex from the Jukbong Intersection on National Route 2, improvements to the traffic-handling capacity of intersections near the complex became necessary.


To address this, the city invested KRW 1.5 billion to expand the intersection section near Jeongchon Industrial Complex at the terminus of City Road No. 27 from two lanes to five lanes, with one lane in each direction becoming additional lanes, and temporarily opened it in November.


The expansion work was carried out to improve intersection access for vehicles entering Jeongchon Industrial Complex and to ease traffic flow on surrounding roads.


The city is also preparing to resume construction of the City Road No. 27 project, which will connect the Sinjinju Station area with Maedong Village in Jeongchon-myeon.


The project will build a two-lane road, one lane in each direction, spanning 1.83 km and measuring 9 meters wide, at a total cost of KRW 48.5 billion.


Construction was temporarily suspended after the project was put out to tender in November 2023 to allow for compensation negotiations and additional administrative procedures. The city plans to resume construction in early 2027.


Jinju City expects the completed road to expand transport links between the Sinjinju Station area and Jeongchon-myeon and help divert traffic from National Route 3.


Earlier, in February 2026, the city completed improvement work at Bang-a Intersection near the Sinjinju Station area, adding a dedicated left-turn lane to the existing two-lane road.


The city expects the improvement to make it easier for vehicles traveling toward the Sinjinju Station area and Sacheon to pass through the intersection.


◆ Construction on Urban Planning Road Near Former Jinju Station Begins in November; Opening Targeted for First Half of 2027

Jinju City also began construction this November on an urban planning road project to improve access to the area around the former Jinju Station in Gangnam-dong.


[Photo provided by Jinju City] Location map for the Sinjinju Station-Jeongchon Maedong Road (City Road No. 27) project, 추진ed by Jinju City to disperse traffic on National Route 3 and improve traffic conditions around Jeongchon Industrial Complex.

[Photo provided by Jinju City] Location map for the Sinjinju Station-Jeongchon Maedong Road (City Road No. 27) project, 추진ed by Jinju City to disperse traffic on National Route 3 and improve traffic conditions around Jeongchon Industrial Complex.

View original image

The project will build a 252-meter urban planning road at a total cost of KRW 6.9 billion, with opening targeted for the first half of 2027.


The area around the former Jinju Station is the site of projects related to cultural facilities, including a cultural park, a public specialized aerospace science museum, the relocation of the National Jinju Museum, and the creation of a cultural street.


In anticipation of the development of these cultural facilities and an increase in visitors, the city is expanding the surrounding road network and building the urban planning road to improve travel convenience for local residents and visitors.


The road was designated as an urban planning facility in October 2022. Following detailed design, funding and other procedures, construction began in November 2026.

Jinju City expects the road to improve access to cultural facilities around the former Jinju Station and nearby residential areas once it opens.


A city official said, "We are pursuing major road expansion and construction projects to divert traffic from National Route 3 and ease congestion around Jeongchon Industrial Complex. We will also proceed with local road network expansion projects, including the urban planning road near the former Jinju Station, as planned to improve travel convenience for residents."


Meanwhile, Jinju City plans to proceed in stages with follow-up administrative procedures for the National Route bypass, the resumption of construction on City Road No. 27, and the urban planning road project near the former Jinju Station.



For Jinju City's road network expansion projects to bring meaningful relief from traffic congestion, it will be important to expedite follow-up procedures for the National Route bypass and improve connections between existing and new roads.