Gwangju Metro Line 2 Moves to Prevent Construction Delays... Utility Management Agency Consultative Body Launched
Underground utilities differing from design plans repeatedly found during Phase 1 construction
Phase 2 agencies to coordinate response... relocation schedules to be aligned in advance
To prevent a recurrence of delays during Phase 1 of Gwangju Metro Line 2, when underground utilities differing from the design plans were discovered and relocation schedules set by different management agencies did not align, Jeonnam-Gwangju Special Metropolitan City will establish a standing consultative body with agencies involved in Phase 2 to coordinate utility relocation schedules and construction plans in advance.
Gwangju Metropolitan City’s Urban Railway Construction Headquarters announced on November 17 that it would establish and operate a “Utility Management Agency Consultative Body” to minimize delays to construction of Phase 2 of Gwangju Metro Line 2.
Various utility lines, including stormwater drains, water mains, gas pipes, communications lines, power cables and sewer pipes, are installed at the construction site for Gwangju Metro Line 2. Provided by Gwangju Special City.
View original imageGwangju Metro Line 2 is being built using the cut-and-cover method, in which roads are excavated and underground structures are installed along the entire route. Before construction can proceed, underground utilities such as water and sewer pipes, gas pipes, and power and telecommunications lines must be relocated or protected from damage.
During Phase 1, the actual excavation work frequently uncovered utilities whose locations differed from those shown in the design plans, as well as facilities not marked on the plans. Because different agencies manage different utilities, relocation schedules did not align, leading to construction delays and other difficulties.
The number of sites requiring utility relocation or protection in Phase 1 increased from an initial 291 sites (25,531 m) to 384 sites (44,732 m). The total rose by 93 sites, and the overall length increased by 19,201 m.
To prevent the same problems from recurring in Phase 2, where civil engineering work is underway, the Urban Railway Construction Headquarters has established a framework for cooperation among the relevant agencies. Participants in the consultative body include Buk-gu and Gwangsan-gu, the Waterworks Headquarters, the National Police Agency, Korea Electric Power Corporation, Haeyang Energy, a city gas supplier, and telecommunications companies.
The consultative body will hold regular meetings every quarter and convene additional meetings as issues arise. The agencies will share their utility relocation and protection plans in advance and coordinate construction plans and schedules, while also discussing ways to shorten the consultation period. If unidentified utilities are found or unexpected situations arise during construction, the agencies will respond through working-level consultations.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
The Urban Railway Construction Headquarters will also pursue memoranda of understanding (MOUs) among the agencies. Awards will be presented to agencies and individuals who contribute to shortening the construction period and improving safety management.
© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.