Jeong Giseong, a member of the Jeonnam-Gwangju Integrated Special City Council (Democratic Party of Korea, Jangseong 2), strongly criticized the education office's inadequate management and supervision of facility construction projects involving tens of billions of won and called for measures to address the problem.


At an administrative audit of the Jeonnam-Gwangju Integrated Special City Office of Education held on November 13, Councilmember Jeong raised concerns over excessive design changes and budget increases during the reconstruction of Seongdong Elementary School in Suncheon and Goheungdong Elementary School under the "Green Smart School" project.

Jeong Giseong, member of the Jeonnam-Gwangju Integrated Special City Council.

Jeong Giseong, member of the Jeonnam-Gwangju Integrated Special City Council.

View original image

"At Seongdong Elementary School in Suncheon, after the original contractor went bankrupt, a single-source contract for the remaining construction work was signed for 1,692,790,000 won when the project was 70% to 80% complete, but the contract amount rose substantially following design changes," Jeong said. "There were as many as 164 items for which work not carried out after the contract was signed had to be reconciled, meaning that education office experts completely failed to conduct a thorough preliminary review during both the initial design and the contracting stage for the remaining work."


Noting that the contract amount for Goheungdong Elementary School also increased by more than 80 million won after a single-source contract was signed for the remaining work, Jeong called for special inspections of both schools and reports to the committee.


Jeong also raised the establishment of a "semiconductor meister high school" in connection with the relocation of the Gwangju military airport and the creation of semiconductor industrial complexes by companies including Samsung and SK. "If we do not prepare in advance to establish a school in an area with good living conditions, such as Jangseong near Advanced District 3, it will be too late once industries have been attracted," he said. "Businesses, local governments, and the education office should work together to proactively invest 50 billion won in expanding educational infrastructure."



He also pointed to the adverse effects of the "open recruitment system for principals." "Complaints have been raised that some principals appointed through the system cite compliance with school rules as a reason to cut off communication with parent associations and local communities, and are even uncooperative about opening school facilities such as gymnasiums to the public," Jeong said, strongly calling for verification of the objectivity of interview evaluation forms and the introduction of regular assessments after appointment to determine whether principals are following through on their management plans.