Democrats' sweeping victory in U.S. midterm elections
Fears of tighter regulation and cuts to AI capital spending

AI technology directly tied to national security and economic dominance
Tighten environmental and permitting requirements rather than impose blanket restrictions
Shift power grid expansion costs to companies

Power shortages, which take time to resolve, are a bigger problem than regulation
Reduced financing and delayed operations would add to the cost burden

Uncertain how semiconductors will be affected
Semiconductor orders unlikely to plunge in the short term
Semiconductor boom alongside service providers in the red is abnormal
The real impact may emerge in two years

Concerns are growing that pressure to regulate data centers and cuts to artificial intelligence (AI) capital investment could follow the Democrats' sweeping victory in the U.S. midterm elections. This has fueled expectations that data center investment could be curbed, sending semiconductor-related stocks plunging worldwide.


Gina Hinojosa, a Democratic state representative elected governor of Texas in this U.S. midterm election. Hinojosa said data center construction should be halted until policies to protect residents are in place. AP-Yonhap News

Gina Hinojosa, a Democratic state representative elected governor of Texas in this U.S. midterm election. Hinojosa said data center construction should be halted until policies to protect residents are in place. AP-Yonhap News

View original image
[Kim Sangcheol's Economic Focus] U.S. Data Centers Turn Pale, Semiconductors Flash Red Alert View original image

According to Bloomberg, about 40% of the data centers planned in the United States are concentrated in states where candidates who pledged to temporarily halt data center approvals have been elected governor. Moves to tighten regulations over the cost of expanding power grids and tax incentives are also expected. As a result, construction of new data centers could naturally be delayed.


However, delays in data center construction due to tighter regulations do not immediately translate into canceled memory chip orders. Even if some data center projects are delayed, the broader trend of expanding AI investment will continue. In practice, tighter data center regulations are likely to move toward a reasonable approach, because global competition in AI technology is directly tied to national security and economic dominance. There is little chance that data center construction will be fundamentally restricted as part of the race for AI supremacy. Data centers already account for a significant amount of U.S. tax revenue and job creation. So rather than imposing blanket restrictions, the more likely course is to strengthen environmental regulations and permitting requirements and require companies to bear the cost of expanding power grids. In other words, construction would not be prohibited, but companies pursuing data center projects would be required to cover power-related costs as well.


The incoming governor of Texas, which has the most data centers, announced a halt to new data center development and called for safeguards to protect residents, particularly regarding electricity bills and water use. Similar measures are likely to spread to other areas. The effect of regulations on delaying semiconductor demand is clear: costs will rise and construction will be delayed. But while the direction of regulatory expansion is clear, its pace is difficult to predict. It remains uncertain when and to what extent expanded regulations will affect semiconductor prices and the earnings of related companies. In fact, efforts to regulate data centers were already well underway before the midterm elections, with little difference between the parties. Amid worsening public sentiment and the resulting regulatory tightening, 30% to 50% of data center construction projects in the United States have already been delayed this year. In that light, the chances of semiconductor orders plunging in the short term are limited. For now, little will change for data centers already under construction or already approved. About 75% of the data centers scheduled to begin operating in 2027 across the 20 major U.S. states are reportedly already under construction. In the long term, however, the picture is different. The potential delay or rejection of projects awaiting approval is a concern. Swiss global investment bank UBS estimates that about 30% of the new data center capacity expected to be added in the United States in 2028 could face construction delays.


There is another issue that is even harder to resolve than tighter regulations on data center construction: power shortages. Unlike relocating a project or covering additional costs, addressing power shortages inevitably takes time. On average, it takes about 18 months to two years to build a data center. But if power generation capacity is insufficient, a completed data center may not be able to operate. Currently, about 35% to 45% of AI data center projects in North America are expected to begin operating at least two to three years later than planned because of delays in connecting to the power grid and local regulations. Delays in bringing data centers online mean that revenue generation is delayed by the same amount. A data center that cannot operate has absorbed investment but is not generating new revenue. At a time when AI-related companies are already reaching the limits of their ability to raise funds, delays in bringing data centers online add to their cost burden.


Hyperscalers' AI investment is currently at an astronomical $1.1 trillion annually, and none have announced plans to cut investment yet. In platform businesses, the first to cut investment loses the race. Even when returns decline, it is difficult to stop investing. U.S. hyperscalers' capital expenditure in 2027 is expected to be about 60% higher than this year. However, difficulties in raising funds will eventually affect demand. A substantial portion of the funding needed to build data centers is already being raised through private credit rather than bank loans. Private credit is more expensive than bank financing.


[Kim Sangcheol's Economic Focus] U.S. Data Centers Turn Pale, Semiconductors Flash Red Alert View original image

In the current period of excess demand, semiconductor supplies needed to build data centers are covered by long-term supply agreements of three years or more, with volumes and minimum prices set in advance. Most of the supply through 2027 is likely already secured under contracts. The total value of long-term purchase agreements signed by Nvidia and hyperscalers is reportedly close to $1 trillion. However, signing a long-term supply agreement does not strictly guarantee the timing or price of every delivery. The full impact is likely to emerge during renegotiations for 2028 supply. Buyers may seek to delay delivery, reduce supply volumes, or renegotiate contract prices. Nvidia's graphics processing unit (GPU) product cycles are also about 12 to 18 months.


It is difficult to find reliable evidence that can predict changes in the current semiconductor market. Signals from spot market prices remain mixed. But the distribution of earnings among AI-related companies is currently far from balanced. In the third quarter, Samsung Electronics posted an operating margin of 50%, while SK hynix posted 80%; Nvidia's margin is reportedly above 70%. But if the companies that ultimately provide services using products supplied by these firms are generating negative cash flow, this value-chain structure cannot be considered normal. Excessive profits that undermine the balance and hamper industry growth cannot be sustained for long. Hyperscalers' massive investments have yet to be fully reflected in their income statements. If power shortages, expanding regulations, and high interest rates all converge, investment may continue, but its execution will inevitably be delayed. By the second half of 2027 at the latest, the global AI ecosystem is likely to look very different from today.



[Kim Sangcheol's Economic Focus] U.S. Data Centers Turn Pale, Semiconductors Flash Red Alert View original image

Kim Sangcheol, economic commentator


This content was produced with the assistance of AI translation services.