Councilor Jeong Giseong Criticizes Design Flaws and Civil Engineering Work at Muan Haengbok Elementary School
"Difficult to Hold Anyone Responsible as the Legal Defect Liability Period Has Already Expired"

At an administrative audit on the 10th, the Education Committee of the Jeonnam-Gwangju Integrated City Council examined nine education support offices in Mokpo, Jangheung, Gangjin, Haenam, Yeongam, Muan, Wando, Jindo and Sinan. Problems in local education administration came under scrutiny, including ground subsidence at a newly built school and delays in opening a public library.


During the audit, Councilor Jeong Giseong (Democratic Party of Korea, Jangseong 2) strongly criticized the ground subsidence at Muan Haengbok Elementary School, now in its sixth year since opening, and focused on the repair work, which cost 266 million won.

Jeong Giseong, a member of the Jeonnam-Gwangju Integrated City Council.

Jeong Giseong, a member of the Jeonnam-Gwangju Integrated City Council.

View original image

"Given that the school site was once a muddy field, the cause should have been clearly established first, including whether there were any flaws in the initial design or civil engineering work," Councilor Jeong said. "Ground subsidence occurred at a school attended by around 1,500 students, yet the education office has not even determined the exact details."


Councilor Jeong's questions went beyond the visible damage to examine the construction methods and responsibility for the problem. He asked in detail whether the initial design, including pile work to prevent subsidence, had been properly carried out when the building was constructed on muddy ground, and what response the construction company had given to the incident.


Following the audit and repeated requests from Councilor Jeong, the Muan Office of Education submitted a separate written response containing materials on the causes of ground subsidence at Muan Haengbok Elementary School and the related construction work.


According to the response, the ground subsidence was first detected on August 5, 2025. At the time, part of the asphalt on an internal access road at the school had sunk. The repair work was subsequently included in the 2026 main budget and was completed between May 14 and September 30, 2026.


Of the total construction cost of about 266 million won, which Councilor Jeong had initially questioned, 33,229,993 won was spent on repairing the sunken section of asphalt, accounting for 12.48% of the total. The rest was identified as the cost of an elevator expansion project.


Regarding the key issue of who was responsible, the response indicated that it would be difficult to hold the construction company liable. The response listed the defect liability periods by type of work for the new construction project commissioned by the provincial education office in 2019. The periods for the key civil engineering and landscaping work ran from October 7, 2020, to October 6, 2022.



By the time the subsidence was discovered in August 2025, the construction company's legal liability period for the civil engineering work had already expired nearly three years earlier. The defect liability periods for the reinforced concrete and steel-frame work had also expired on October 6, 2025.


This content was produced with the assistance of AI translation services.

© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.

Today’s Briefing