When an LNG carrier enters Gwangyang Bay, two tugboats pull alongside and push its enormous hull toward the unloading dock. Once the vessel is in position, four mechanical arms at the dock lower and connect to the vessel's manifolds. Three are unloading arms that transfer LNG from the vessel, while the fourth is a vapor return arm that sends gas back to the vessel to equalize tank pressure.

A view of POSCO International's Gwangyang LNG terminal. Bridges and pipelines connect the offshore unloading dock to the storage tanks on land. POSCO International

A view of POSCO International's Gwangyang LNG terminal. Bridges and pipelines connect the offshore unloading dock to the storage tanks on land. POSCO International

View original image

During a visit on November 2 to POSCO International's Gwangyang LNG Terminal in the Gwangyang National Industrial Complex in Jeonnam-Gwangju Integrated Special City, the unloading dock was seen floating at the end of a bridge extending more than 700 meters out to sea. Liquefied natural gas, cooled to minus 162 degrees Celsius to reduce its volume to one-six-hundredth, flows through pipelines on the bridge to storage tanks on land. According to Kim Woo-heon, head of the Terminal Operations Group in POSCO International's Terminal Business Office, it takes around 10 hours to transfer the 68,000 to 70,000 tons carried by a fully loaded 174,000-cubic-meter LNG carrier, one of the most commonly used vessel sizes in the world. It takes about 26 hours from a vessel's arrival until it has unloaded its cargo and departed.


On November 10, POSCO International held a comprehensive completion ceremony for Terminal 2 at the site. Around 100 people attended, including POSCO Group Chairman Jang In-hwa, POSCO International President Lee Gye-in, National Assembly member Kwon Hyang-yeop, Korea Development Bank Chairman Park Sang-jin, and Gwangyang Mayor Park Seong-hyeon.


The addition of two 200,000-kL storage tanks, Nos. 7 and 8, increased total storage capacity from 930,000 kL to 1.33 million kL. According to POSCO Group, that is enough gas for heating to meet the needs of the entire population for about 40 days. The project cost KRW 949.2 billion and took 47 months to build. Gwangyang Terminal began commercial operations in 2005 as South Korea's first privately owned LNG import terminal and has expanded several times since.


Terminal 2 is different in scale, starting with its berth. The berth at Terminal 1 could accommodate vessels of up to 180,000 cubic meters, while the new berth can accommodate the ultra-large Q-Max class, or LNG carriers of up to 270,000 cubic meters. The unloading dock is located far out at sea because of the water depth. A depth of at least 14 meters is needed for large LNG carriers to berth, but the sea in front of the terminal is only 4 to 5 meters deep even at its deepest points. So instead of dredging the seabed, the company extended the bridge far out to sea.


The reason a steelmaker is expanding its gas tanks on the coast lies in the group's strategy. At the CEO Investor Day in July, Chairman Jang personally announced the "Triple Core" strategy, which will reorganize the business portfolio around industrial resources (steel), strategic resources (lithium, anode and cathode materials, and others), and energy resources (LNG and renewable energy). Choi Dong-yong, head of the Management Strategy Office at POSCO Holdings, who oversees the strategy, said at an on-site briefing on November 2: "Steel currently accounts for 50% of revenue and 70% of operating profit, but by 2035 we aim to create a structure in which the three pillars contribute almost equally to earnings." He explained that, as geopolitical risks grow for South Korea, which imports all of its energy, the group sees "resources" as central to industrial security and plans to expand its LNG business.


Its results also support this direction. According to POSCO International, KRW 399.6 billion, or about 51%, of its KRW 786.5 billion in operating profit in the first half of this year came from its energy business. The business model involves producing gas from fields in Myanmar and Australia, storing and trading it at the Gwangyang terminal, and operating power plants in places such as Incheon. POSCO Group aims to grow its energy division, which recorded KRW 4 trillion in revenue and KRW 600 billion in operating profit last year, to KRW 9 trillion in revenue and KRW 1.4 trillion in operating profit by 2031.


The terminal is also broadening its revenue sources beyond storage. Seo Gi-sik, head of the Terminal Construction Promotion Unit on POSCO International's Energy Construction Task Force, said that the terminal itself has a stable, if modest, profit margin, and that profitability varies depending on the scale of its ancillary businesses. One example is commissioning new LNG carriers built at domestic shipyards by loading them with LNG to test their systems. This year, the company also commissioned an ammonia carrier for the first time. It also provides LNG bunkering services to vessels berthed at the terminal. A new 20,000-cubic-meter bunkering berth has been built at Terminal 2. Starting in the second quarter of 2027, the company will also begin ship-to-ship (STS) bunkering, in which a 12,500-cubic-meter bunkering vessel currently under construction will deliver fuel directly to LNG-powered vessels at sea. Construction of an air separation unit that uses the cold energy released when LNG is regasified to produce oxygen and nitrogen will begin next year. Using this cold energy can save 25% to 30% of the electricity required.

A 200,000-kiloliter storage tank at POSCO International's Gwangyang LNG Terminal 2, completed on the 10th. POSCO International.

A 200,000-kiloliter storage tank at POSCO International's Gwangyang LNG Terminal 2, completed on the 10th. POSCO International.

View original image

The tanks incorporate the group's steelmaking technology. Seo compared a tank to a pressure cooker. The structure consists of an inner vessel and an outer shell, with insulation between them. The inner vessel, which comes into contact with LNG at minus 162 degrees Celsius, requires materials that retain their strength at extremely low temperatures. Tanks Nos. 1 to 4 use 9% nickel steel, while tanks Nos. 5 to 8 use high-manganese steel, which POSCO was the first in the world to develop. High-manganese steel, made by mixing 22.5% to 25.5% manganese with iron, retains its properties even at minus 196 degrees Celsius. Manganese is abundant and inexpensive, making the steel about 30% cheaper than 9% nickel steel. POSCO E&C handled the construction. In effect, the company that makes steel is building an energy storage facility with its own steel and filling it with gas.


The company is also bringing in LNG from North America. In 2022, POSCO International signed a contract with U.S. company Cheniere Energy to import 400,000 tons of LNG annually for 20 years. The first shipment under the contract will arrive at the Gwangyang terminal this month aboard the dedicated carrier HL Fortuna. This is the first time POSCO International has imported North American LNG under a long-term contract. The terminal has also set aside land for tanks Nos. 9 to 12. The company is discussing further expansion with the Ministry of Trade, Industry and Energy in line with the government's LNG supply and demand plan.



At the completion ceremony on November 10, Chairman Jang said, "The completion of Gwangyang LNG Terminal 2 is a clear result of our efforts to put POSCO Group's energy resources strategy, one of the Triple Core pillars, into practice. With this completion, we will strengthen the LNG value chain and contribute to national energy security."