KEPCO President Kim Dongcheol: "Electricity Rates Need at Least a Modest Adjustment... Industrial Hikes a Last Resort"
Highlights need to adjust electricity rates amid 34 trillion won in accumulated deficits and power grid investment burden
"Fuel cost adjustment system is not working properly"... calls for improvements to rate system
Confident power supply to Honam semiconductor cluster by 2028... transformer procurement remains a variable
Kim Dongcheol, president of Korea Electric Power Corporation (KEPCO), answers reporters' questions at a press briefing with the Ministry of Climate, Energy and Environment press corps at the Kimdaejung Convention Center in Gwangju on the 4th. KEPCO
View original imageKim Dongcheol, president of Korea Electric Power Corporation (KEPCO), said electricity rates need to be adjusted at least modestly to address accumulated deficits and expand the national power grid. However, he stressed that further increases in industrial electricity rates should be a last resort, as several previous hikes have already offset a substantial portion of the accumulated deficits in that sector. He expressed confidence that KEPCO would be able to supply power to the Honam semiconductor cluster by the end of 2028, while identifying equipment procurement issues amid a global shortage of transformers as a potential variable.
At a press briefing with reporters covering the Ministry of Climate, Energy and Environment during BIXPO 2026 at the Kim Dae-jung Convention Center in Gwangju on Nov. 4, Kim said, "Expanding the power grid is urgent as we pursue the three major mega-projects, and several issues are intertwined, including compliance with the limit on bond issuance. Ultimately, we need to discuss with the government how to achieve at least a modest adjustment to electricity rates and resolve this issue one way or another."
This is because demand for large-scale power grid investment and the burden of accumulated deficits are both growing. KEPCO suffered massive losses as international energy prices surged following the Russia-Ukraine war. Although the company has since worked to improve its financial structure, its accumulated deficit still stands at about 34 trillion won. Kim explained, "At the time of the Russia-Ukraine war, European countries reflected rising fuel costs in electricity rates, and rates rose by as much as three to five times in some countries. We were unable to reflect those costs sufficiently."
He expects the expansion of power grid investment under the government's three major mega-projects and the 12th Basic Plan for Electricity Supply and Demand to further increase the financial burden. KEPCO estimates that annual demand for power grid investment, previously projected at around 12 trillion won, could rise to around 14 trillion won as electricity demand grows from new industrial complexes, artificial intelligence (AI) data centers and other sources.
"Expanding the power grid to ensure a stable electricity supply is one of KEPCO's core responsibilities," Kim said, adding, "It is not sustainable to fund this through bond issuance or external borrowing." He stressed, "Accumulated deficits should at least be addressed through revenue from electricity sales, and it is also appropriate to fund power grid expansion with KEPCO's own revenue."
However, he took a cautious stance on further increases in industrial electricity rates. "Rates for industrial users have been raised several times, and as far as I know, the accumulated deficits in the industrial sector have been almost entirely addressed," Kim said. "Given that, I think an increase in industrial electricity rates should be a last resort."
He also stressed the need to make the current fuel cost adjustment system more effective. "The fuel cost adjustment system has been introduced, but it is not functioning properly," he said. "If we make it more responsive to actual costs, we can signal to the public that electricity rates do not only go up, but can also fall when international fuel prices decline."
KEPCO plans to continue its own efforts to improve its financial structure. Kim said, "Over the four years from 2022 through last year, we carried out self-help measures worth 15 trillion won. This year, we expect to exceed our initial target of 2.2 trillion won and achieve about 2.5 trillion won."
Kim Dongcheol, president of Korea Electric Power Corp. (KEPCO), answers reporters’ questions at a press briefing with journalists from the Ministry of Climate, Energy and Environment at BIXPO 2026 at the Kimdaejung Convention Center in Gwangju on the 4th. KEPCO
View original imageKim expressed confidence about the power supply schedule for the Honam semiconductor cluster. "We have formed a consultative body involving the Ministry of Climate, Energy and Environment and local governments to arrange power supply for the cluster," he said. "If we finalize the specific transmission line route related to Jangrok Wetland by the end of this year and begin construction early next year, there should be no problem supplying power by the end of 2028."
KEPCO plans to resolve the selection of transmission line routes, the biggest obstacle to construction, by the end of this year and shorten the construction period by applying new methods. A KEPCO official explained, "In the past, construction took a long time because rebar was assembled and concrete poured on site. Recently, however, we have been able to use construction methods in which structures manufactured at a plant are installed on site. We plan to use this approach to meet the target of completing construction by the end of 2028."
Transformer procurement remains a potential variable. "There are no major procurement issues with overhead wires, cables or switchgear, but amid rising global demand, it takes about three years to receive transformers," Kim said. "Because the project schedule for the Honam semiconductor cluster is tight, transformer procurement could become a problem."
KEPCO plans to respond by adjusting equipment procurement schedules for substation construction projects underway across the country. "Some projects may be delayed while others may move faster, so we are considering ways to manage equipment procurement schedules flexibly," Kim said. "This does not mean we intend to sacrifice a particular region to push ahead with the Honam semiconductor cluster."
Kim made clear that he considers the introduction of a locational marginal pricing (LMP) system necessary. "If transmission constraints mean that expensive LNG generators have to be operated in the Seoul metropolitan area, it is appropriate to apply those costs to that area," he said. "Applying the same costs to generators outside the capital region is not appropriate, either in theory or in practice."
However, he said measures would be needed to address the reduced revenues that power generators could face following the introduction of the LMP system. "It is true that generators outside the capital region would see their revenues decline," Kim said. "Renewable energy operators participating in the spot market could face particular difficulties, so the government needs to review the system to ensure that no one suffers unfair harm." He nevertheless stressed, "Even with those concerns, I believe the LMP system must be introduced."
KEPCO plans to accelerate the development of direct current (DC) distribution networks to address the spread of renewable energy and AI data centers. "Directly connecting DC power sources to equipment that uses DC can reduce losses during power conversion," Kim said. "We will expand DC-based power grids and lead the development of global standards, making this a new growth engine."
KEPCO plans to apply DC distribution technology at the new buildings for its Gangwon and Gyeonggi regional headquarters and, in cooperation with private companies, expand its use to data centers, industrial facilities and other sites. A KEPCO official explained, "Last year, we formed the K-DC Alliance, which includes the government, industry and academia, and we are also working on technical standards and demonstration projects related to low-voltage DC distribution."
KEPCO also presented its AI-powered virtual power grid technology, showcased at BIXPO, as a means of supporting power grid expansion. The technology recreates the entire national power system in a virtual space and uses AI to repeatedly simulate transmission grid investment, fault analysis and the capacity to accommodate renewable energy, among other factors. KEPCO is targeting commercialization around 2031 to 2032.
KEPCO expects the integration of public power generation companies to help improve its financial structure. A KEPCO official explained, "Even after the integration, the power generation companies are expected to remain wholly owned subsidiaries of KEPCO. Unifying fuel purchases, facility investment and procurement would reduce costs through economies of scale and would also help improve the consolidated financial statements."
Kim declined to comment directly on the breakdown of negotiations for a construction contract for the Czech Republic's Dukovany nuclear power plant between Korea Hydro & Nuclear Power (KHNP) and a consortium of Daewoo E&C and Doosan Enerbility. "It is difficult to comment because I have not been able to properly understand the details of the dispute between KHNP and the construction company from beginning to end," he said.
Regarding the settlement issue over the Barakah nuclear power plant in the United Arab Emirates (UAE), a project that had also led to a dispute with KHNP, Kim said, "KEPCO is also in a position where there is a potential dispute with KHNP or Team Korea. We first need to resolve the settlement issue with the UAE client, so we are asking the companies involved to wait."
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
A KEPCO official also explained, "We have agreed to resolve the settlement issue with the client first and then proceed with follow-up negotiations with our partners. We will also review the relevant details with KHNP and prepare measures to prevent similar issues from arising in future overseas nuclear power projects."