LS Cable & System, LS Marine Solution Move Ahead with Submarine Cable Supply and Installation for Taean Offshore Wind Project
Agreement signed to secure production and installation schedules
Main contract to be signed within the year; completion targeted for 2030
7,000-ton-class submarine cable-laying vessel to be deployed
LS Cable & System and LS Marine Solution are moving ahead with the submarine cable business for the 504 MW Taean Offshore Wind Power Project.
LS Cable & System and LS Marine Solution announced on November 2 that they had signed a CRA (agreement to secure production and installation schedules) with Taean Wind Power Co., Ltd. for the supply and installation of submarine cables.
A CRA is an agreement to secure schedules in advance for cable production facilities and installation vessels before signing the main contract.
The two companies were selected as preferred bidders in 2024, and this agreement gives concrete shape to their participation in the project. They are currently conducting cable engineering and preliminary surveys while reviewing cable specifications and the scope of installation. They plan to finalize detailed terms, including the contract value, within this year and sign the main contract.
Taean Offshore Wind Power is a project jointly developed by Korea Western Power, Singaporean renewable energy company Vena Energy, and Danish renewable energy investment and development firm Copenhagen Infrastructure Partners (CIP). The project will be built offshore near Taean County, South Chungcheong Province, with completion targeted for 2030.
This is the second large-scale offshore wind project in which LS Cable & System and LS Marine Solution are participating together, following the Shinan-Ui Offshore Wind Power Project. LS Marine Solution plans to deploy its submarine cable-laying vessel GL2030, which has been upgraded to a capacity of 7,000 tons.
Building on their experience delivering large-scale offshore wind projects in Korea and overseas, the two companies plan to step up efforts to capture a greater share of Korea's offshore wind market, which aims to reach 55 GW of installed capacity by 2035.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
An LS Cable & System official said, "Given the unique installation conditions at sea, it is important to closely coordinate cable production and installation to improve on-site responsiveness and accountability. We will ensure the main contract proceeds smoothly and expand our efforts to capture a greater share of Korea's offshore wind market."
© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.