Agreement signed to secure production and installation schedules
Main contract to be signed within the year; completion targeted for 2030
7,000-ton-class submarine cable-laying vessel to be deployed

LS Cable & System and LS Marine Solution are moving ahead with the submarine cable business for the 504 MW Taean Offshore Wind Power Project.


LS Cable & System and LS Marine Solution announced on November 2 that they had signed a CRA (agreement to secure production and installation schedules) with Taean Wind Power Co., Ltd. for the supply and installation of submarine cables.


A CRA is an agreement to secure schedules in advance for cable production facilities and installation vessels before signing the main contract.


The two companies were selected as preferred bidders in 2024, and this agreement gives concrete shape to their participation in the project. They are currently conducting cable engineering and preliminary surveys while reviewing cable specifications and the scope of installation. They plan to finalize detailed terms, including the contract value, within this year and sign the main contract.


LS Marine Solution's submarine cable-laying vessel GL2030. LS Corp.

LS Marine Solution's submarine cable-laying vessel GL2030. LS Corp.

View original image

Taean Offshore Wind Power is a project jointly developed by Korea Western Power, Singaporean renewable energy company Vena Energy, and Danish renewable energy investment and development firm Copenhagen Infrastructure Partners (CIP). The project will be built offshore near Taean County, South Chungcheong Province, with completion targeted for 2030.


This is the second large-scale offshore wind project in which LS Cable & System and LS Marine Solution are participating together, following the Shinan-Ui Offshore Wind Power Project. LS Marine Solution plans to deploy its submarine cable-laying vessel GL2030, which has been upgraded to a capacity of 7,000 tons.


Building on their experience delivering large-scale offshore wind projects in Korea and overseas, the two companies plan to step up efforts to capture a greater share of Korea's offshore wind market, which aims to reach 55 GW of installed capacity by 2035.



An LS Cable & System official said, "Given the unique installation conditions at sea, it is important to closely coordinate cable production and installation to improve on-site responsiveness and accountability. We will ensure the main contract proceeds smoothly and expand our efforts to capture a greater share of Korea's offshore wind market."