"Construction costs account for 7-11 percentage points more of total project costs," KHNP says, trading blame with Daewoo E&C
Competitive bidding planned for new contractor; government to manage project schedule directly

Government Activates Emergency Management System for Czech Nuclear Plant as KHNP-Daewoo E&C Dispute Intensifies View original image

The government is activating an emergency management system led by the minister and vice ministers after negotiations on the construction contract for the Czech Republic's Dukovany nuclear power plant project ended in a final breakdown. As a dispute over construction costs and contract terms between Korea Hydro & Nuclear Power (KHNP) and the consortium of Daewoo Engineering & Construction and Doosan Enerbility dragged on, the government stepped in to manage the project schedule directly. KHNP has pointed to the contractor's demands to change the contract terms and its allegedly excessive construction cost estimates as the reasons for the breakdown, intensifying the dispute over which side is responsible.


Government Activates Emergency Management System for Czech Nuclear Plant as KHNP-Daewoo E&C Dispute Intensifies View original image

According to the Ministry of Trade, Industry and Energy on Nov. 2, Minister Kim Jeonggwan decided to activate an emergency management system led by the minister and vice ministers in response to the end of negotiations on the construction contract for the Czech Republic's Dukovany nuclear power plant on Oct. 29. The move aims to minimize project delays resulting from a change of contractor and maintain confidence in "On Time, On Budget" construction, a key competitive advantage of Korea's nuclear industry.


The ministry will alternate weekly between a "Meeting to Review the Progress of Team Korea's Czech Nuclear Power Project," chaired by the minister, and a "Meeting to Review KHNP's Action Plan," chaired by a vice minister. KHNP and the companies participating in the project will share progress and key issues, while the government directly reviews any necessary measures.


The first meeting was held that morning, chaired by Vice Minister Park Dongil. Participants focused on plans for carrying out key work following the end of negotiations on the existing construction contract; the process and timeline for selecting a new contractor; plans to meet key construction milestones; and follow-up measures related to the construction contract.


The government plans to develop measures to keep key milestones on schedule, including applying for a construction permit in April 2027, beginning site preparation in January 2029, and starting construction in November of the same year. Since a new contractor must be selected and a contract signed following the breakdown in negotiations with the existing contractor, the government will manage the follow-up process to ensure it does not affect the overall project schedule.


Meanwhile, KHNP maintains that the breakdown in negotiations with the existing consortium was unavoidable. According to KHNP, the two sides held 91 rounds of discussions over approximately 15 months after signing the main contract for the Czech nuclear power project, but failed to bridge their differences over the contract structure and construction costs.


The sharpest disagreement concerned how construction costs would be calculated. KHNP said Daewoo Engineering & Construction had initially proposed a lump-sum fixed-price contract during the 2022 initial bidding, but then requested a switch to a quantity-based settlement method during the final bidding stage in 2024. KHNP said the contractor continued to seek changes to the contract terms after winning the project in June last year, including requesting settlement after completion of the detailed design.


KHNP said the construction costs sought by Daewoo Engineering & Construction accounted for a share of total project costs that was approximately 7 to 11 percentage points higher than in nuclear power plant construction projects in Korea and overseas. When KHNP and the contractor failed to agree on construction costs during the final bidding in April 2024, KHNP submitted its bid using a price it had calculated independently. KHNP maintains that accepting the contractor's demands as they stood could have made the bid price excessively high and weakened its competitiveness.


The contractor, in contrast, claimed that KHNP had pressured it to lower unit prices to keep the total contract amount unchanged despite an increase in construction work, and had tried to shift responsibility for design errors and construction delays onto the contractor. KHNP countered that it had proposed a compromise that included reflecting anticipated increases in work quantities in the contract price in advance and allowing settlement based on actual costs for most civil engineering work, but that the contractor had rejected it.


KHNP also cited the risk of design delays resulting from the prolonged negotiations as a factor behind the termination of the contract. It said it had been difficult to extend negotiations further when the submission of design documents was expected to be delayed by several months due to issues managing local subcontractors in the Czech Republic. KHNP plans to replace its previous negotiated contract approach with competitive bidding to select a new contractor and to review construction costs and contract terms.



Minister Kim Jeonggwan said, "The competitiveness of Korea's nuclear industry comes from 'Team Spirit,' with the capabilities of individual companies brought together. We must build an even stronger Team Korea in preparation for the many nuclear export opportunities ahead." He added, "For the time being, the minister and vice ministers will directly operate the emergency management system, review project issues every week, and take any necessary measures."