[Feature] Gwangju Urban Railway Line 2: Trains Have Arrived, but When Can Residents Ride?
1994 Basic Plan Approved, Construction Began in 2019... Train Unveiled on October 21
Phase 1 Civil Engineering Work 99% Complete... Opening Target Set for December 2028
Phase 2 Progress at 13.4%... Opening in 2035, Partial Opening Under Consideration
Two-Car Trains to Carry Up to 153 Passengers... Crowding Concerns and Safety Challenges at Unmanned Stations
The trainsets for Gwangju Urban Railway Line 2 have been unveiled for the first time. This comes seven years after construction began in 2019, following changes to the route and construction method and public consultations, after the basic plan was approved in 1994. Civil engineering work on Phase 1 is now 99% complete, but follow-up work, including the installation of electrical, communications and signaling equipment and test runs, remains. Gwangju Special City has set December 2028 as the opening target for Phase 1 and December 2035 for Phase 2.
On the 21st, an official inspects a subway train unveiled for the first time at the inspection depot of the Gwangju Metro Line 2 vehicle depot in Yuchon-dong, Seo-gu, Gwangju, Jeollanam-do. Photo by Song Bohyeon
View original imageOn the morning of October 21, at the inspection depot at the Line 2 vehicle base in Yuchon-dong, Seo-gu, Gwangju, a train delivered on a trailer was lowered onto the tracks. After workers connected the two cars and completed their inspection, the passenger compartment was opened to the public. It was fitted with seats, handrails and information screens. The train will operate automatically without a driver, so it has no separate driver's cab.
Existing Gwangju Urban Railway Line 1 is a heavy-rail system, with four cars per trainset and a total length of about 72 meters. Line 2, by contrast, is a light-rail system, with two cars per trainset and a total length of 20.9 meters. The cars are 2.75 meters wide on Line 1 and 2.4 meters wide on Line 2. Line 2 uses rubber tires instead of steel wheels and has a maximum operating speed of 70 kilometers per hour. The overall plan calls for 33 trainsets, or 66 cars: 17 trainsets (34 cars) for Phase 1 and 16 trainsets (32 cars) for Phase 2.
Repeated Changes to Route and Construction Method from Initial Plan to Start of Construction
Gwangju Urban Railway Line 2 received government approval of its basic plan in March 1994, together with Line 1. At the time, Line 2 was envisioned as a route connecting the northern and southern parts of Gwangju.
In October 2002, while construction of Line 1, which had begun in 1996, was underway, the basic plan for Line 2 was revised to make it a loop line around the city center. The plan called for an elevated route 27.4 kilometers long with 34 stations, at a total project cost of KRW 1.3375 trillion. The government approved the revised basic plan.
Debate continued over the route and construction method for Line 2. Following a preliminary feasibility study in 2010, a revised basic plan extending the route to 41.7 kilometers was approved in November 2011. In December 2013, the construction method was changed from an elevated route to a shallow underground system.
Stage-by-stage route map of Gwangju Metro Line 2. Provided by Jeonnam-Gwangju Integrated Special City.
View original imageIn 2014, whether to proceed with the project was reconsidered. In 2018, the question of whether to build the line was put to public consultation. Of the 243 members of the citizen panel who took part in the final survey, 191, or 78.6%, supported construction. Gwangju City accepted the result and began construction in September 2019.
After construction began, some work was delayed when unexpected bedrock and underground utilities were discovered. The time needed for follow-up work and test runs was also not adequately accounted for in the original schedule.
When construction began, Phase 1 was targeted to open in 2023, but after several schedule revisions, the target was pushed back to December 2028. The opening target for Phase 2 was also changed from December 2030 to December 2035.
Phase 1 Civil Engineering Work 99% Complete; Phase 2 Progress at 13.4%
Most of the civil engineering work on Phase 1 of Gwangju Urban Railway Line 2 has been completed. According to data released by Gwangju Special City in early October, civil engineering work is 99% complete. All roads where traffic had been restricted due to construction have reopened. By contrast, follow-up work, including station construction and the installation of electrical, communications and signaling equipment, is about 50% complete on average. Vehicle performance tests and comprehensive railway test runs also remain to be completed.
As of early October, overall progress on Phase 2 stood at 13.4%. Work had not begun in Contract Sections 7 and 10, around Chonnam National University and Bonchon Industrial Complex, after five bidding rounds ended without a successful bid. Construction in Contract Section 13, which passes through Suwan District, has been suspended in some areas due to site conditions, including an underpass and transmission lines. A redesign is underway to reroute the affected section along the service road beside Pungyeongjeongcheon Stream.
On October 2, Gwangju Special City released the findings of a comprehensive review of the project and explained that its management had focused on civil engineering work, leaving follow-up work in areas such as architecture, mechanical systems, electrical systems and communications, as well as the test-run schedule, insufficiently accounted for.
Jeonnam-Gwangju Integrated Special City Mayor Min Hyungbae speaks about the achievements of the first 100 days and the city administration's future direction at a press conference marking the special city's first 100 days, held at the Gwangju City Hall on the morning of the 8th. Photo by Song Bohyun
View original imageAt a press conference marking his 100th day in office on October 8, Jeonnam-Gwangju Integrated Special City Mayor Min Hyung-bae said, "Each work schedule was managed separately, and there was not enough coordination between them." He added, "If Phase 1 is delayed, Phase 2 will naturally be delayed as well, yet continuing to tell residents that it will open in 2030 is disrespectful to them."
The city's review findings included plans to manage civil engineering, construction, electrical and communications work as an integrated schedule, and to release monthly updates on progress, causes of delays and response measures.
A recently released comprehensive audit of the Urban Railway Construction Headquarters also identified 24 issues. The Audit Committee pointed out, among other things, that the city had not followed the procedures for revising the basic plan, even though the existing opening target was difficult to meet given the actual construction schedule.
The total project cost has also risen. It was KRW 1.7394 trillion at the time of the 2010 preliminary feasibility study and has now reached KRW 3.243 trillion. Of the KRW 1.5036 trillion increase, inflation accounted for the largest share at KRW 1.0021 trillion. The increase also includes costs arising from changes to the construction method and from changes in design and site conditions.
Two-Car Trains to Carry Up to 153 Passengers; Concerns over Capacity and Platform Safety
After the train was unveiled, some residents expressed concern about whether trains smaller than those on Line 1 would be able to handle commuter demand. Others said the trains should have been designed from the outset to allow more cars to be connected.
Each trainset can carry up to 623 passengers on Line 1 and 153 on Line 2. The Line 2 figure comprises 36 seated passengers and 117 standing passengers, about one-quarter of Line 1's capacity.
According to demand forecasts from Gwangju Special City, an estimated 88,000 or so passengers will use Line 2 each day when Phase 1 opens, rising to about 191,000 when Phase 2 is also open. The projected daily ridership across the entire line is 3.9 times the approximately 49,000 passengers who currently use Line 1.
The interior of a train for Gwangju Metro Line 2, unveiled for the first time on the morning of the 21st at the depot inspection facility in Yuchon-dong, Seo-gu, Jeonnam Gwangju. Each two-car train can carry up to 153 passengers, including 36 seated and 117 standing. Photo by Song Bohyeon.
View original imageA 2022 operations report estimated that, because train travel times would be longer than originally planned, 40 trainsets - seven more than the existing plan - would be needed to maintain four-minute-and-30-second intervals during rush hour once Phase 2 is complete.
The Audit Committee also presented an analysis that crowding could reach 201.2% if the line were operated with 31 trainsets using the travel times calculated in the 2022 operations report. That would exceed the 150% full-capacity benchmark used in the audit materials. However, this analysis applied past demand forecasts and specific operating conditions; it does not reflect actual crowding after the line opens.
The train intervals presented by Gwangju Special City at the train unveiling on October 21 were four minutes and 30 seconds to five minutes during rush hour and eight to 10 minutes at other times. These figures have not yet been finalized. Simulation results showed a lower average operating speed than originally planned, so the operating plan requires further review.
Platform safety was also flagged in the audit. Fifteen of the 20 Phase 1 stations were planned to be unmanned, with no staff on duty at all times. A March audit found that there were inadequate measures to provide guidance during periods of heavy passenger congestion or control the number of people entering stations.
In its response to the Audit Committee, Gwangju Special City proposed using CCTV to monitor crowding in real time and make announcements, establishing ways to control passenger flows, and revising scenarios for driverless operations.
Main-Line Test Runs Next Year; Early Opening of Some Phase 2 Sections Under Consideration
Trainsets for Line 2 began arriving at the vehicle base on October 14. The city aims to complete delivery of the Phase 1 trainsets by November 2026.
According to the schedule presented by Gwangju Special City, test runs at the vehicle base will continue through July 2027. Main-line test runs are scheduled to take place from the second half of 2027 through June 2028. After comprehensive test runs linking the trains with signaling, communications and other facilities, the city aims to open Phase 1 in December 2028.
Bae Migyeong, spokesperson for Jeonnam-Gwangju Integrated Special City (center), announces the opening schedule for Gwangju Subway Line 2 and plans for a partial opening of Phase 2 at the City Hall briefing room on the 2nd. On the left is Park Geumhwa, head of the Urban Railway Construction Headquarters. Photo by Song Bohyeon.
View original imageA plan is under consideration to open first the 11.9-kilometer section of Phase 2 from Yangsan-dong through Cheomdan, Suwan and Singa Districts, which includes nine stations. The early opening target is April 2034, one year and eight months ahead of the overall target of December 2035.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
However, a partial opening has not been confirmed. Procedures with central government agencies, including revisions to the basic plan and discussions on the total project cost, remain to be completed. Roads along the Yangsan-Singa section of Phase 2 are targeted to reopen in the first half of 2030.