Daewoo Engineering & Construction and Doosan Enerbility Express Regret Over Breakdown in Negotiations
"No Explanation for Contract Changes... Call for Return to Negotiations"

Regarding the breakdown of the construction contract for the Dukovany nuclear power plant in the Czech Republic, the construction consortium of Daewoo Engineering & Construction and Doosan Enerbility said on October 29, "We were not given sufficient time to review the proposed contract submitted by the prime contractor, Korea Hydro & Nuclear Power (KHNP), on October 7 after it changed the subcontract terms."


Earlier, KHNP, the prime contractor, announced today that it had declared negotiations with the construction consortium over a subcontract for the main works unsuccessful and would select a new construction company. Today was the deadline KHNP had set for the contract negotiations. Daewoo Engineering & Construction and Doosan Enerbility have worked together since being selected in 2018 as construction partners for Team Korea's Czech nuclear power plant project, through their selection as preferred negotiating parties in May 2024 and the signing of the main contract in June 2025. Negotiations between the prime contractor and the construction consortium over the scope of work, project costs and other details had been marred by repeated disputes, and today they officially decided to part ways.


The consortium said, "After the main contract was signed, we continued negotiations with the prime contractor on a subcontract for the main works at the new nuclear power plant, and communicated our willingness to accept the unit prices for the work that we had submitted to KHNP in January 2024." It added, "Even through the deadline for negotiations today, we made every effort to reach a subcontract agreement with the prime contractor, including submitting a revised contract proposal with the amount reduced to a level at which we could bear the losses. We are deeply disappointed by the announcement that negotiations had broken down."

A panoramic view of Dukovany, the planned site for a new nuclear power plant in the Czech Republic. Photo provided by Yonhap News and Daewoo E&C.

A panoramic view of Dukovany, the planned site for a new nuclear power plant in the Czech Republic. Photo provided by Yonhap News and Daewoo E&C.

View original image

The construction companies claimed that KHNP did not provide specific reasons when it presented revised contract terms early this month. They said they had asked to extend the negotiation deadline until the end of this year so they could thoroughly review the changes, but that the prime contractor refused. The construction companies said, "Because this Czech nuclear power plant project will be the first commercial nuclear power plant anywhere in the world to use the APR1000 model, the construction costs, schedule and scope of work must be finalized through thorough advance preparation and research. However, it was simply unrealistic to require us to determine our final position and conclude negotiations within just three weeks, without guaranteeing sufficient time for review."



KHNP is reportedly arguing that a lump-sum construction contract is a contract type that meets international standards. The construction companies countered that requiring them to bear a high proportion of additional work resulting from design changes, without any corresponding adjustment to construction costs, does not meet international standards when they are not in a position to participate in the basic or detailed design of the nuclear power plant. The construction companies said, "The new terms proposed by the prime contractor inherently involve risks that could threaten the survival of private companies, so the construction consortium needs more time for a more detailed review."

Artist's rendering of the new nuclear power plant in Dukovany, Czech Republic. Provided by Korea Hydro & Nuclear Power.

Artist's rendering of the new nuclear power plant in Dukovany, Czech Republic. Provided by Korea Hydro & Nuclear Power.

View original image

The construction companies stressed that they could not accept a unilateral declaration that negotiations had broken down. They argued that refusing to continue negotiations unless the prime contractor's proposal was accepted, despite the negotiating environment having changed dramatically, was also inconsistent with the principle of good faith in contracts. They said, "Even now, we ask the prime contractor to once again engage in amicable negotiations with the construction consortium in the broader interest of the country and the national interest."