The AIDC Paradox: Why Did Meta Leave RE100? [Energy Odyssey] 14
III. The Dream of Electrification
Surging AI Data Center Power Demand Drives Growth in Gas-Fired Generation
U.S. Big Tech Companies Move to Diversify Energy Sources
RE100's Limitations... Google Announces 24/7 CFE Goal
Nuclear Power Likely to
Solaseado, a future energy city being developed across 20,899,330 square meters (about 6.32 million pyeong) in Guseong-ri, Sani-myeon, Haenam County, South Jeolla Province. The groundbreaking ceremony for the National AI Computing Center was held here this past August. The plan is to build a national AI computing hub to support the training and research of large-scale AI models by installing 15,000 graphics processing units (GPUs) by 2028. In effect, it will be a state-operated AI data center.
One reason the National AI Computing Center is being built in Solaseado is the abundance of renewable energy nearby. Solaseado is home to one of the largest solar power complexes in South Korea, equipped with 98 megawatts (MW) of solar power generation capacity and a 306-megawatt-hour (MWh) energy storage system (ESS) on a site of approximately 158 square meters (about 480,000 pyeong). Haenam is making every effort to leverage these strengths and have Solaseado designated as a national industrial complex for RE100 (using 100% renewable energy).
RE100 is a term that symbolically represents the Lee Jae-myung administration's policy of expanding renewable energy. RE100 is a global campaign led by the UK-based nonprofit organization The Climate Group, through which companies pledge to source 100% of the electricity they use from renewable energy.
Major big tech companies, including Apple, Google, and Microsoft (MS), are members. As of 2026, 36 South Korean companies, including Samsung Electronics, SK hynix, Hyundai Motor, and LG Energy Solution, are participating in RE100 as members.
Separately from the global campaign, the Ministry of Climate, Energy and Environment is implementing the K-RE100 policy, which aims to raise the share of renewable energy used by public institutions to 60% by 2030. Starting this year, the ministry plans to assess the K-RE100 performance of 88 public institutions subject to management evaluations and reflect the results in their evaluation criteria.
Institutions and companies participating in RE100 can have their compliance certified through various methods, including direct generation, power purchase agreements (PPAs), purchases of renewable energy certificates (RECs), and green pricing programs.
So how much of the RE100 target can the National AI Computing Center, being built in Haenam's Solaseado, one of the most renewable-energy-rich areas in South Korea, achieve?
Can Haenam's National AI Data Center Achieve RE100?
The National AI Computing Center is scheduled to be built in its first phase with a capacity of 40 MW. This means it will consume 40 MW of electricity per hour, requiring 960 MWh to operate for 24 hours a day.
Because it is located in the Solaseado complex, the National AI Computing Center can meet RE100 requirements through direct PPAs. This approach involves signing a power purchase agreement directly with a power generator without using the Korea Electric Power Corporation (KEPCO) grid.
Even if the center used all the power from Solaseado's 98 MW solar power plant and its 306 MWh ESS, they could supply the electricity needed by the National AI Computing Center for only about eight hours.
As a result, the center has little choice but to use the KEPCO grid rather than a direct PPA. Oh Taewon, head of the Korea AI Computing Center Co., Ltd. (KOACC), the joint venture established to build and operate the National AI Computing Center, said, "We plan to connect to Korea Electric Power Corporation's grid first and receive electricity through it. As the project is still in its early stages, we have not yet decided on the specific ways the center will use renewable electricity." Two years remain until the National AI Computing Center is scheduled for completion in 2028.
The National AI Computing Center said that receiving electricity through the KEPCO grid does not mean it will use no renewable energy at all. Oh said, "Although we will not receive renewable energy directly, you can understand it as receiving an indirect supply through the KEPCO grid of the abundant renewable energy produced in the region. We may also consider using distributed energy or receiving renewable energy directly in the future."
The consortium currently participating in the National AI Computing Center project comprises Samsung SDS, Naver Cloud, Samsung C&T, Kakao, Samsung Electronics, Klush, KT, Jeonnam-Gwangju Integrated Special City, and Seonamhaean Enterprise City Development. At the end of this past June, as part of the government's mega-projects, Samsung Group announced that Samsung SDS plans to invest KRW 17 trillion in Solaseado to build a 210 MW AI data center. This would make the center more than five times larger than it is now.
As the scale of AI data centers expands, so does the amount of electricity they need. Haenam's Solaseado plans to develop a 400 MW solar power complex by 2028, making it the largest solar power complex in South Korea on a single site, using 4.79 million square meters of idle land, including reclaimed land affected by saltwater. Of this, 10 MW will be developed as agrivoltaics.
Climate, Energy and Environment Minister Kim Seonghwan takes part in a groundbreaking ceremony for a solar power facility at a renewable energy complex in Haenam County, Jeonnam-Gwangju, announcing the start of construction on the country’s largest single-site solar power facility, with a capacity of 400 MW. August 7, 2026. Ministry of Climate, Energy and Environment
View original imageExpanding renewable energy alone will not immediately make it possible to supply electricity to AI data centers. Infrastructure such as ESS facilities is also needed to compensate for intermittency, which inevitably increases costs.
If renewable electricity is expensive, companies will see little reason to use it. Another key question is whether electricity can be supplied reliably around the clock using renewable energy alone.
What Happened When Meta Left RE100?
As AI data center construction spreads worldwide, securing electricity has emerged as a bottleneck. Big tech companies that had joined the RE100 campaign to achieve carbon neutrality and reduce greenhouse gas emissions are now facing difficult decisions in the age of AI. They believe renewable energy alone cannot provide enough electricity to operate large-scale AI data centers and are revising their strategies.
A notable example is Meta, the parent company of Facebook. In July, Meta acknowledged that it was no longer an RE100 member. Meta joined RE100 in 2016, when it was still known as Facebook, and said it had achieved RE100 in 2021.
According to Meta's sustainability reports, from 2020 through 2024 the company matched 100% of its annual electricity use with renewable energy. In a filing with the U.S. Securities and Exchange Commission (SEC) this past April, Meta also said it had matched 100% of its annual electricity use with clean, renewable energy since 2020.
Companies do not have to receive renewable energy directly from sources such as solar or wind power to achieve RE100. They can demonstrate their use of renewable energy through indirect methods, such as purchasing RECs, signing PPAs, or using green pricing programs.
In practice, companies receive electricity from a grid that does not identify where the power was generated. However, if they match their annual electricity use with renewable energy through REC purchases or PPAs, they are recognized as having achieved RE100. For example, a company called A that uses 1 gigawatt-hour (GWh) of electricity a year would be recognized as having achieved RE100 if it bought RECs covering 1 GWh or signed a contract with a wind farm for that amount of electricity.
Despite this, Meta left RE100 this past July. The Climate Group, which runs RE100, told The Asia Business Daily, "Meta had been an RE100 member since 2016. Following several in-depth discussions between Meta and The Climate Group, Meta withdrew from the RE100 initiative because its new investments in gas-fired power generation meant it could no longer meet the membership criteria."
Meta appears to have failed to meet RE100's technical criteria after increasing its investment in gas-fired power plants to ensure a stable and rapid electricity supply for its AI data centers.
Meta is building Hyperion, a massive data center in Louisiana. To supply electricity to the facility, it is investing in 10 natural gas-fired power plants with a combined capacity of 7.5 gigawatts (GW). Meta also plans to receive electricity from a 200 MW gas-fired power plant under construction in Ohio.
U.S. Big Tech Companies Diversify Their Power Sources
This is not just a Meta issue. U.S. big tech companies are also investing one after another in gas-fired power plants for their AI data centers, or signing purchase agreements for large-scale nuclear plants and small modular reactors (SMRs). They are diversifying their energy sources to secure power for AI.
On October 6, Google signed a long-term power supply agreement with Black Hills for a new gas-fired power plant to supply electricity to a data center being built in Wyoming. Black Hills will supply up to 590 MW of electricity to Google's data center through 2048. To do so, it plans to invest $1.8 billion (about KRW 2.4 trillion) to build a 564 MW gas-fired power plant.
Two days later, on October 8, Google signed a 3,950 MW PPA with Constellation, the largest nuclear power company in the United States. This is equivalent to the output of three to four 1 GW nuclear power plants. Constellation previously signed a long-term 835 MW power purchase agreement with MS in September 2024, followed by supply agreements with Meta for 1.1 GW in June 2025 and Amazon for 690 MW in September this year.
Amazon, too, is scrambling to secure power from sources including gas-fired plants and nuclear power. This past August, Amazon acquired the GW Ranch, a large data center complex in Pecos County, Texas. It plans to build three data centers there, along with a 7.65 GW gas-fired power plant.
In June, U.S. oil company Chevron signed an agreement with MS to supply electricity for 20 years from a 2.67 GW gas-fired power plant being built in Texas. Under this behind-the-meter arrangement, MS will build a data center near the power plant and receive electricity directly, without using the existing grid.
The increase in gas-fired power generation accompanying the expansion of AI data centers is also reflected in the statistics. According to an August 2026 report by market research organization Global Energy Monitor (GEM), plans for gas-fired power capacity in the United States totaled 378 GW in the first half of 2026. Half of this, or 189 GW, is tied directly to data center projects. Plans for gas-fired power generation linked to data centers have doubled in a year, rising from 97 GW last year.
Although they are increasing their use of nuclear and gas-fired power, U.S. big tech companies have not given up on investing in renewable energy. Meta says it is "working to match our data center electricity use with 100% clean and renewable energy."
Google's "24/7 CFE": How Does It Differ From RE100?
On October 6, at a parliamentary audit by the National Assembly's Trade, Industry, Energy, SMEs and Startups Committee, Minister of Trade, Industry and Energy Kim Jeong-kwan was asked about RE100 measures for the Yongin National Industrial Complex. He said, "On the issue of carbon neutrality, the companies that first raised this in the semiconductor industry are in fact giving up or postponing their efforts. Even companies like Google have now moved from RE100 to CF100 (Carbon Free 100). RE100 alone is no longer enough to meet demand from AI data centers and similar facilities."
Climate and environmental groups immediately disputed the minister's remarks. They said Google had never switched from RE100 to CF100. In a report published on October 22, renewable energy fact-checking platform Refact said that, after contacting The Climate Group directly, it had confirmed that "Google has never left RE100 to join CF100." Google has achieved RE100 for nine consecutive years, from 2017 through last year.
Still, the minister was not entirely wrong. His assessment that "RE100 alone is no longer enough to meet demand from AI data centers" is accurate.
Although Google remains an RE100 member, it does not treat RE100 as an absolute standard. Recognizing RE100's limitations, Google is pursuing the more demanding 24/7 CFE (Carbon-Free Energy) goal. The CF100 mentioned by the minister and Google's 24/7 CFE are different concepts.
In September 2020, Google announced that it would achieve 24/7 CFE by 2030, using carbon-free energy around the clock, every day of the year, at all its data centers and offices worldwide.
Unlike RE100, which matches renewable energy use on an annual basis, 24/7 CFE certifies the use of carbon-free energy hour by hour. It requires the use of carbon-free energy around the clock. Google considers 24/7 CFE better suited to achieving carbon neutrality in practice.
24/7 CFE has a broader scope than RE100 because it includes nuclear power as well as renewable sources such as solar and wind. Nuclear power is included because it is virtually impossible to match electricity generation with consumption hour by hour using intermittent sources such as solar and wind. Although companies are also investing in storage facilities such as ESS, supplying renewable energy around the clock requires massive investment.
CF100, meanwhile, refers to the CFE Initiative proposed by the Yoon Suk Yeol administration to the international community in 2023. The CFE Initiative covers not only renewable energy but also nuclear power, clean hydrogen, and carbon capture and storage (CCS) technologies.
The Yoon Suk Yeol administration formed the CF Alliance with participating private companies and pursued international standardization, but the effort fizzled out after the change in government. No decision was made on whether CF100 would use an annual matching system like RE100 or an hourly one, and no details have been made public on how it would be certified. Therefore, it is incorrect to say that Google switched to CF100.
Is Google's Approach the Answer?
Google's electricity use last year was 43.6 terawatt-hours (TWh), up 37.5% from 31.7 TWh the year before. Even so, it achieved RE100 by covering 100% of its annual electricity consumption with renewable energy purchases.
This means that even if Google's data centers or offices around the world use electricity generated by gas-fired power plants, the company meets the requirement to use 100% renewable energy overall by purchasing an equivalent amount of renewable energy annually. Google said it signed contracts to purchase more than 12 GW of new clean energy in 2025 alone.
Although Google has achieved RE100, its progress toward 24/7 CFE has stalled for several years. Google's global share of CFE use in 2025 was 65%. Its CFE share has remained nearly flat for five years, after reaching 66% in 2021. At this rate, achieving 24/7 CFE by 2030 appears difficult.
Google's CFE share has made little progress because demand for electricity from AI data centers is growing faster than the company can secure carbon-free power. Solar and wind have limitations when it comes to providing a stable supply around the clock, while building other carbon-free sources, such as nuclear, fusion, and geothermal power, takes time.
In October 2024, Google signed a 500 MW power purchase agreement with Kairos Power, an SMR developer. The reactor is not expected to begin operating until after 2030. In July 2025, Google signed an agreement to purchase 200 MW of electricity from fusion company Commonwealth Fusion Systems. That plant, too, is not expected to begin operating until the early 2030s.
It is also notable that Google's greenhouse gas emissions have risen significantly despite its achievement of RE100.
In its 2026 Environmental Report, Google said its greenhouse gas emissions in 2025 rose 18% from the previous year to 14.5 million metric tons of carbon dioxide equivalent (tCO2e). This was the largest annual increase since Google began publishing environmental reports in 2016. The sharp rise is believed to have been driven by the large-scale infrastructure required to expand AI data centers.
IEA: "Nuclear Power to Play an Important Role After the 2030s"
U.S. big tech companies are relying on gas-fired power to meet the immediate electricity needs of their AI data centers, but nuclear power is expected to replace a substantial part of gas-fired generation's role over the long term.
The International Energy Agency's (IEA) 2025 report, "Energy Supply for AI," found that natural gas accounted for the largest share of electricity supplied to data centers in the United States, at 40%. Renewable energy followed at 24%, while nuclear power and coal accounted for 20% and 15%, respectively.
The IEA forecast that natural gas would be the largest source of additional supply over the next five years, providing an extra 130 TWh of electricity annually by 2030. Renewable energy is expected to follow, supplying 110 TWh.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
The IEA said, "Nuclear power will play an important role in meeting electricity demand from U.S. data centers," adding that it would become "even more important after the 2030s, when small modular reactors (SMRs) are expected to come online." The IEA expects the expansion of renewable energy and SMRs to reduce natural gas use. It projects that low-emissions energy sources will account for half of the electricity supplied to data centers by 2035, driven by increased renewable generation and the expansion of SMRs.