Developer: "Did Hyosung Heavy Industries have the authority to change the building owner's name?"
Hyosung Heavy Industries: "We repaid the loan and obtained ownership"
Dispute also over site access and management rights

A court has issued an order prohibiting the disposal of a building in the Jamwon-dong mixed-use development project in Seocho-gu, Seoul, which Hyosung Heavy Industries had registered in its own name. After missing the completion deadline, Hyosung Heavy Industries, the construction company, repaid the developer’s loan and secured ownership of the building. The court granted the developer’s injunction request, filed in response.


The building at a mixed-use development project in Jamwon-dong, Seocho-gu, Seoul, where Hyosung Heavy Industries and the developer are embroiled in an ownership dispute. The court granted the developer’s injunction request, prohibiting Hyosung Heavy Industries from disposing of the building. Provided by Jamwon-dong Mixed-use Development PFV.

The building at a mixed-use development project in Jamwon-dong, Seocho-gu, Seoul, where Hyosung Heavy Industries and the developer are embroiled in an ownership dispute. The court granted the developer’s injunction request, prohibiting Hyosung Heavy Industries from disposing of the building. Provided by Jamwon-dong Mixed-use Development PFV.

View original image

According to legal sources on October 16, Judge Kim Su-il of the Seoul Central District Court’s Civil Division 53 granted an application for an injunction prohibiting the disposal of real estate, filed by the developer, Jamwon-dong Mixed-use Development PFV, against Hyosung Heavy Industries. The developer had requested the injunction, saying, “The ownership preservation registration in Hyosung Heavy Industries’ name must be canceled,” and asking the court to “prevent the building from being disposed of until the ownership dispute is resolved.” The court granted the request, ordering that “disposal of the building, including its sale or the creation of a mortgage, is prohibited.”


The building covered by the court’s order is an office and neighborhood commercial facility in Jamwon-dong, with eight basement levels and 12 above-ground floors and a total floor area of about 26,500 square meters. Jamwon-dong Mixed-use Development PFV is developing the project, with Hyosung Heavy Industries serving as the contractor. Completion was originally scheduled for July 2026, but approval for use was delayed amid a dispute over construction of the parking ramp and remedial work. The developer cites problems with the ramp construction, while Hyosung Heavy Industries points to the developer’s withdrawal of its application for approval and failure to submit it as the causes of the delay.


The dispute between the two parties over ownership of the building also began after the completion deadline was missed. Under a construction contract signed in 2023, Hyosung Heavy Industries agreed to take over the developer’s project financing (PF) loan debt if approval for use was not obtained by the deadline. In August 2026, it repaid 346.4 billion won in loans and took over the lenders’ claims and contractual position. It then changed the building owner’s name to its own, obtained approval for use in September 2026, and completed the ownership preservation registration.


The developer disputes whether Hyosung Heavy Industries had the authority to change the building owner’s name. When the loan was arranged, the developer submitted a blank consent form agreeing to transfer the project to a new developer designated by the lenders if the project ran into trouble. The developer alleges that Hyosung used the form to insert its own name and transfer the project to itself, even though it had not been designated as the new developer, after taking over the loan claims. Its position is that the authority to repay the loan and the authority to take ownership of the building are separate matters.


Hyosung Heavy Industries, meanwhile, maintains that it changed the name based on the authority transferred to it by the lenders. A company representative said, “Under the loan agreement, the developer gave the PF lenders a blank proxy consent form for changing the building owner’s name, and we changed the name accordingly.” The representative also argued that it “acquired a security interest by way of transfer to recover the debt as a creditor that repaid the loan on the developer’s behalf.”



Meanwhile, a decision is also pending in a separate case concerning the developer’s application for an injunction against obstruction by Hyosung Heavy Industries. The developer claims that restrictions on access to the site and the exercise of a lien are interfering with its leasing and management work. Hyosung Heavy Industries, in contrast, says the developer has no right to make such demands now that ownership of the building has been transferred to the company. The court completed its hearing on October 7 and is reviewing materials submitted by both parties.