Confirmed illegal activities, including an unauthorized concrete low-water bridge, stockpiled aggregate, and a stream-water pipe
Measures completed for aggregate stockpile and pipe... Administrative execution procedures to proceed for illegally occupied land
Long-term nonpayment of stream usage fees and passage of heavy vehicles transporting raw stone... Concerns also raised over stream damage and safety
County issues prior notice to restore bridge... Continues corrective measures and follow-up action against unauthorized structures

Geochang County in South Gyeongsang Province is stepping up administrative measures to restore a local stream near the entrance to a quarry operated by Jusang Enterprise in Jusan-myeon, after confirming illegal activities including unauthorized occupation and the installation of unpermitted structures.


A concrete low-water bridge used as an access road to the quarry has been installed across the stream. Concerns have also been raised over unpaid stream-land usage fees and damage to the surrounding stream, prompting calls for a thorough investigation under relevant laws and measures to restore the area.


[Photo courtesy of Geochang County] A concrete submerged bridge and the surrounding stream near the entrance to the quarry operated by Jusang Enterprise in Jusang-myeon, Geochang County. The county has confirmed illegal activities in the area, including unauthorized occupation of the stream and installation of unlicensed structures, and is taking administrative steps to restore the site to its original condition.

[Photo courtesy of Geochang County] A concrete submerged bridge and the surrounding stream near the entrance to the quarry operated by Jusang Enterprise in Jusang-myeon, Geochang County. The county has confirmed illegal activities in the area, including unauthorized occupation of the stream and installation of unlicensed structures, and is taking administrative steps to restore the site to its original condition.

View original image

According to the county's report on follow-up measures in response to a complaint about illegal occupation of the stream, officials conducted an on-site inspection of the local stream on July 3 and confirmed illegal activities, including the stockpiling of aggregate, the installation of a stream-water pipe, and the unauthorized occupation of land.


On July 15, the county issued prior notice requesting the voluntary removal of the aggregate and stream-water pipe and restoration of the site. The county confirmed that measures regarding those facilities had been completed on August 20.


On August 21, it issued prior notice requesting the voluntary removal of structures on the illegally occupied land and restoration of the site. For areas where corrective action has not been taken, the county plans to issue the first warning ahead of an administrative execution in October.


On September 18, the county also issued prior notice requesting the voluntary removal of the bridge crossing the local stream and restoration of the site in response to the illegal activity. The county plans to order the facility's installer to take the necessary measures in accordance with relevant procedures and to continue checking whether they are carried out.


The concrete low-water bridge in question is reportedly used as a main access route for vehicles transporting raw stone quarried at Jusang Enterprise's quarry to outside locations.


However, the stream management authority's permit records show no permit for the facility, raising legal concerns over the installation of an unauthorized structure.


It was also found that no usage fees have been paid for the stream land since a payment was made in 2006.


Accordingly, the county may need to review the history of fees assessed and collected for the long-term occupation of the stream, as well as whether compensation should be imposed for the period of unauthorized occupation.


Concerns have also been raised about the bridge's structural safety, as large trailers carrying raw stone are reportedly known to have crossed it repeatedly for years.


It has also been alleged that vehicles weighing more than 100 tons traveled along the route while transporting raw stone. This has prompted calls to verify the vehicles' actual gross weight, cargo loads, and operating conditions, and to inspect whether the concrete low-water bridge was designed and built to withstand such loads.


Damage to the area around the stream is another major issue. Concerns have been raised that the installation of the bridge and its use as an access road to the quarry may have affected the stream environment, including by altering the terrain of the streambed and parts of the embankment and by stockpiling aggregate nearby.


In particular, concrete structures in a stream can affect water flow and sediment movement during heavy rain. A comprehensive review is therefore needed of the stream's capacity to convey water, its flood-response function, and the safety of nearby embankments.


Article 33 of the current River Act stipulates that, in principle, anyone seeking to occupy land within a river zone or to construct, rebuild, or alter a structure must obtain a permit from the river management authority.


If a river is occupied or a structure is installed without a permit, administrative measures, including orders to restore the site and remove the facility, may be taken under relevant laws. Whether penalties apply may also be reviewed, depending on the nature of the violation.


The county may also consider imposing compensation for unauthorized occupation under relevant laws. The issue of unpaid usage fees over an extended period must be handled after checking the permit period, the history of assessments and collections, and the legally allowable collection period.


Following the complaint about illegal occupation, Geochang County is proceeding in stages with an on-site inspection, prior notice requesting voluntary removal, and restoration procedures.


The county has already completed measures regarding the stockpiled aggregate and stream-water pipe, and is continuing follow-up administrative procedures concerning the illegally occupied land and the bridge.


The follow-up process outlined by the county begins with an order to restore the site, followed by first and second warnings ahead of an administrative execution, and then the execution itself.


However, whether to proceed with an administrative execution will be determined after comprehensively reviewing compliance with the corrective order and whether the requirements under relevant laws have been met.


Attention is focused on the outcome of follow-up measures in this case, which involves not only administrative action against illegal occupation of a local stream but also concerns over the safety of an unauthorized concrete low-water bridge, long-term nonpayment of stream usage fees, and damage to the surrounding area.


In particular, the bridge used for an extended period by vehicles transporting large raw stones should be assessed for structural safety and its impact on the stream's flow. Further reviews of a safety inspection and the scope of restoration may also be necessary.


Geochang County plans to continue corrective measures against the illegal occupation of local streams, including ordering those responsible for installing unauthorized facilities to take the necessary steps under relevant laws and administrative procedures, and continuing to check whether they comply.


The county also plans to conduct on-site inspections and follow-up administrative procedures to ensure that restoration measures concerning the illegally occupied land and the bridge lead to substantive action.



Attention will be focused on whether these administrative measures can help restore the public function of the local stream, ensure its safety, and address illegal occupation within the stream zone.


This content was produced with the assistance of AI translation services.

© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.