Materials from the office of Democratic Party of Korea Rep. Lee Yongwoo
As of April 2025, 97% of the funds had been disbursed
All eight work processes, including drilling gas collection wells, were "inadequate"
Discrepancies between reported prog

The Korea Environment Corporation provided approximately KRW 2.9 billion in government subsidies for an international greenhouse gas reduction pilot project it promoted in Uzbekistan, but an on-site inspection found that all eight planned work items were “inadequate.”


According to documents the Korea Environment Corporation provided to Assemblyman Lee Yongwoo of the Democratic Party of Korea, a member of the National Assembly’s Climate, Energy, Environment and Labor Committee, the corporation pursued a greenhouse gas reduction project at the Maidontol landfill in Uzbekistan with the private company Sejin GNE.

[Exclusive] Korea Environment Corporation: Where Did the KRW 2.9 Billion in "International Greenhouse Gas Reduction" Subsidies Go? View original image

The project involves capturing landfill gas, operating a 1.2 MW power generation facility and securing greenhouse gas reduction credits. The total project cost is KRW 13,659,000,000. Government subsidies amounted to KRW 2,989,000,000, of which the corporation had disbursed approximately 97%, or KRW 2,908,000,000, as of April 2025.


However, an on-site inspection that same month found that all eight work items originally scheduled for completion by December 2024 were “inadequate”: setting up an on-site office, basic civil engineering work, drilling gas collection wells, procuring equipment and materials, construction and mechanical work, covering the landfill, electrical work, and commissioning and operations training.


The inspection also found cases where reports did not match actual conditions at the site. The project operator reported in December 2024 that drilling equipment for the collection wells had been brought to the site and was being assembled and tested. However, the equipment was not there during an on-site inspection in April 2025, and drilling work on the collection wells had not begun.


There was also a wide gap between the subsidies paid and the submitted expenditure records. The corporation had paid approximately KRW 2.9 billion in subsidies, but the project operator reported spending only KRW 1,301,000,000.



Assemblyman Lee said, “The corporation should disclose the reviews and supporting documents required at each stage of subsidy disbursement, as well as the progress of construction and records of how the subsidies were used after inspections. If improper spending is confirmed, it should take necessary measures, including recovering the funds, and clarify its responsibility for management and oversight.”

Lee Yongwoo, a lawmaker from the Democratic Party of Korea.

Lee Yongwoo, a lawmaker from the Democratic Party of Korea.

View original image


This content was produced with the assistance of AI translation services.

© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.

Today’s Briefing