Residents Raise Questions about Electromagnetic Fields, Noise, Heat Island Effect, and Fire Safety
Gwacheon Juam Daetori Trust: "We Will Carefully Consider Residents' Opinions in Project Implementation"

Gwacheon Juam Daetoriuts held a resident briefing session on the data center development project at the main auditorium of Gwacheon Nonghyup headquarters on the 6th. (Source: Gwacheon Juam Daetoriuts)

Gwacheon Juam Daetoriuts held a resident briefing session on the data center development project at the main auditorium of Gwacheon Nonghyup headquarters on the 6th. (Source: Gwacheon Juam Daetoriuts)

View original image

Gwacheon Juam Daeto Development No.1 Real Estate Investment Trust Co., Ltd. (hereinafter referred to as "Gwacheon Juam Daetori Trust") held a resident briefing session on October 6, 2026 at the main auditorium on the 4th floor of the Gwacheon Nonghyup headquarters to share updates on the Gwacheon Juam District data center development project (Block 1-9 for business facilities).


This event was attended by local residents, including members of the Juam Janggun-maeul Housing Redevelopment and Maintenance Project Association as well as future residents. Gwacheon Juam Daetori Trust presented the project's architectural plan and environmental impact review, and answered a variety of questions from residents.


The project, formally named the "Gwacheon Juam District AI Hub Center New Construction," involves the construction of a broadcasting and telecommunication facility (data center) with a total floor area of 14,538 square meters, a site area of 2,274 square meters, 3 basement floors and 7 above-ground floors, a height of 54.3 meters. The power capacity is 9.5 MW (megawatts), and Gwacheon Juam Daetori Trust described it as a small data center since the capacity is below 10 MW.

Gwacheon Juam Daetori Trust Holds Resident Briefing on Data Center Development Project View original image

Gwacheon Juam Daetori Trust explained that this data center receives power via the 22.9kV Korea Electric Power Corporation's public distribution network, which also supplies nearby apartments and business facilities, so there is no need to install new transmission towers or extra-high voltage transmission lines. The company reported that measured and projected values for electromagnetic fields, including the highest measured value around the site (1.46mG), are all within 0.2% of the domestic human protection standard (833mG). Noise and vibration are controlled by installing soundproofing and vibration-proof devices on generators and chillers. As a result, expected noise is 45dB(A) and vibration is 49dB(V), both meeting residential evaluation standards.


Regarding concerns about the heat island effect, it was explained that the warm air generated by the chillers rises and disperses rapidly, resulting in negligible impact on temperatures in surrounding residential areas. The center uses air-cooled (dry cooling) systems, so there will be no wastewater or white vapor (condensation plume). For fire safety, the battery room is separated with a fireproof wall, high heat-stability batteries are used, and oil tanks are buried underground with enhanced automatic fire detection equipment, allowing for 24-hour monitoring.


There is growing interest among local residents and industry stakeholders as to whether this technically safe, urban-type small data center can integrate smoothly with the city and operate stably.



A representative from Gwacheon Juam Daetori Trust stated, "We were able to fully listen to a range of resident opinions at the briefing session," adding, "We will carefully consider the suggestions as we move forward with the project and will continue to communicate with residents in the future."