Demolition Completed at Gangbuk District Office... Competition Begins to Select Contractor for 17-Story New Complex
15 Construction Companies Participate in Pre-Construction Briefing on the 18th
Groundbreaking Scheduled for August Next Year, Completion Targeted for November 2030
Gangbuk District in Seoul (Mayor Jang Changsoo) has completed the demolition of six buildings on the site designated for the new district office, including the existing district office building, and has now begun the process of selecting a construction company. Ahead of the bidding, the district is disclosing project information in advance to encourage competition among construction firms.
Jang Chang-su, mayor of Gangbuk District, is giving a greeting at the preliminary briefing session for the construction of the administrative complex town. The background behind features a bird's-eye view of 'Gangbuk Samgyeong'. Provided by Gangbuk District.
View original imageThe district announced on the 21st that it held a preliminary briefing on the construction project at Gangbuk Pine Hall in the Gangbuk Culture and Arts Center on September 18. In attendance were representatives from 15 construction companies who had preregistered for the event, along with about 400 residents, including district managers and members of the residents' association council.
The district stated that by disclosing design drawings, construction methods, and project volumes prior to the official announcement, the briefing was intended to attract capable construction companies to participate in the bidding and to ensure a fair competitive process for the selection of the contractor. Updates on the progress of the new district office project and the future schedule were also shared at the event.
The new district office will be built at 192-59 Suyu-dong, consisting of six basement levels and 17 above-ground floors, with a total floor area of approximately 69,080 square meters. The district plans to house the district office, community center, health center, and district council—all major administrative agencies—in this complex. The first floor, which will be open by raising the structure, will serve as a community space in the form of a park or plaza, and the underground parking garage, with more than 400 spaces, is designed to help address the parking shortage in the Suyu Station area.
The design of the building is based on 'Gangbuk Samgyeong,' which won the international design competition in 2024. The design work has been underway since September of that year for about two years and is now in the completion stage. The competition initially attracted 94 teams from 133 companies across 26 countries, and the consortium led by Heerim Architects & Planners was selected as the representative firm.
The district is aiming to break ground in August 2025, with completion targeted for November 2030. The original target for completion had been December 2028, but it was adjusted to reflect the design and construction conditions. The district explained that, in advance of the main construction, it carried out preparatory work—such as demolition, archaeological investigations, relocation of water and sewage pipelines, development of detour roads, and geothermal energy works—which has shortened the overall construction period by 1 year and 8 months.
On this day, the district also announced a plan to rename the "Gangbuk-gu New District Office Construction Project" to the "Gangbuk-gu Administrative Complex Town." This is intended to highlight that, in addition to administrative agencies, the project will also include community facilities such as an observatory, a performance hall, and a book lounge for the benefit of residents.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
Mayor Jang Changsoo said, "We will select a competent construction company through a fair and transparent competition to realize the new district office, which was awarded first place for best design among public buildings at the Seoul Design Awards, just as it appears in the bird’s-eye view. We will work unwaveringly toward our goal of breaking ground in August next year, aiming to bring the design of Gangbuk District’s new district office to reality."