Ministerial Nominee Hong Ji-seon Announces Plans for Compensation Claim
Seoul City: “Deep Regret Over Burden to Taxpayers”
“Will Firmly Hold Parties Accountable If Claim Proceeds”

The Seoul Metropolitan Government has strongly refuted Minister of Land, Infrastructure, and Transport nominee Hong Ji-seon's position that the city should be billed for operational loss compensation due to the omission of rebar at GTX-A Samseong Station, calling it “preposterous” to force Seoul citizens to bear the increased costs with their taxes. The city also stated that, should a claim for compensation be pursued, it would clearly define the scope of responsibility regarding the rebar omission.


On the afternoon of September 17, a statement was released under the name of Lee Min-kyung, spokesperson for the Seoul Metropolitan Government, saying, “We deeply regret that on September 16, during the National Assembly personnel hearing, Minister nominee Hong asserted his intention to seek compensation from the Seoul Metropolitan Government for operational loss resulting from the omitted rebar at GTX-A Samseong Station.”

Seoul City on Notice of Compensation Claim for Samseong Station Rebar Omission: "Preposterous, Will Clarify Responsibility" View original image

Previously, in an Assembly session the day before, Yonggi Jeon, a lawmaker with the Democratic Party, asked, “Isn’t it necessary to seek a compensation claim over the losses caused by the missing rebar at Samseong Station?” to which nominee Hong replied, “That is planned.” Hong assessed that Seoul bears the primary responsibility for the rebar omission.


However, spokesperson Lee explained, “The Seoul Metropolitan Government conducted its own safety inspection immediately after confirming the omission of rebar in November 2025 and established reinforcement measures in December of the same year. On March 2026, a detailed construction plan was drawn up and, on April 24, shared with the National Railroad Authority, and on April 29, with the Ministry of Land, Infrastructure, and Transport, including specific reinforcement measures and future plans. While ensuring safety, reinforcement construction and trial operations for service were to be carried out simultaneously, with the goal of completing reinforcement works within July.” This, according to the city, demonstrates that safety was confirmed directly through inspections involving the Ministry and the National Railroad Authority.


The spokesperson went on to say, “Even after safety had been established during a sensitive pre-election period, the Ministry delayed the start of reinforcement construction and extended the original inspection period, which was to end by July 20, by another four months until November 20. As a result, the reinforcement works that could have been completed in July, as well as the scheduled non-stop train passage at Samseong Station in August, were postponed.”


Ultimately, the assessment is that, despite both the Ministry and the National Railroad Authority verifying structural safety and resuming test operations, the procedures were significantly delayed for additional verification. The spokesperson concluded, “Imposing the resulting additional costs on citizens of Seoul is preposterous.”



The Seoul Metropolitan Government stated that, should a claim for compensation actually be filed, it will differentiate liability resulting from the omission of rebar and that arising from additional inspections and ensuing delays. The spokesperson added, “We will respond firmly to any attempt to shift the burden of additional expenses incurred due to the Ministry’s decisions onto the taxpayers of Seoul.”