Daewoo Engineering & Construction Wins
Asia Construction Awards Grand Prize in Overseas Category
Key Contributor to Iraq’s National Reconstruction Project

The first-phase project of the Al Faw New Port Container Terminal in Iraq, carried out by Daewoo Engineering & Construction, has won the Overseas Grand Prize at the 21st Asia Construction Awards. This project is part of the Iraqi government's national key infrastructure initiative to develop the Al Faw New Port, for which Daewoo Engineering & Construction is solely responsible for three major works: the quay construction, dredging and reclamation, and channel dredging.


The quay construction for the container terminal began in August 2021 and was completed in September 2024. After successfully finishing the preceding facilities on schedule, the company is targeting completion of the subsequent works by the end of this year. Once finalized, the core infrastructure for phase one of the new port will be ready. The Al Faw Grand Port is a mega infrastructure project designed to support Iraq’s national reconstruction and economic revitalization while also establishing a strategic logistics corridor linking the Middle East and Europe.


Daewoo Engineering & Construction has demonstrated its integrated capabilities not only in constructing single structures, but also in delivering large-scale port infrastructure by seamlessly executing three core works—berthing facilities, port hinterland, and navigation channel—as a connected project.

Overview of Al Faw New Port in Iraq. Provided by Daewoo E&C

Overview of Al Faw New Port in Iraq. Provided by Daewoo E&C

View original image

Large-scale maritime construction is regarded as a highly complex undertaking. In this project, overcoming extremely soft ground conditions and a harsh marine environment were key challenges. The quay work required 1,736 large steel pipe piles, each 50 meters in length. The total length exceeded 88 kilometers. It is a multifaceted marine civil engineering project with 2.8 million cubic meters of dredging and 1.54 million cubic meters of reclamation. The company carefully analyzed sequential relationships for each type of work and optimized equipment movement lines, and in critical processes, divided and performed work in parallel to minimize interference between construction phases.



Taking site conditions into account, the cantilevered traveler method was adopted. To install piles efficiently, a standalone system mounted with a 250-ton crane was used as large-scale mobile equipment. By creating multiple working surfaces, productivity was maximized—thousands of large steel pipe piles were installed with an average construction error within 47 millimeters, ensuring precise execution. For the large-scale concrete deck works, a separate precast system was implemented in a dedicated workshop, which helped minimize quality variance while maintaining the construction schedule.


This content was produced with the assistance of AI translation services.

© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.

Today’s Briefing