[Exclusive] "Please Raise Redevelopment and Reconstruction Costs"... 1.6 Trillion Won Cut After Inflated Requests
Ahn Taejun's Office Cites Data from Korea Real Estate Board
1.6 Trillion Won Cut Across Top 10 Projects After Verification
20 Percent of Cost Increases Found Unnecessary
A review by the Korea Real Estate Board of redevelopment and reconstruction projects where construction costs were increased at contractors’ request found that 21.7% of the increases were amounts that did not need to be added in the first place. The total amount cut at the 10 project sites with the largest reductions was 1.6 trillion won. One apartment project site required a construction cost reduction of more than 300 billion won.
A view of an apartment reconstruction site in Seocho-gu, Seoul, on the 23rd. This is a reference photo not directly related to the article. Photo by Yonhap News Agency
View original imageAccording to data submitted by the Korea Real Estate Board to the office of Ahn Tae-jun of the Democratic Party of Korea, a member of the National Assembly’s Land, Infrastructure and Transport Committee, on September 15, the average reduction rate in construction cost reviews over the past five years (2022–2026) was 21.7%. Under the system operated by the Board, when a redevelopment project seeks to increase construction costs by more than a certain percentage, the project implementer must request a review by a verification agency to assess whether the costs are appropriate.
Expanding the analysis to the 20 project sites with the largest reductions, the Board found that approximately 2.3991 trillion won could be cut. The project site with the largest reduction was an apartment reconstruction project in Seoul. The contractor had initially requested revised construction costs of 3.4879 trillion won, but following the Board’s review, the amount was adjusted to 3.1738 trillion won. A total of 314.059 billion won was cut.
There was also a redevelopment project where the contractor requested an increase of approximately 322% over the amount it had proposed. The contractor for a redevelopment zone in Seoul requested that the original contract amount of 231.1 billion won be increased to as much as 975.5 billion won. Following the Board’s review, the amount was adjusted to 911.3 billion won, resulting in a final reduction of approximately 64.2 billion won.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
The main reasons for construction cost increases reviewed by the Board were found to include design changes and rising prices. Assemblyman Ahn said, “Construction cost increases in redevelopment and reconstruction projects can place a burden on association members and prospective residents, so they must be handled transparently and objectively. Institutional improvements and thorough oversight are needed to prevent unnecessary burdens from arising during the construction cost increase process.”
© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.