Three districts within Sacheon City, South Gyeongsang Province, have been selected for the Ministry of the Interior and Safety's "2027 Disaster Prevention Project." The city will undertake maintenance of steep slopes and disaster-risk reservoirs in these areas.
On September 10, the city announced that projects for stabilizing the steep slopes in Yesu District and for maintaining disaster-risk reservoirs in Gigok and Nosigok districts had been selected for this initiative.
The total project budget for the three initiatives is 4.2 billion KRW, of which 3.3 billion KRW will come from national and provincial funds.
[Photo by Sacheon City] Sacheon City will invest a total of 4.2 billion KRW in maintenance projects for three districts selected for the '2027 Disaster Prevention Project' hosted by the Ministry of the Interior and Safety: Yesuji District steep slope, and Disaster Risk Reservoirs in Gigok and Nosigok Districts.
View original imageThe steep slope stabilization project in Yesu District will focus on roads and adjacent slopes in the area of 550-14 Yesu-ri, Jeongdong-myeon.
This area has been designated with a D grade, with a targeted area of 4,371 square meters. The city plans to invest a total project cost of 2.5 billion KRW by 2028 to reinforce and stabilize a slope with a length of 58 meters and a height of 15 meters.
The disaster-risk reservoirs in Gigok and Nosigok districts have also been included as maintenance targets.
The project budget for the Gigok district, located at 24 Guam-ri, Sacheon-eup, will be 1 billion KRW, and for the Nosigok district, located at 257-1 Gamgok-ri, Jeongdong-myeon, it will be 700 million KRW.
Both districts have received a D grade. The total reservoir capacity is 17,800 cubic meters for Gigok District and 6,860 cubic meters for Nosigok District.
The city plans to repair outdated and vulnerable facilities, such as embankments and spillways, at the two reservoirs by 2027. Downstream from the reservoirs, there are 42 households comprising 84 residents, and 42 buildings are located in the area.
This project aims to mitigate the risk of steep slope collapse and reservoir overflow caused by heavy rains and typhoons. Maintenance work for each district will proceed following design and administrative procedures.
Park Dongsik, Mayor of Sacheon City, said, "We will carry out maintenance projects for disaster-risk areas as scheduled and will continuously check on-site safety throughout the process."
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
However, since it is difficult to completely eliminate all natural disaster risks through facility maintenance alone, continuous facility inspections, maintenance, and a response system to prepare for heavy rainfall will also be necessary after the project is completed.