[Report] "A 20-Pyeong Apartment Transformed into a National Standard Unit"… First Remodeling of a 1,000-Unit Mega Complex ‘The Sharp Bundang Hiesto’
Neutimaleu 4 Complex Remodeled into 1,149 Units
From 16 Buildings and 1,006 Units to 17 Buildings and 1,149 Units
Expanded Floor Plans and Resolution of Chronic Parking Shortage
"We expanded the length of the living room by 2 meters vertically and built a wall next to the kitchen to create an additional bathroom. What used to be a 20-pyeong class apartment has now been transformed into a standard national-sized unit with two bathrooms." (Lee Jaeho, Site Manager at POSCO E&C)
On September 9, at the construction site of Neutimaleu Apartment Complex 4 in Bundang-gu, Seongnam City, Gyeonggi Province, a four-level underground parking lot was being built on the land where a 32-year-old apartment complex once stood. The exterior, with window installations finished and the structural frame in place, already looked like a newly-built apartment complex.
Remodeling construction is underway on the site of Nutimaeul 4 Complex in Jeongja-dong, Bundang-gu, Seongnam City on the 9th. Photo by Lee Jieun
View original imageHowever, upon entering the interior of the units, traces of the old complex remained. Unlike new construction, where the entire building is demolished and rebuilt, many of the existing walls—such as those in bathrooms and kitchens—remained intact. Here, remodeling work is being carried out by expanding space to the front and back and constructing new walls, all while retaining the structural frame built over 30 years ago.
This month, POSCO E&C is launching sales for 'The Sharp Bundang Hiesto,' the largest remodeling complex in Korea. This is the first time the company has constructed a project of approximately 1,000 units via remodeling, and the complex is expected to serve as a benchmark for Korea's remodeling technology.
Interior of a house undergoing remodeling construction. The existing structural frame remains intact next to the living room wall. The house's area has been expanded to 84 square meters through remodeling. Photo by Lee Jieun
View original imageThe complex, which was completed in 1994, consists of 16 buildings with a total of 1,006 units. Through vertical and horizontal extensions as well as the addition of a separate building, the total number of units has been increased to 1,149. After subtracting the units allocated to cooperative members, 143 units will be offered for general sale.
The main buildings were extended vertically by adding one floor, and the structures were expanded horizontally at both the front and back by 2 to 2.5 meters, increasing the actual usable area while retaining the original frame. As a result, units previously 66 square meters in size have been expanded to the standard national floor area of 84 square meters. The building coverage ratio increased by approximately 20 percentage points, from 14% to 34%. With the larger area, a second bathroom was added, and the rooms could now be arranged in a row facing south.
With the increase in unit area through remodeling, a variety of floor plans have emerged, ranging from 66 square meters to 84 square meters. This is in contrast to the original Neutimaleu 4 Complex, which primarily consisted of smaller units such as 58, 66, and 67 square meters. A new building was also constructed as a separate structure, but as the overall building volume increased during remodeling, the distance between buildings became slightly narrower than before.
Securing the standard national floor area also improved the business's profitability. By offering the 84-square-meter units for general sale, the cooperative members' additional contributions could be reduced. Remodeling projects are only permitted to increase the number of units by up to 10%, making it difficult to maximize profits through sales volume. Therefore, profitability must be improved by supplying larger unit types for general sale. For The Sharp Bundang Hiesto, it is estimated that the additional contribution for owners moving from a 66-square-meter to an equivalent-sized unit will be around 100 million won.
The chronic parking shortage, commonly cited as a problem of older complexes, has also been resolved. After excavating the site with the top-down construction method, a four-level underground parking lot was built with earthquake-resistant design and reinforcement of the foundation. Compared to the previous complex, which only had ground-level parking (0.6 vehicles per household), the number of parking spaces has been significantly increased to 1.71 vehicles per household. Elevators have been installed from the first to the fourth basement level, further enhancing parking convenience for residents.
An underground parking garage with four basement levels located within The Sharp Bundang Heist complex. Photo by Lee Ji-eun
View original imagePOSCO E&C has been leading the industry in remodeling contracts since entering the market in 2014. As of this year, the company’s cumulative order value stands at approximately 14.3 trillion won, and it has secured construction contracts for a total of 46 complexes. In terms of number of units, this translates to 47,562 households. This year, POSCO E&C secured orders worth 332.1 billion won in core areas of the capital region, including the Mullae Hyundai 5th Complex in Yeongdeungpo-gu and the Garak Hanshin Complex in Songpa-gu.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
The company has completed construction at a total of 10 complexes to date, including Geopo The Sharp Triewe, The Sharp Dunchon Foret, and Jamsil The Sharp Ruben. It also plans to begin construction on Suji Bowon, Suji Initial, and Bundang Hansol 5 Complex in the near future. Earlier, The Sharp Dunchon Foret, completed in 2024, moved its ground-level parking lot underground and created playgrounds and landscaped areas on the former parking lot site.
The Shop Dunchon Foret in Dunchon-dong, Gangdong-gu, completed through remodeling. The above-ground parking lot was moved underground, and landscaping space was created on the existing site. Photo by Lee Ji-eun
View original imageA representative from POSCO E&C stated, "Remodeling is a project method with significant strengths in improving residential functionality, reducing energy consumption, and enhancing structural stability. By maintaining the original structural frame and bringing living performance up to the standard of new construction, remodeling is emerging as a practical solution for addressing the aging housing problem."