Leak Detected in Saeul Unit 3 Piping During Commissioning... Reactor Manually Shut Down
The Saewool Unit 3 nuclear reactor, which is currently under commissioning, was manually shut down after a leak was detected in the pipe that drains condensate water from the steam supplied to the turbine.
Saewool Nuclear Power Headquarters of Korea Hydro & Nuclear Power (President: Kim Sangwoo) announced on September 6 at 3:01 p.m. that the 1.4 million kW-class Saewool Unit 3 reactor had been manually shut down.
Saewool Unit 3, which is currently in the commissioning phase, had a leak detected in the piping that drains the condensate water from the steam supplied to the turbine.
Saewool Nuclear Power Headquarters manually shut down the reactor to stabilize and maintain the facility. The exact cause of the leak is currently under investigation.
Hot Picks Today
"I Went for the Cheap Coffee, but Now I Feel Uneasy"... Major Coffee Franchises Cited for Violations One After Another
- In Korea, Studying Medicine Is in High Demand, but in China, It's Shunned: "Why Become a Doctor When You Can’t Make Money?"
- "Surprisingly Real, Perfect Like AI" -- Global Media Praise Korean Fencer's Beauty
- "50 Million Won for Weekly Encounters"... Man in His 60s Sentenced for Deceiving Woman in Her 20s with Forged 1.4 Billion Won Account
- "I've Already Booked My Trip to Japan, But This Is Serious"...Highest Number of Measles Cases in Japan in a Decade Spurs Emergency Alert
The headquarters confirmed that there is no radiological impact due to the reactor shutdown. The plant remains in a stable condition as of now, according to Saewool Nuclear Power Headquarters.