Doosan Fuel Cell Makes First Entry into U.S. AI Data Center Market with KRW 501.4 Billion Fuel Cell Supply
Sequential Delivery from the Second Half of This Year to the First Half of 2028
"Aiming to Resolve U.S. Power Bottlenecks with Rapid On-Site Power Supply"
Doosan Fuel Cell is entering the U.S. power market for the first time by supplying fuel cells for artificial intelligence (AI) data centers to HyAxiom, Doosan’s U.S. subsidiary. This project was made possible as HyAxiom secured an order for fuel cells dedicated for data centers within the United States. Both companies are using this opportunity as a launching pad to accelerate growth in the rapidly expanding North American power market.
Doosan Fuel Cell announced on September 2 that it has signed a contract with HyAxiom to supply phosphoric acid fuel cells (PAFC) worth KRW 501.4 billion. The products will be delivered sequentially to HyAxiom from the second half of this year through the first half of 2028, and HyAxiom will supply them to AI data centers in the United States.
The construction of AI data centers in the U.S. is increasing rapidly, and securing enough power has emerged as a new challenge. As AI services proliferate, the power demand for data centers has surged, but it takes several years to build power plants and transmission/distribution networks, widening the gap between the pace of data center construction and the expansion of power infrastructure.
As a result, on-site power generation, where power plants are located near data centers to supply electricity directly, is gaining attention as a promising alternative. Doosan Fuel Cell explained that its fuel cells are suitable for the stable power supply required by data centers, as they can operate continuously 24 hours a day and offer high power generation efficiency.
In particular, for this project, Doosan Fuel Cell and HyAxiom plan to collaborate so that installations at U.S. customer sites can be completed in about a year following the contract. The ability to supply power in line with the data center construction schedule is considered a key competitive advantage. With the adoption of a modular structure, the facilities can also be expanded incrementally to meet increasing power demand.
The heat generated by the fuel cells can also be utilized for cooling the data centers. By connecting with absorption chillers or heat pumps, the heat produced during power generation can be used for cooling, enabling the creation of comprehensive solutions that supply both electricity and cooling simultaneously.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
A Doosan Fuel Cell official said, “With this contract, we have demonstrated our competitiveness as a behind-the-meter (BTM) solution that can address power bottlenecks at data centers in the AI era, especially in the key U.S. market. Building on this momentum, we will expand additional orders in the North American market based on our rapid supply capabilities and scalable solutions.”