Court Orders Government to Pay 40.45 Billion Won

Korean Air has achieved a partial victory in the appellate trial regarding the dispute with the Defense Acquisition Program Administration (DAPA) over responsibility for delays in unmanned aerial vehicle (UAV) deliveries.

Korean Air New CI. Korean Air

Korean Air New CI. Korean Air

View original image

On August 20, the 22-2 Civil Division of the Seoul High Court (Presiding Judge Nam Sungmin) dismissed appeals from both Korean Air and the state in a lawsuit filed by Korean Air seeking confirmation of non-existence of obligation, thereby upholding the partial victory of the plaintiff in the original verdict.


In December 2015, Korean Air signed a contract with DAPA to deliver 16 sets of division-level reconnaissance UAVs to be used for independent surveillance and reconnaissance operations by division-level units.


After delivery was delayed, DAPA claimed Korean Air was responsible, imposing a delay penalty amounting to 208.1 billion won and deducting 65.85 billion won from the delivery payment.


Korean Air filed a lawsuit in April 2021, arguing that delays in production were due to DAPA’s unilateral demands for specification changes.



Previously, the first trial court ruled that Korean Air's delay penalty should be 25.4 billion won, which amounts to 10 percent of the contract value of 254 billion won. Accordingly, the court ordered DAPA to return 40.45 billion won of the 65.85 billion won it had deducted from the delivery payment as a delay penalty.


This content was produced with the assistance of AI translation services.