No Mayor-Led Briefing Scheduled Yet
Formal Process to Adjust Local Government’s 400 Billion-Won Cost Share Not Initiated
City Continues to Press Land and Finance Ministries; Seeks Support from Local Lawmakers
Total Project Budget at 793.4 Billion Won, Only 2% Complete—Rising Concerns Over Delays

Despite the transition committee’s recommendations to renegotiate the cost-sharing ratio and to consider grade separation or undergrounding for certain segments of the Donggwangju IC to Gwangsan IC expansion project on the Honam Expressway, a follow-up schedule has yet to be established by the Jeonnam Gwangju Integrated Special City. No reporting session led by the mayor has been scheduled, and no formal administrative procedures have been initiated to adjust the local government’s funding burden, which amounts to approximately 400 billion won.


As of August 20, 2026, according to the Jeonnam Gwangju Integrated Special City, the city continues to urge the Ministry of Land, Infrastructure and Transport and the Ministry of Economy and Finance to revise the project’s cost-sharing structure. Cooperation from local National Assembly members is also being sought to facilitate discussions with the central government.


Since its launch, the Integrated Special City has been undergoing its next organizational restructuring process. As the new organizational system has yet to be finalized, even the reporting schedule for transportation issues—including the transition committee’s recommendations—remains undetermined.

Location map of the Honam Expressway Gwangju section (Donggwangju IC to Gwangsan IC) expansion construction. The project involves expanding the 11.2 km section from Donggwangju IC to Gwangsan IC from 4 lanes to 6 lanes in both directions. It is divided into Sections 1, 2, and 3, with the goal of completion by the end of 2029. Provided by Jeonnam Gwangju Integrated Special City.

Location map of the Honam Expressway Gwangju section (Donggwangju IC to Gwangsan IC) expansion construction. The project involves expanding the 11.2 km section from Donggwangju IC to Gwangsan IC from 4 lanes to 6 lanes in both directions. It is divided into Sections 1, 2, and 3, with the goal of completion by the end of 2029. Provided by Jeonnam Gwangju Integrated Special City.

View original image

Groundbreaking After 12 Years Since Preliminary Feasibility Passed—Project Budget Tripled

The Donggwangju IC to Gwangsan IC expansion project on the Honam Expressway involves widening an 11.2 km stretch that crosses Gwangju’s urban core from a four-lane road to six to eight lanes. A new access road will be built at Yongbong IC, along with the installation of 12 noise barriers and 20 bridges. Upgrades to aged bridges, noise walls, and other existing infrastructure are also included.


This section originally opened in 1973 as a two-lane bidirectional highway and was expanded to four lanes in 1986. At that time, it served mostly as a bypass for Gwangju’s outskirts. However, with urban expansion and the establishment of interchanges such as Yongbong, Dongnim, Sanwol, and Munheung, it now serves as a key arterial road for the city center. While road capacity remained unchanged, the number of vehicles has steadily increased, leading to long queues on local roads as drivers line up to enter the expressway during peak commuting hours.


In 2009, Gwangju City formally requested the Ministry of Land, Infrastructure and Transport to expand the section between Gwangsan IC and Donggwangju IC. The project began in earnest after a coordination meeting among related agencies hosted by the Office for Government Policy Coordination in 2012 and passed the Korea Development Institute’s preliminary feasibility test in 2013. At the time, the project’s economic feasibility rating was 0.96, falling short of the required standard, but a comprehensive evaluation—covering policy goals and regional balance—found project implementation to be appropriate.


The original target was construction to begin in 2017 and completion in 2021. However, even after a project cost-sharing agreement was signed between Gwangju City and Korea Expressway Corporation in 2015, basic design, detailed design, and repeated feasibility studies dragged on for years. Final design documents were completed only in 2023, and actual construction began in September 2025.


During these delays, the total project cost nearly tripled from 276.2 billion won to 793.4 billion won. Noise reduction facilities such as noise tunnels were added to mitigate the impact on residential areas, and improvements to aging infrastructure were also included. Rising material and construction costs further contributed to the increase.


The project cost is to be split evenly between the central government and Korea Expressway Corporation on one side and the city on the other. The local government’s share amounts to approximately 400 billion won. Last year, Gwangju City demanded greater central government funding to relieve this financial burden, but related budget lines were cut from the government’s supplementary budget, sparking concerns about possible project disruption. Nevertheless, the city resolved to proceed as planned and broke ground in September of the same year.


Project Progress at 2%—Cultural Heritage Excavations Also a Variable

Construction is divided into three sections centered on Donggwangju IC, Yongbong IC, and Seogwangju IC. As of the second week of July, overall project progress stands at 2.02%. By section, progress rates are 1.73% for Section 1, 2.19% for Section 2, and 2.15% for Section 3. Ongoing site activities include relocating obstructing trees and preparing for civil engineering work.


Cultural heritage surveys present a further variable. Remains and artifacts dating from the Bronze Age to the Joseon Dynasty have been identified along the construction corridor, leading to intensive archaeological excavations. Depending on the findings, measures such as preserving records, removing and relocating, or preserving on-site will be determined.


At present, the entire project has not been suspended, nor has its completion date officially been pushed back. However, depending on when archaeological investigations conclude and the preservation methods chosen, some aspects of project progress may be affected. The official completion target remains the end of 2029.


Transition Committee: "Renegotiate Cost Sharing"—Residents Fear Additional Delays

The Jeonnam Gwangju Major Transition Planning Committee recommended revisiting the local government’s burden and future transportation demand, essentially calling for a reassessment of the project. The committee proposed aligning the cost-sharing ratio with similar projects in other areas and renegotiating with the central government and Korea Expressway Corporation.


To improve connectivity between city districts divided by the expressway, it also recommended grade separation and undergrounding for certain sections. The committee further suggested enhancing the existing project plan with additional measures to mitigate residents’ inconvenience during construction.

The Jeonnam Gwangju Grand Transformation Planning Committee proposed to Gwangju City the task of reexamining transportation infrastructure. It urged reviewing the local government’s financial burden for the Honam Expressway expansion project and considering measures such as grade separation and underground construction for certain sections. Provided by Jeonnam Gwangju Grand Transformation Planning Committee

The Jeonnam Gwangju Grand Transformation Planning Committee proposed to Gwangju City the task of reexamining transportation infrastructure. It urged reviewing the local government’s financial burden for the Honam Expressway expansion project and considering measures such as grade separation and underground construction for certain sections. Provided by Jeonnam Gwangju Grand Transformation Planning Committee

View original image

The city previously stated that complete cancellation is not under consideration since much of the project planning has already been completed. However, it has indicated that it will continue to review the project’s feasibility and practicality, making adjustments or additions based on internal review if necessary—even as construction proceeds.


Residents in Buk-gu are concerned that the long-delayed project could be pushed back again. Kim, a 45-year-old who has lived in Yongbong-dong for 20 years and commutes via the Honam Expressway, said, "Every evening during rush hour, vehicles waiting to enter the expressway are so backed up that it causes traffic jams on local streets as well."



Kim added, "When I heard about the ground-breaking, I thought we would finally get some relief, but all this talk of reconsideration is frustrating. Shouldn’t the issues of construction costs and funding have been sorted out before starting the project? For the citizens who have endured over a decade of traffic congestion, I hope the project can be completed as originally planned."


This content was produced with the assistance of AI translation services.