Daejin General Industrial Complex Stalls for Years... Sacheon City Cancels Designation of Project Implementer
Despite Additional Opportunities, Key Requirements for Normalization Were Not Met
Resolving Land Trusts and Retention Rights Remains a Future Challenge
Sacheon City in South Gyeongsang Province has canceled the status of the existing project implementer for the Daejin General Industrial Complex development project in Daejin-ri, Gonyang-myeon, which had been delayed for an extended period.
On August 13, the city announced that it had decided to cancel the designation of the project implementer for the Daejin General Industrial Complex development project, after comprehensively reviewing the progress, financial conditions, and the potential for normalizing the project.
This administrative action cancels only the status of the existing project implementer who has led the development, not the designation of the industrial complex itself. Therefore, it does not mean that the site’s status as an industrial complex has been revoked or that its future use has been determined.
[Photo provided by Sacheon City] Sacheon City has decided to cancel the designation of the project implementer for the Daejin General Industrial Complex Development Project after comprehensively reviewing the project's progress and financial conditions. Meanwhile, a banner announcing the exercise of a retention right is displayed on-site.
View original image◆ Project Delayed for Years Since 2015 Approval
The Daejin General Industrial Complex was planned on about 247,913 square meters at 71-2 San, Daejin-ri, Gonyang-myeon, Sacheon City. The industrial complex plan was approved and announced in July 2015, after which the project began to proceed.
The total project cost was initially set at 57.896 billion won, including 32.013 billion won for construction, 10.3 billion won for compensation, and 15.583 billion won for other expenses.
The complex was planned to attract industries such as electrical equipment manufacturing (C28), other machinery and equipment manufacturing (C29), other transportation equipment manufacturing (C31), and solar power generation (D35114).
However, construction and financing did not proceed as planned during the project’s implementation. Even after stone extraction and stockpiling operations were completed, the main construction, including essential infrastructure, did not proceed normally for a long period. The industrial complex plan was also revised several times from September 2019 to December 2024 to reflect changing project conditions.
◆ Extension of Project Period and Hearings, but Normalization Not Achieved
Before taking administrative action due to project delays, Sacheon City conducted procedures to confirm the possibility of normalizing the project and to hear the opinions of the project implementer. The city checked the fulfillment of requirements for normalization in 2025 and held two hearings in July and November of that year.
Subsequently, to provide an additional opportunity for normalization, the city approved and announced a change to the industrial complex plan, extending the project period from December 31, 2025 to March 31, 2026. The requirements necessary for normalization were also included in this revised plan.
However, even after the extension, core measures for normalization, such as securing funds, were not sufficiently implemented, nor was substantial progress made toward normalizing the project, according to Sacheon City.
The city notified the halt of onsite work on December 31, 2025. Prior to canceling the project implementer's designation, Sacheon City held another hearing on July 9, 2026, to once again listen to the project implementer’s opinion.
◆ Comprehensive Review of Financial Capacity and Project Status
Sacheon City concluded, after reviewing the financial capacity of the project implementer, the project's progress to date, and the possibility of normalization, that continuing with the current implementer would be difficult.
In particular, even though the project period had been extended and multiple opportunities for submission of opinions and explanations were provided, substantial measures for normalization were not implemented, which led to the decision to cancel the implementer's designation.
The city explained that during the administrative disposition process, it had confirmed the project implementer's opinions through hearings and reviewed the relevant documentation.
[Photo by Sacheon City] Sacheon City, after comprehensively reviewing the development progress and financial conditions of the Daejin General Industrial Complex Development Project, decided to cancel the designation of the project implementer. Meanwhile, banners notifying the exercise of retention rights are displayed at the site.
View original image◆ Separate Review for Site Management and Future Actions
Even after canceling the designation of the project implementer, Sacheon City will continue to manage the site and respond to safety and environmental issues.
Currently, some sections of the Daejin General Industrial Complex site require maintenance and some equipment has been confirmed to have been removed. Additionally, with legal rights such as the exercise of retention rights and land trusts existing, site management and decisions about the project’s future require further review of these interests.
Sacheon City plans to continuously monitor the situation onsite and implement necessary measures to prevent safety incidents and environmental problems.
However, this action does not revoke the designation of the Daejin General Industrial Complex itself. Future handling of the industrial complex plan and usage of the project site will be determined after comprehensively reviewing the status of the land and facilities, current rights and interests, the industrial complex plan, and relevant laws and regulations.
An official from Sacheon City stated, "We provided the project implementer with opportunities for normalization and for submitting opinions, and conducted the relevant procedures. After comprehensively reviewing the hearing results, financial capacity, and project progress, we decided to cancel the implementer’s designation."
The official added, "This disposition only cancels the status of the project implementer and does not determine the future actions for the industrial complex site. We plan to formulate future measures after a comprehensive review of the rights and interests associated with the land and facilities and onsite conditions."
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
Given that the industrial complex project has been delayed for nearly a decade, diligent follow-up administration is now essential. Authorities must go beyond merely canceling the implementer, and closely examine land and legal relations and onsite safety to prevent additional damage caused by continued neglect and to develop effective follow-up measures that will benefit the local community.