Cheongju City Loses Final Supreme Court Battle in 'Ochang Hugiri Incineration Plant' Dispute... Court Cites Breach of Legitimate Expectations
Supreme Court Finalizes Verdict on Ochang Incineration Plant Case
The Supreme Court has delivered a final verdict in the legal battle that has persisted for over five years between the city of Cheongju and a private enterprise over the construction of a waste incineration plant in Hugiri, Ochang-eup, Cheongju, Chungcheongbuk-do. The court ruled that Cheongju City acted unlawfully by breaking the memorandum of understanding (MOU) and refusing to initiate the incineration plant project.
According to the legal community on August 13, the Supreme Court’s Third Division (Presiding Judge Oh Seok-Jun) upheld the lower court’s ruling, partially favoring the plaintiff, in the ‘administrative lawsuit to cancel the denial of the urban management plan proposal’ filed by Seowon Environment (formerly ESG Cheongwon) against the Mayor of Cheongju.
Seowon Environment attempted to establish a landfill and incineration facility in the Ochang Science Industrial Complex but faced opposition from local residents. In March 2015, the company signed a memorandum of understanding with Cheongju City stating that the two parties would “actively cooperate in the relocation of incineration facilities to another area within the jurisdiction.”
Subsequently, to enable the business relocation, Seowon Environment proposed in December 2020 to build a 165-ton-per-day incineration facility and a 160-ton-per-day shredding and crushing facility in Hugiri, Ochang-eup, as part of an urban management plan. However, Cheongju City rejected the proposal, citing environmental concerns and potential adverse health effects for residents.
The court of first instance ruled in favor of Cheongju City, recognizing the city’s discretion in urban planning decisions. However, the court of second instance reversed this decision, stating that Cheongju City violated the principle of protection of legitimate expectations by refusing the project after previously agreeing to cooperate through the MOU. The court also found that the portion of the project related to the shredding and crushing facility was not covered by the agreement, and thus Cheongju City’s refusal in that regard was lawful.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
The Supreme Court agreed with the appellate court’s verdict and rejected both parties’ appeals. The panel stated, “Cheongju City violated the principle of protection of legitimate expectations by publicly expressing its intention to actively cooperate in the relocation of the incineration facility but then refusing to do so.”
© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.