Will Celltrion Avoid Novo Nordisk’s ‘Idle U.S. Plant’ Pitfall? Proceeding with Caution
Novo Faces Setback on New Product Launch Due to FDA Restrictions
Celltrion’s U.S. Plant Awaits Key Approval for Manufacturing Site Addition
OAI Track Record Prior to Acquisition Emerges as a Factor During FDA Inspection
Attempts by Novo Nordisk to secure a U.S. manufacturing base by acquiring an entire local plant have run into regulatory barriers. This is due to the company’s failure to obtain additional local approval for the production of new products. Since Celltrion also acquired a U.S. plant late last year to begin manufacturing its own products in a similar manner, there is growing analysis that the key issue will be how smoothly it can overcome regulatory hurdles, such as applications to add new manufacturing sites.
According to the global bio industry and other sources on the 12th, American biotechnology company Scholar Rock recently resubmitted a Biologics License Application (BLA) for its spinal muscular atrophy drug candidate, apitegromab, to the U.S. Food and Drug Administration (FDA), but excluded the former Catalent plant now owned by Novo from its contract manufacturers.
The Catalent plant, which Novo acquired in 2024 to establish a U.S. production base, is a finished drug manufacturing facility. However, it received an Official Action Indicated (OAI)—the FDA’s most severe enforcement status—last year. After another inspection in April of this year, it was issued a second OAI. As a result, even after 1 year and 8 months since the acquisition, the facility remains hamstrung by regulatory roadblocks and is unable to function as intended.
A view of the Celltrion production facility located in Branchburg, New Jersey, USA. Celltrion
View original imageThis naturally shifts attention to Celltrion. The local U.S. plant Celltrion acquired to establish its own production base must also pass similar inspections. In December 2025, Celltrion purchased Eli Lilly’s drug substance (DS) manufacturing plant in Branchburg, New Jersey, for $330 million (approximately 467 billion won). Currently, under a contract manufacturing organization (CMO) agreement with Lilly, Celltrion is manufacturing Lilly’s products at the site and recorded 50 billion won in sales during the second quarter.
Celltrion’s larger purpose in acquiring this facility is to begin manufacturing its own pipeline products. To do so, Celltrion must submit a supplemental Biologics License Application (sBLA) to add the Branchburg plant as a manufacturing site for relevant products and then undergo a pre-approval inspection (PAI) by the FDA. Novo’s Catalent facility likewise received a Complete Response Letter (CRL) from the FDA at the plant addition review stage.
Celltrion Plant Also Faces 'FDA OAI History' as a Variable
The Branchburg plant acquired by Celltrion also has a regulatory inspection history. According to FDA facility inspection records reviewed as of the 12th, the Branchburg plant was hit with two OAIs by the FDA in 2019 and 2020, when it was operated by Eli Lilly. In the most recent inspection in 2022, the severity was reduced to a Voluntary Action Indicated (VAI), but it is analyzed that facilities which received prior corrective actions are subject to even stricter pre-approval inspections. This may serve as a variable in the upcoming site registration process.
Moreover, since Branchburg is a DS (drug substance) plant, converting the site for full-scale manufacturing is considered even more challenging compared to a finished product plant like Catalent’s. Whenever there is a change in the raw material production process, a new comparability assessment is required to prove that the same product substance is being manufactured.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
Celltrion is aiming to avoid repeating Novo’s mistakes and has spent more than six months preparing for the approval process, with the goal of beginning in-house product manufacturing at the plant next year as planned. The company is said to be focusing its capabilities on eliminating procedural uncertainties in advance by leveraging its local network and other resources. A Celltrion official stated, “We are currently carrying out technology transfer and validation, and we plan to sequentially submit sBLAs to add manufacturing sites for products as soon as data preparation is complete.” It typically takes anywhere from six months to more than a year to receive approval after submitting a site change application and undergoing inspection.
The situation for other major bio companies with U.S. manufacturing plants is somewhat different. Unlike Celltrion, which must pass the hurdle of site registration since its primary goal is manufacturing its own products, Samsung Biologics (Rockville, Maryland, formerly GSK plant) and Lotte Biologics (Syracuse, New York, formerly BMS plant) are focused on contract manufacturing existing client pharmaceuticals. Therefore, they can continue to use their current production systems as they are.