Saeul Unit 3 Automatically Shuts Down During Commissioning... Nuclear Safety and Security Commission Launches Investigation
View of Units 3 and 4 of the Saeul Nuclear Power Plant. Korea Hydro & Nuclear Power
View original imageThe Nuclear Safety and Security Commission announced that it had received a report from Korea Hydro & Nuclear Power indicating that Saeul Nuclear Power Plant Unit 3 experienced a reactor shutdown at approximately 8:56 p.m. on August 11.
Saeul Unit 3 has been undergoing power escalation tests since receiving its operating license from the Nuclear Safety and Security Commission on December 30 last year. Korea Hydro & Nuclear Power reported that the reactor automatically shut down during a commissioning test in which power transmission was blocked at 80% reactor output.
The Nuclear Safety and Security Commission explained that Saeul Unit 3 remains in a safe shutdown state and that no radiation-related anomalies have been detected.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
Currently, the Commission is inspecting onsite safety at the Saeul Nuclear Power Plant regional office and announced plans to dispatch an investigation team comprised of experts from the Korea Institute of Nuclear Safety (KINS) to meticulously investigate the cause of the incident and assess the safety of the facility.