Military Facilities to Be Relocated in Phases and Temporarily Dispersed to Other Bases
Industrial Complex Development to Begin on Secured Land; Construction of First Fab to Start Next Year
Targeting First Phase Completion in 2029, Mass Production Scheduled for 2030

Plans are underway to construct a semiconductor plant on the site of Gwangju Military Airport even before the complete relocation of the airport. The government intends to gradually relocate military facilities or temporarily assign them to other bases by 2028, beginning with converting the ammunition depot site, which will be vacated first, into an industrial complex for the semiconductor sector.


According to an explanation on August 11 from Jeonnam Gwangju Integrated Special City, President Lee Jae-myung instructed at the '2nd Joint Public-Private Inspection Meeting on Mega Projects' held at the Blue House the previous day, "The Ministry of National Defense should temporarily assign the functions of Gwangju Military Base to other military airports by mid-2028 to ensure early use of the Gwangju Military Airport site for the semiconductor industrial complex."

President Lee Jae-myung is speaking at the 2nd Public-Private Joint Inspection Meeting for Mega Projects held at the Blue House on the 10th. Photo by Yonhap News

President Lee Jae-myung is speaking at the 2nd Public-Private Joint Inspection Meeting for Mega Projects held at the Blue House on the 10th. Photo by Yonhap News

View original image

Kang Hoon-sik, chief presidential secretary, stated, "For the planned ammunition depot site, we will start preparations early and proactively refurbish the area so that if a company wishes, they can break ground for a semiconductor fab at the earliest possible time."


Traditionally, the site of the military airport can only be utilized after designating the relocation site and relocating all military facilities following the construction of a new military airport. If the relocation is delayed, the groundbreaking of the semiconductor industrial complex would inevitably be postponed as well.


The government has decided to begin with facilities that can be moved first, relocating them in phases, while temporarily assigning functions that are more difficult to relocate immediately to other military facilities. The land thus secured will be transformed into a semiconductor industrial complex as soon as it becomes available.

A panoramic view of Gwangju Military Airport, the planned site for the Honam region's semiconductor advanced national industrial complex. Provided by Jeonnam Gwangju Integrated Special City.

A panoramic view of Gwangju Military Airport, the planned site for the Honam region's semiconductor advanced national industrial complex. Provided by Jeonnam Gwangju Integrated Special City.

View original image

The first area to be developed is the ammunition depot within the military airport. Preparatory administrative procedures and site development will be carried out in advance, allowing the construction of a semiconductor fab to begin even before the complete relocation of the military airport.


The project operator, Korea Land and Housing Corporation (LH), is currently conducting research and design work. The government plans to sign tenancy agreements with semiconductor companies in October this year and pursue an exemption from the preliminary feasibility study for the industrial complex development project in November and December.


Next year, the goal is to complete the industrial complex master plan and design, while also beginning upgrades on a portion of the military airport site in order to launch construction of the first semiconductor fab. Essential infrastructure such as electricity and water will also be established by 2028.


The phased relocation of military facilities and their temporary reassignment is scheduled to be completed by the second half of 2028. The government will sequentially secure the necessary sites for the semiconductor industrial complex, carrying out the military airport relocation and industrial complex development concurrently, with the aim of completing the first phase of the fab by 2029 and achieving mass production by 2030.

Gwangju Military Airport, confirmed by the government as the site for the Honam Semiconductor Industrial Complex. Photo by Bohyun Song

Gwangju Military Airport, confirmed by the government as the site for the Honam Semiconductor Industrial Complex. Photo by Bohyun Song

View original image

However, there are numerous procedures that must still be addressed. Decisions have not yet been made regarding which military facilities will be dispersed, where they will go, or in what order ammunition depots and other facilities will be relocated. Coordination with the Ministry of National Defense and related agencies is required.


There are also facilities within the military airport that require consultation with the United States. If discussions with the U.S. side are delayed, this could also impact the overall timeline for the semiconductor industrial complex project. The government announced it will coordinate these discussions across all relevant ministries.



An official from Gwangju Special City stated, "The most significant aspect of the government’s policy is that it allows for earlier use of the site in accordance with semiconductor investment timelines, even before the formal completion of the military airport relocation process. The key factors are how extensively military facilities can be relocated or dispersed, and how much the construction schedule for the fab on the ammunition depot site can be accelerated."


This content was produced with the assistance of AI translation services.