Responding to AI-Driven Memory Demand,
Full-Scale Execution of Mid- to Long-Term Investment Plan
Yongin Second Fab to Open Cleanroom in June 2029
Cheongju "M17" to Open Cleanroom in December 2028

SK hynix has announced plans to invest a total of 54 trillion won to build large-scale new fabs in Yongin, Gyeonggi Province, and Cheongju, North Chungcheong Province, in order to meet the rapidly increasing demand for memory semiconductors in the era of artificial intelligence (AI).

Aerial view of Yongin Semiconductor Cluster. SK hynix

Aerial view of Yongin Semiconductor Cluster. SK hynix

View original image

On August 7, SK hynix revealed that, following a board resolution, it has decided to invest 35.2 trillion won in the second fab of the Yongin Semiconductor Cluster and 19.1 trillion won in 'M17' in Cheongju. This initiative is a full-fledged execution of the company's mid- to long-term investment strategy announced in June.


Among the four fabs that will be sequentially established at the Yongin Semiconductor Cluster, the second fab, Y2, will be developed as a production base dedicated to DRAM, featuring a total floor area of 341,000 pyeong. Groundbreaking is scheduled for July next year, with the first cleanroom opening planned for June 2029. The facility will focus on producing next-generation DRAM, including high bandwidth memory (HBM). The first fab (Y1), which is currently under construction, is on track to open its first cleanroom in February next year, paving the way for a connected production system. The investment will be executed through October 2031 and also includes the cost of support buildings equipped with staff work and welfare facilities, an integrated R&D center for experimental, testing, and analytical operations for developed products, as well as infrastructure such as water supply and power substations.

Perspective view of the M17 fab planned to be built by SK hynix in Cheongju. SK hynix

Perspective view of the M17 fab planned to be built by SK hynix in Cheongju. SK hynix

View original image

The Cheongju M17 plant, which will serve as a NAND flash production base, will be built with a total area of 206,000 pyeong. It is scheduled to break ground first in February next year, with its cleanroom set to open in December 2028. The investment will be executed in phases according to the business schedule through April 2031.


SK hynix explained, "We chose Cheongju as the new NAND production base because it enables us to construct the fab most quickly. M11, M12, and M15, which already produce NAND, are located at the Cheongju campus, making efficient production in conjunction with existing fabs possible. Additionally, much of the required land, power, and water supply has already been secured."


SK hynix expects this investment will not only establish a foundation for future growth but also strengthen the competitiveness of the domestic semiconductor ecosystem and revitalize local economies. The company stated, "This investment is a decision to seize opportunities at the pace of market growth, and by preemptively securing our production base, we aim to solidify our role as a core partner for the global AI semiconductor supply chain and contribute to stabilizing AI infrastructure."



The company further commented, "The simultaneous large-scale investments in both Yongin and Cheongju will broaden opportunities for our partners to grow together, create jobs, and boost local businesses, thereby contributing to the sustainable growth of the national economy."