[Mega Project Success Factors]②Water, Power, and Permits...Bold Acceleration Is the Answer
Urgent Need for New Dams and Securing Water Rights
Supplementary Power from Renewables and ESS Must Be Integrated
Managing Community Conflict over Industrial Wastewater Disposal Is a Critical Challenge
While the government and industry are accelerating efforts to establish a semiconductor cluster in the Honam region, several unresolved issues remain. These include securing a large supply of industrial water essential for fab operations, ensuring an uninterrupted 24-hour power grid, and challenges related to wastewater discharge and environmental impact assessments.
650,000 Tons of Industrial Water Per Day and Ultrapure Water...Where Will the Supply Come From?
Semiconductor manufacturing is often called a "water industry" due to the enormous volume of water required. In order to produce the highest purity "ultrapure water" for wafer cleaning, the source water quality and quantity must be stable and guaranteed.
In particular, the water burden of domestic semiconductor fabs is overwhelming compared even to global IT infrastructure such as artificial intelligence (AI) data centers. According to the 2026 sustainability report, last year Samsung Electronics and SK hynix recorded worldwide water intake volumes of 197.7 million tons (about 90% for semiconductors) and 117 million tons, respectively. These figures far exceeded the annual direct water intake of all Amazon global data centers (approximately 9.5 million tons). Unlike energy-intensive data centers, for semiconductor fabs, securing water sources and obtaining the necessary pipeline permits are considered the most critical limiting factors determining the success of these projects.
If four fabs are built in the southwestern region, the required industrial water could reach 600,000 to 650,000 tons per day. There are concerns that the existing major water systems in Honam, such as the Juam Dam and Gwangju Dam, will be insufficient to meet this demand. While the key for the Yongin cluster is delivering water from multiple sources—such as the Paldang Dam, Hwacheon Dam, and Yeoju Weir—in a timely manner, in the southwestern region, the challenge lies in securing water sources, building ultrapure water infrastructure, and obtaining the necessary water rights.
Changhan Lee, former Vice Chairman of the Korea Semiconductor Industry Association, commented, "Honam currently relies on water systems from Juam Dam and Gwangju Dam, but ultimately, to bring in more water, a new dam will have to be built." He emphasized that fundamental solutions—such as new dam construction—and calculations of costs in the trillion-won range must come first.
There are also warnings that water-related risks could delay the entire investment execution. Hyebin Cho, Senior Analyst at Kyobo Securities, said, "Given this is a government-led project, the likelihood of water supply itself being scrapped is low. However, negotiations to secure water sources, the start of pipeline construction, and approval for ultrapure and recycled water infrastructure could all be delayed, which would in turn push back fab operation rates and investment recovery timelines. The timing of water supply and the execution power for related permits are thus the leading variables for semiconductor facility investment."
"Uninterrupted 24-Hour Baseload Power Is Essential...Transition from Renewables Alone to a 'Nuclear Mix' Is Urgent"
Power supply is another major hurdle. Just one second of voltage drop or a blackout can cause semiconductor fabs to incur wafer losses amounting to billions of won, making 24/7 stable power supply absolutely critical. Although the southwestern region boasts the richest renewable energy resources in Korea, some argue that these should serve as supplementary sources, utilized in tandem with energy storage systems (ESS), rather than as the main energy supply.
Juhyun Moon, Professor of Energy Engineering at Dankook University, stressed, "A baseload power source that can supply electricity securely 24 hours a day, 365 days a year, must be the foundation." He added, "We need to rapidly pursue the continued operation of the currently inactive Yeonggwang nuclear plant and even consider building new nuclear plants in Honam to cover any shortfall." Sung-Hwan Kim, Minister of Climate, Energy and Environment, recently suggested combining six Hanbit nuclear units with regional renewables as the power source, and mentioned the possibility of building LNG power plants for semiconductor processes requiring heat and steam.
Younghwan Jeon, Professor in the School of Electronic and Electrical Engineering at Hongik University, explained, "The apparent lack of renewable energy infrastructure is mainly because Korea Electric Power Corporation (KEPCO) has withheld permits for new power generation projects due to a lack of large factories or metropolitan transmission networks to receive the electricity." He predicted that, "If a major semiconductor fab becomes an anchor demand, approval bottlenecks for new generation will break and, with KEPCO's system interconnection, power plants will be constructed sequentially." Adding the ongoing 3GW construction to the currently operating 3GW-scale LNG power infrastructure in the Yeosu, Suncheon, and Gwangyang areas would provide sufficient power capacity. Uninterrupted power needed to run four fabs is estimated at around 6.3GW—comparable to the output of 4.5 large nuclear reactors.
Military airport site in Gwangju, Jeonnam, selected as the site for the Honam semiconductor cluster. Photo by Yonhap News
View original imageWastewater Discharge and Conflicts with Local Governments and Residents: A 'Time Bomb'
Even if water and power are secured, handling large quantities of industrial wastewater could spark social conflicts with local governments and residents. Wastewater from semiconductor fabs contains not only chemicals and trace heavy metals but also hot water, so stringent water quality management and discharge strategies are mandatory.
The challenge lies in the environmental limitations of the southwestern water systems. Professor Moon noted, "Discharging wastewater into the sea causes relatively less pollution and ecological damage, but river discharge is much more problematic." He observed that, "Rivers in Honam have much lower flow than the Han or Nakdong rivers, so the environmental impact of wastewater discharge could be much greater."
Even if an alternative is pursued, such as constructing marine pipelines stretching dozens of kilometers to discharge wastewater into the South Sea, stakeholders will face thorny issues over who covers the construction cost and inevitable backlash from coastal fisheries cooperatives over infringement of fishing rights. Prioritization during severe droughts caused by climate change is also an outstanding question. Professor Moon pointed out, "In particular, when extreme droughts cause water shortages, securing local resident consent to prioritize semiconductor fabs for water allocation is an urgent challenge."
Yoonjong Lee, Invited Professor in the School of Electrical Engineering at KAIST, also remarked, "Wastewater treatment and permitting issues are not simply technical, but political and social matters tied to local sentiment. In regions with less experience in semiconductor industrial complexes, a greater gap between expectations and reality may make resolving community conflicts even more difficult than in previous cases like Yongin."
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
Previously, the Yongin semiconductor cluster also suffered delays of several years beyond the original schedule, due to late bidding for construction as well as conflicts between local governments over water and power line permits. An industry insider noted, "Workforce and logistics are relatively easier to resolve as location requirements for a semiconductor plant. However, water, electricity, and local government disputes are the key variables. In particular, securing and discharging water are issues that must account for droughts and competition with the water needs of residents and agriculture, making them extremely difficult to resolve in the short term."