Second Quarter Earnings Conference Call
5-Year LTA Execution with Global Big Tech Accelerates
Construction on Taylor Plant 2 to Begin This Year; 2nm Orders to Double
Denies U.S. Listing Speculation: "Not Under Review"

Samsung Electronics announced that it expects the shortage in memory semiconductor supply to continue through 2028, and that it is actively pushing ahead with long-term supply agreements (LTAs) with major customers. The company said sales of high-bandwidth memory (HBM)4 in the third quarter of this year are expected to more than triple compared to the previous quarter, signaling a rapid recovery of its leadership in HBM. Samsung Electronics also plans to comprehensively expand the supply of high-value-added products such as server SSDs.


On July 30, during its Q2 2026 earnings conference call, Samsung Electronics presented this market outlook as well as detailed strategies for its memory, foundry, and NAND flash business segments.


Samsung Electronics Seocho Building, Seocho-dong, Seocho-gu, Seoul. Photo by Dongju Yoon

Samsung Electronics Seocho Building, Seocho-dong, Seocho-gu, Seoul. Photo by Dongju Yoon

View original image

"Memory Shortage Until 2028... Five-year Long-term Contracts With Big Tech"

Samsung Electronics diagnosed that the structural supply shortage in the memory market will become prolonged. The company stated, "Even though the industry is expanding its capital expenditures (CAPEX), it takes more than three and a half years from new fab construction to wafer production, which means that expanding supply through capacity increases will inevitably require a significant amount of time," adding, "Given this, it will be difficult to expect a meaningful supply increase through 2028."


In particular, it explained that demand unmet this year is being carried over to next year, resulting in additional supply pressure. Samsung Electronics emphasized, "The supply shortage is expected to intensify further in 2027 compared to this year, and such shortages are forecast to persist into 2028."


As a result, requests from customers to secure long-term supply are surging. Samsung Electronics explained, "AI frontier model companies are sharing mid- to long-term demand forecasts and have begun to convey their direct intention to purchase from us, while simultaneously requesting multi-year supply contracts for significant additional supply." The company continued, "After securing cleanroom infrastructure through preemptive investment, we plan to more firmly apply our existing supply operation strategy, which entails flexibly introducing facilities depending on demand changes."


Currently, Samsung Electronics has entered LTAs with five major global data center customers and has nearly finalized negotiations with an additional five large customers. These multi-year contracts are generally for five years but employ a rolling mechanism where the term can be extended by one year annually through negotiation. To enhance the binding nature of the agreements, prepayment conditions have been included, and the company has already received about one quarter of the total prepayment amount. However, specific figures remain undisclosed due to confidentiality agreements with customers.


Samsung Electronics added, "In terms of flexibility in supply, we aim for long-term contracts to account for approximately 60-70% of the total, but there are multiple additional customers, and several of those with completed contracts are also requesting further supply."



HBM4 Sales Triple... Server SSD Share Surpasses 60%

In its core memory and NAND segments, Samsung Electronics is accelerating its shift toward premium products. HBM4 sales in the third quarter are expected to more than triple compared to the previous quarter, and in the second half of this year, HBM4 is projected to surpass 60% of the company's total HBM sales. With this, the company aims to attain a balanced DRAM portfolio by achieving parity between its overall DRAM market share and its HBM market share in the second half of 2026.


The NAND segment is also rapidly transforming into a high-value-added business, driven by the spread of agentic AI. The proportion of server solid-state drives (SSDs) in total NAND sales for this year is expected to exceed 60%, up more than 20 percentage points from last year. Samsung Electronics explained, "From the QLC perspective, after completing development of the V9 2-terabit QLC in March, we have expanded our lineup to include large-capacity products such as the 256TB server SSD, and bit shipments of QLC products are expected to more than double in the second half compared to the first half." The company added, "Looking ahead, we plan to begin mass production of V10 NAND, which adopts bonding and three-stack technology, in August."


In the foundry (semiconductor contract manufacturing) segment, momentum for advanced process orders is picking up. Samsung Electronics has secured orders for 2nm projects from major CSP (cloud service provider) and AI/HPC (high-performance computing) customers and begun the design phase, forecasting that the number of 2nm order projects in 2026 will more than double from the previous year. The company is also continuing to expand collaboration on new projects with major customers such as Broadcom.


Facility expansion to meet the growing demand for advanced processes is proceeding as planned. The first plant in Taylor, United States, is preparing for operation within this year. Construction on the second Taylor plant is scheduled to begin by the end of this year, with mass production targeted for 2030. Due to increasing customer inquiries for 1.4nm processes, Samsung Electronics is also considering the acquisition of additional fabs.


Denies U.S. ADR Listing Rumors... Bonus Accrual Reflected

Meanwhile, Samsung Electronics dismissed the recent market rumors about potentially issuing American Depositary Receipts (ADR) to list shares in the U.S. stock market. The company stated, "Our diversified business portfolio ensures robust cash generation, so there is little need for ADR issuance for new fundraising. Therefore, ADR issuance is not under consideration at this time." However, it left open the possibility of longer-term review from the perspective of enhancing mid- to long-term shareholder value.



Regarding the bonus accrual, the company explained, "In the first quarter, incentives were not reflected because the specific details were not yet finalized during ongoing negotiations. In the second quarter, however, we accrued special bonuses amounting to approximately 10.5% of operating profit for the first half of this year, reflecting six months' worth of bonuses in the first half."