Hwaseong National Road Construction Delayed 5 Years Due to Late Site Acquisition
Supreme Court: "Other Remedies Such as Contract Price Adjustment Are Available"

Even if construction is significantly delayed due to reasons attributable to the client, the contractor cannot claim "delay damages for work suspension" according to the contract, the Supreme Court has ruled. The Court emphasized that clauses pertaining to liquidated damages must be interpreted strictly, and that other remedies, such as contract price adjustments, are available.


Supreme Court, Seocho-gu, Seoul. Yonhap News Agency

Supreme Court, Seocho-gu, Seoul. Yonhap News Agency

View original image

According to the legal community on July 20, the Supreme Court's First Division (Presiding Justice Seo Kyunghwan) upheld the lower court's decision, which ruled against the plaintiffs in a lawsuit where construction companies sought additional construction payments from the client.


The construction companies had signed a contract for widening and paving the Hwaseong National Road in December 2009 and submitted a commencement report.


However, due to delays in site acquisition by the client, construction did not begin for more than five years. Actual work commenced only around August 2015 and was completed around June 30, 2021. Although the full contract sum was paid, the construction companies filed a lawsuit demanding additional compensation for the period of delayed commencement.


The dispute centered on whether the contract provision for "delay damages for work suspension" could be applied "in cases where commencement itself is delayed." The court of first instance accepted liability for compensation, but the court of appeal reversed the decision, ruling against the plaintiffs on the grounds that the clause does not apply to delays in commencement.



The Supreme Court also found the appellate court's decision to be correct. The panel stated, "The provision in question applies only in limited circumstances where the work is suspended after commencement," adding, "Even if there is a risk of loss due to delayed commencement, the contractor can request a contract price adjustment. Therefore, it cannot be concluded that this results in an unfairly disadvantageous outcome for the contractor." The appeal was dismissed.